Article 15. Total investment level, total investment capital and financial plans
Circular 86/2015/TT-BGTVT — Hướng dẫn chi tiết về lĩnh vực đầu tư và nội dung báo cáo nghiên cứu khả thi dự án đầu tư theo hình thức đối tác công tư thuộc lĩnh vực giao thông vận tải.
Contents of feasibility study reports
1. Total investment level shall be fully determined, ensuring its accuracy in compliance with the law on management of construction costs and Decree No. 15/2015/ND-CP, and calculating and clarifying the following:
a/ The minimum equity, loans and the State’s investment capital in the implementation of the project (if any);
b/ Contingency and loan interest expenses to be paid in the course of construction which shall be determined on the basis of disbursement progress in conformity with the protect implementation progress (cash flow in the project implementation shall be determined).
2. The total investment capital shall be fully determined, ensuring its accuracy in compliance with Decree No. 15/2015/ND-CP and other relevant regulations, and calculating and clarifying the following:
a/ The minimum equity and loans;
b/ The basis for, and necessity of, calculating expenses related to initial working capital for the project operation.
3. A financial plan must present at least the following:
a/ Sufficient bases for identifying parameters of the project financial model; and on that basis, to calculate and assess the financial feasibility and loan-borrowing ability of the project and determine the duration of capital retrieval and profit generation;
b/ Detailed explanation of expenses in the financial model: the total investment capital of the project enclosed with the project financial plan (the plan to mobilize capital for the project), expected interest rate, loan-borrowing conditions and other expenses;
c/ Project revenues: details about prices and charge rates expected to be applied according to the type of the project contract, common prices and charge rates and current regulations, and at the same time based on demand analysis and forecast results prescribed at Point b, Clause 2, Article 7 of this Circular to explain and produce in detail different scenarios on project revenues (at the fundamental, minimum and maximum levels);
d/ To analyze sensitivity appropriate to input factors of the financial model (including analysis in case optimal and minimal financial plans are available);
dd/ To analyze in detail output parameters of the financial model to ensure the ability to get loans of the project, at least including: loan to equity ratio; debt service coverage ratio (DSCR); net profit to minimum equity ratio or equity internal rate of return; financial internal rate of return (FIRR); financial net present value (FNPV) and time of capital recovery.
4. In case a project requires the State’s investment capital to increase its feasibility, to base on the financial model and results of analysis of the financial model of the project to explain in detail the contents related to the State’s investment capital for implementation of such project, including:
a/ The necessity to have the State’s investment capital for implementation of the project;
b/ Determination of the maximum value and capital allocation ability; disbursement method, plan and schedule of the investor;
c/ Such requirements on the State’s investment capital for project implementation as different plans and selected plan, value, proposed instruments, and disbursement and payment mechanisms;
d/ For investment projects in the form of PPP implemented under build-transfer-lease or build-lease-transfer contracts: the State’s investment capital portion which shall be paid to service-providing investors and the annual capital allocation ability.
Article 15, Circular 86/2015/TT-BGTVT