Article 13. Project schedule and project contract implementation duration
Circular 86/2015/TT-BGTVT — Hướng dẫn chi tiết về lĩnh vực đầu tư và nội dung báo cáo nghiên cứu khả thi dự án đầu tư theo hình thức đối tác công tư thuộc lĩnh vực giao thông vận tải.
Contents of feasibility study reports
1. To present a general plan on project implementation (scheduling the project implementation), specifying time of commencing and time of completing main jobs of the project, including making of the feasibility study report, approval of project investment, bidding for investor selection, signing of the project contract, construction stage, operation stage, time limit for transfer, and other time limits (if any). The plan must suit the reality to ensure the progress of project implementation.
2. For projects having construction components: to make a general construction schedule o based on the construction volume, topographic and geological conditions and weather characteristics of the project location so as to determine the project implementation duration, calculate costs and allocate investment capital.
3. Project commercial operation duration is determined from the date project works are commissioned or handed over from the management agency (for projects implemented under O&M contracts) to the date of expiration of the project commercial operation duration according to the financial plan. This duration must be counted in days.
Article 13, Circular 86/2015/TT-BGTVT