Article 31. Rights and obligations of the EPC contractor
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Rights of the EPC contractor:
a) To request the principal to provide information, documents and working equipment (if so agreed upon in the contract) for the performance of jobs of the contract according to the signed contract:
b) To propose to the principal jobs arising outside the signed contract: to refuse to perform jobs outside the signed contract not yet agreed upon by the two parties or unlawful requests of the principal:
c) To organize and manage the performance of jobs under the signed contract:
d) Other rights provided by law.
2. Obligations of the EPC contractor:
a) To provide sufficient workforce, materials, machines, equipment and other necessary facilities for the performance of jobs under the contract;
b) To receive, manage, preserve and return documents and facilities provided by the principal (if so agreed upon in the contract);
c) To notify the principal of insufficient information and documents or poor-quality working facilities which affect the performance of jobs under the signed contract;
d) To keep confidential information related to the contract as agreed upon in the contract or provided by law:
e) To perform jobs under the contract, assuring safety and quality, according to the set schedule and other agreements in the contract:
f) To make designs (technical designs and construction drawing designs) of work items and major works of the bid package and project in conformity with approved basic designs or FEED designs and submit them to the investor for appraisal and approval:
g) To organize the procurement, manufacture and provision of technological equipment to meet requirements and performance progress of the contract; to select sub-contractors (if any) through bidding or appointment, then propose them to the investor for approval: to reach agreement with the investor on contents of the bidding dossier for procurement of technological equipment (if so agreed upon in the contract):
h) To train managerial staff and workers to operate and use the work, and transfer technologies and accompanying technical services (if so agreed upon in the contract):
i) To perform jobs of testing, adjustment and test operation of the whole work and hand over the completed work to the principal as agreed upon in the contract and provided by current law;
j) To guarantee that products it provides do not infringe upon intellectual property rights under law;
k) To hand over dossiers and documents related to products of the contract to the principal under the signed contract:
l) Other obligations provided by law.
Article 31, Decree 48/2010/NĐ-CP