Article 5
Decision 21/2002/QĐ-BCN — Về việc ban hành Quy định nội dung, trình tự và thủ tục quy hoạch phát triển điện lực
The order and procedures for compilation of blueprint and registration of capital for the elaboration of electricity development plannings shall be as follows:
1. For the national electricity development planning:
For each 5-year cycle, the Ministry of Industry shall approve the cost estimate blueprints and register the State budget capital plans according to current regulations
2. For the plannings on electricity development in the provinces and centrally-run cities:
For each 5-year-cycle, the provincial/municipal Industry Services shall work out and submit the cost estimate blueprints to the provincial/municipal People’s Committees for approval, and register the State budget capital plans for the elaboration of the provincial electricity development plannings according to current regulations.
3. For the district electricity development plannings:
For each 5-year cycle, the provincial/municipal Industry Services shall, based on the demand for electricity development in each region, work out the blueprints and cost estimates for the planning activities and submit them to the provincial/municipal People’s Committees for the latter to approve and apportion the local budget capital therefor according to the current regulations.
4. The unit price for the elaboration and funding for the appraisal of the electricity development plannings shall comply with the current regulations.
Article 5, Decision 21/2002/QĐ-BCN