Article 40. Adjustment of work construction investment projects
Law 16/2003/QH11 — Luật Xây dựng số 16/2003/QH11
1. The already approved work construction investment projects shall be adjusted in one of the following cases:
a/ Natural calamities, enemy sabotage or force majeure circumstances occur;
b/ There appear factors which may bring about higher efficiency;
c/ The construction planning changes.
2. Adjusted contents of work construction investment projects must be permitted by the investment deciders and must be re-evaluated. Persons deciding on adjustment of work construction investment projects shall be held responsible before law for their decisions.