Article 30. Rights and obligations of the EPC principal
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Rights of the EPC principal:
a) To refuse to take over products not up to the quality standard agreed upon in the contract and technological equipment not according to the agreement on quantity, quality, category and origin and products infringing upon intellectual property rights:
b) To inspect the performance of jobs by the contractor according to the signed contract without impeding the contractor's normal operation:
c) To cease the performance of jobs under the contract and request the remedying of consequences upon detecting that the contractor performs these jobs in violation of the agreements in the signed contract or the State's regulations:
d) To request the contractor to hand over dossiers and documents related to products of the contract according to the signed contract:
e) To consider and approve the list of subcontractors that are fully qualified but not yet named in the EPC contract at the request of the contractor:
f) Other rights provided by law.
2. Obligations of the EPC principal:
a) To pay to the contractor according to the payment schedule agreed upon in the contract:
b) To assign its persons to participate in managing and performing the contract and notify in writing the contractor of these persons:
c) To provide to the contractor information, documents and facilities necessary for job performance (if so agreed upon in the contract):
d) To promptly conduct takeover test, appraise and approve technical designs and construction drawing designs of works and work items under regulations;
e) To apply for a construction license under regulations, and hand over clear grounds to the contractor according to the contract performance schedule:
f) To supervise the performance of jobs according to the signed contract: to inspect measures to assure labor safety, environmental protection, fire and explosion prevention and combat under regulations;
g) To reach agreement with the contractor on the bidding dossier for procurement of technological equipment (if so agreed upon in the contract):
h) To conduct takeover test and make payment and settlement of the contract according to the set schedule:
i) To guarantee the copyright to consultancy products under the contract:
j) To organize the training of managerial staff and workers to operate and use the work;
k) Other obligations provided by law.
Article 30, Decree 48/2010/NĐ-CP