Article 21. Conclusions and recommendations
Circular 86/2015/TT-BGTVT — Hướng dẫn chi tiết về lĩnh vực đầu tư và nội dung báo cáo nghiên cứu khả thi dự án đầu tư theo hình thức đối tác công tư thuộc lĩnh vực giao thông vận tải.
Contents of feasibility study reports
1. In the section of conclusions, to briefly present the principal contents of the project’s feasibility study report, at least including:
a/ Project name; name of the competent state agency; name of the project-preparing unit or proposing investor;
b/ Project implementation location and land use area (if any);
c/ Size of project and principal technical standards;
d/ Total investment capital and level (clarification of the State’s support capital, if any);
dd/ Type of project contract and time of project contract (expected schedule of project implementation and operation and use duration);
e/ Financial targets of the project (input and output parameters);
g/ Other contents.
2. In the section of recommendations, to make recommendations and proposals (if any).