Article 41. Rights and obligations of work construction investors in the formulation of work construction investment projects
Law 16/2003/QH11 — Luật Xây dựng số 16/2003/QH11
1. Work construction investors shall have the following rights in the formulation of work construction investment projects:
a/ To formulate work construction investment projects by themselves when they satisfy the conditions for doing so;
b/ To negotiate, sign and supervise the performance of contracts;
c/ To request the concerned organizations to supply information and documents in service of the formulation of work construction investment projects;
d/ To suspend the performance of, or terminate contracts when the contractors for project formulation consultancy breach the contracts;
e/ Other rights provided for by law.
2. Work construction investors shall have the following obligations in the formulation of work construction investment projects:
a/ To hire consultants to formulate projects in cases where they fail to fully satisfy the conditions on capability to formulate work construction investment projects by themselves;
b/ To determine contents of tasks of work construction investment projects;
c/ To supply information and documents related to work construction investment projects to work construction investment project formulation consultants.
d/ To organize the pre-acceptance test, evaluation and approval of work construction investment projects according to their competence or submit them to the competent authorities for evaluation and approval;
e/ To properly perform the already signed contracts;
f/ To archive dossiers of work construction investment projects;
g/ To make compensations for damage caused by the use of consultants unsuitable to the capability to formulate work construction investment projects or supply of untruthful information; evaluation and pre-acceptance test not in compliance with the regulations and other acts of violation causing damage due to their faults.
h/ Other obligations provided for by law.
Article 41, Law 16/2003/QH11