Article 26. Contents of evaluation of a project upon completion
Circular 09/2016/TT-BKHĐT — Hướng dẫn về công tác theo dõi, kiểm tra và đánh giá đầu tư đối với hoạt động đầu tư nước ngoài tại Việt Nam.
Evaluation of foreign investment
1. Progress of contribution of charter capital by the economic organization, or legal capital (for business lines required to have legal capital), or investment capital, of the project; raising of capital and use of raised capital under law; and payment during the project implementation.
2. Project implementation progress against the schedule stated in the written approval of investment policy or in the investment registration certificate, and against the schedule stated in the submitted dossier of request for grant or modification of the investment registration certificate.
3. Use of land and employment of workers under the project; observance of the law on environmental protection.
4. Fulfillment of financial obligations toward the State (payment of taxes, charges, fees, land rental, water surface rent, etc.).
5. Achievement of set objectives, use of mobilized resources, implementation progress, and project benefits.
6. Proposals and recommendations.