Article 19. Analysis of project risks and proposals on investment incentives and assurance
Circular 86/2015/TT-BGTVT — Hướng dẫn chi tiết về lĩnh vực đầu tư và nội dung báo cáo nghiên cứu khả thi dự án đầu tư theo hình thức đối tác công tư thuộc lĩnh vực giao thông vận tải.
Contents of feasibility study reports
1. To determine major risks of the project and assess impacts on the project in cases where risks occur in order to propose the optimal division of risks to competent state agencies and investors, and at the same time propose measures to minimize risks and responsibility of parties for risks management during the project implementation. These contents shall be tabulated to sum up the project risks, including:
a/ To systematically identify such major risks of the project as legal risks; social risks; environmental risks; engineering, construction and production risks; risks in work construction and completion costs; financial risks; macroeconomic risks; market demand risks; operational risks; contract termination risks and other risks (if any);
b/ To describe major risks of the project and at the same time analyze the possibility of such risks as well as their influence on the project (in terms of cost, implementation progress, design change and capital allocation, etc.); to assess financial impacts on the project in case risks occur, and in case of necessity, to experiment different plans in the financial model to assess such impacts;
c/ Based on specific technical, economic and financial conditions of the project, the financial analysis results must assess impacts of risks on the project as well as costs and advantages of measures to minimize risks. A feasibility study report must clarify the expected division of risks and responsibility of parties to manage risks during the project implementation; and propose specific supports of competent state agencies and mechanism of risk sharing between competent state agencies and investors.
2. Based on the assessment of project risks and current financial market developments in the country and the world, to explain in detail proposals on the Government’s investment incentives and investment guarantee and assurance forms specified in Chapter IX of Decree No. 15/2015/ND-CP, and accompanying requirements as well as necessary contingency obligations during the project implementation.
3. To explain in detail handling plans in case the actual revenues of the project are much different from estimated revenues, and forecasts for shortening the duration of capital retrieval through charge collection.
Article 19, Circular 86/2015/TT-BGTVT