Article 20. Order and procedures for issuance of underground water-exploitation and -use permits
Decree 149/2004/NĐ-CP — Quy định việc cấp phép thăm dò, khai thác, sử dụng tài nguyên nước,xả nước thải vào nguồn nước
1. Organizations and individuals applying for underground water-exploitation and use permits shall submit two (2) dossier sets at the dossier-receiving agencies defined in Article 14 of this Decree. Such a dossier includes:
a/ The application for permit;
b/ The underground water-exploitation scheme;
c/ The map of the area and position of the underground water-exploitation project, of 1/50,000- 1/25,000 scale;
d/ The report on the results of exploration and evaluation of underground water deposit, for projects with the flow of 200 m3/day and night; the report on the results of construction of exploitation wells, for projects with the flow of under 200 m3/day and night; the report on the current exploitation situation of operating underground water-exploitation projects;
e/ The results of analysis of the quality of water sources for use purposes according to the State's regulations at the time of application for the permit;
f/ The notarized copies of the certificate or valid papers on the right to use land where exploitation well(s) is (are) located, according to the Land Law's provisions. In cases where the exploitation well land falls beyond the land use right of the applying organization or individual, there must be a written land-use agreement between the exploiting organization or individual and the organization or individual having the land use right, which must be certified by the competent People's Committee.
2. The permit-issuing order is provided for as follows:
a/ Within five (5) working days after receiving dossiers, the dossier-receiving agencies shall have to consider and examine them; in cases where the dossiers are invalid, the dossier-receiving agencies shall notify such to the applying organizations or individuals for dossier completion according to regulations;
b/ In cases where exploitation wells are already available, within fifteen (15) working days after receiving complete and valid dossiers as prescribed in Clause 1 of this Article, the dossier-receiving agencies shall have to evaluate the dossiers, conduct field inspection when necessary and, if obtaining enough permit-issuance grounds, submit the dossiers to competent agencies for issuance of permits; in cases where the permit-issuance conditions are not fully met, the dossier-receiving agencies shall return the dossiers to the applying organizations or individuals and notify the latter of the reasons for non-issuance of permits.
c/ In cases where exploitation wells are not yet available, within ten (10) working days after receiving complete and valid dossiers as prescribed in Clause 1 of this Article, the dossier-receiving agencies shall have to evaluate the dossiers and submit them to competent agencies for issuance of documents permitting the construction of exploitation wells. Within fifteen (15) working days after receiving complete documents on exploitation-well construction, the dossier-receiving agencies shall have to evaluate the dossiers, conduct field inspection when necessary and, if obtaining enough permit-issuance grounds, submit the dossiers to competent agencies for issuance of permits; in cases where the permit-issuance conditions are not fully met, the dossier-receiving agencies shall return the dossiers to the applying organizations or individuals and notify the latter of the reasons for non-issuance of permits.
Article 20, Decree 149/2004/NĐ-CP