Article 31. Execution of investment projects, construction of works
Law 48/2005/QH11 — Luật Thực hành tiết kiệm, chống lãng phí số 48/2005/QH11
1. Investment projects shall be executed only after they are approved by competent state bodies and works shall be constructed only after the investment projects are approved and adequate capital sources are ensured according to construction tempo. The approved investment projects which are not included in plannings or plans, fail to satisfy the prescribed conditions or to comply with the investment process and procedures shall be suspended or cancelled.
2. The ground clearance for execution of construction investment projects must ensure the project execution schedule. The compensation, support and resettlement upon recovery of land by the State for execution of construction investment projects must be publicized, objective, fair and lawful. Acts of violating the provisions of law on compensation, support and resettlement upon land recovery by the State and acts of obstructing, causing difficulties to, slowing down the ground clearance are strictly prohibited.
3. The work construction must strictly comply with construction designs, norms and standards and the approved construction schedule. Investors and project owners shall have to inspect and request contractors to observe the construction schedule, to construct works in accordance with designs, to use raw materials and materials according to the set quality standards and technical requirements, ensuring the work quality and construction progress.
4. Consultancy organizations supervising construction shall have to fulfill their commitments to investors and project owners; detect and prevent in time negative acts, causing waste in construction process. They are strictly forbidden to collude with investors, project owners and/or contractors for illicit profits, thus reducing the quality of works.
5. Investors, project owners must test, accept and settle works according to regulations, must not change at their own will the approved designs, work estimates or bid-wining prices.
6. Agencies, organizations, heads of agencies or organizations being assigned to act as investors or project owners and relevant persons, that violate the provisions of Clauses 1, 2, 3, 4 and 5 of this Article, thus causing waste, shall have to pay compensations and administratively sanctioned or disciplined.
Article 31, Law 48/2005/QH11