Article 43. Tasks and powers of project management units in program and project implementation management
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Management of implementation of
1. The tasks and powers of a project management unit shall be assigned by the project owner in the decision to establish the project management unit.
The project owner may authorize the project management unit to decide or sign documents within the former’s competence in the course of management of the program or project implementation. This authorization shall be stated in the decision to establish the project management unit or in a specific authorization document issued by the project owner.
2. A project management unit may be assigned to manage many programs or projects, but such shall be approved by the project owner and ensure the following principles: Each program or project is not interrupted, and is managed and financially settled in accordance with current laws. If a project management unit lacks conditions for performing certain management and supervision tasks, it may hire consultants to perform these tasks with the approval of the project owner.
3. A project management unit shall perform the tasks assigned by the project owner and report to the project owner, including:
a/ Making a master plan and annual plans on program and project implementation;
b/ Preparing for and implementing programs and projects;
c/ Carrying out bidding activities, contract management, and compensation, support and resettlement work;
d/ Disbursing funds for and managing finance and assets of programs and projects;
dd/ Monitoring and evaluating the program and project implementation;
e/ Preparing for acceptance and handover of output results of programs and projects after completion; finishing audit work, handing over assets of programs and projects; making completion reports and finalization reports of programs and projects; and implementing project closure according to treaties or agreements on ODA or concessional loans for programs and projects;
g/ Performing other tasks in the program or project framework assigned by the project owner.
4. To perform other tasks and powers as prescribed by law and specific treaties or agreements on ODA or concessional loans for programs and projects.
5. To take responsibility before law and managing agencies within the limit of their rights and obligations prescribed in this Decree and relevant laws.
Article 43, Decree 16/2016/NĐ-CP