Article 42. Tasks and powers of project owners in program and project implementation management
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Management of implementation of
1. To organize an apparatus for program and project management and implementation on the basis of decisions of the managing agencies.
2. To take responsibility for management and efficient use of ODA or concessional loans and counterpart fund of programs or projects from the time of preparation and implementation to the time of putting programs or projects into operation or use.
3. To draw up and submit to the managing agencies for approval 5-year medium-term plans, master plans and annual plans for program and project implementation; to draw up and approve annual plans on counterpart fund, for programs and projects funded by loans wholly or partially onlent from the state budget and counterpart fund arranged by the project owners themselves.
4. To draw up action plans for each quarter in order to serve the administration, supervision and evaluation of programs and projects.
5. To perform bidding work in accordance with current bidding law.
6. To negotiate and conclude, and supervise the performance of, contracts and handle problems according to their competence.
7. To coordinate with local administrations in carrying out compensation, support and resettlement work as prescribed by law and specific treaties on ODA or concessional loans for programs and projects (for construction investment projects).
8. To supervise and evaluate programs and projects in accordance with the law on public investment supervision and evaluation and this Decree, aiming to ensure that programs and projects are implemented on schedule, with quality and achieve set objectives.
9. To direct the project management units to make completion reports and settlement reports for programs and projects; to audit and hand over output assets and documents of programs and projects, and comply with provisions on project closure in treaties or agreements on ODA or concessional loans for programs and projects.
10. To take responsibility for loss, waste, corruption, wrongdoings and violations falling within their competence in the program and project management and implementation causing economic, social or environmental damage and affecting the objectives and overall effectiveness of programs and projects.
11. For programs or projects funded by loans wholly or partially onlent from the state budget, to repay fully and timely the onlent loans under the onlending conditions signed with competent financial agencies and banks.
12. To perform other tasks and powers as prescribed by law and specific treaties or agreements on ODA or concessional loans for programs or projects.
13. To take responsibility before law and managing agencies within the limit of their rights and obligations prescribed in this Decree and relevant laws.
Article 42, Decree 16/2016/NĐ-CP