Article 2
Law 38/2009/QH12 — Luật Sửa đổi, bổ sung một số điều của các luật liên quan đến đầu tư xây dựng cơ bản số 38/2009/QH12
To amend and supplement a number of articles of the Bidding Law.
1. To amend and supplement Clauses 30 and 39, Article 4 as follows:
"30. Evaluation price means a price determined on the same ground of technical, financial and commercial elements and shall be used for comparing and rating bids with regard to procurement, construction and installation or EPC bidding packages. Evaluation prices cover bid prices proposed by contractors to undertake bidding packages after correcting errors and necessary expenses for operation and maintenance and other expenses related to the progress, quality or origin of goods or works within bidding packages through their use duration."
"39. Bidding appraisal means the inspection and assessment of bidding plans, bidding dossiers and contractor selection results by agencies or organizations with the appraising function, which serves as a basis for competent persons or investors to consider and make decision in accordance with this Law. The appraisal of contractor selection results does not mean re-assessment of bids."
2. To amend and supplement Article 11 as follows:
"Article 11. Assurance of competitiveness in bidding
1. Contractors participating in bidding for bidding packages under projects specified in Article 1 of this Law must satisfy the following requirements on competitiveness:
a/ The bidding contractor must be organizationally independent and not dependent on the same managing agency of and be financially independent from the contractor providing consultancy on making bidding dossiers and assessing bids;
b/ The contractor providing supervision consultancy on contract performance must be organizationally independent from and not dependent on the same managing agency of and be financially independent from the contract-performing contractor;
c/ The contractor participating in bidding for bidding packages under a project must be organizationally independent from and not dependent on the same managing agency of and be financially independent from the project investor.
2. The Government shall specify assurance of competitiveness in bidding."
3. To add the following Clauses 18 and 19 to Article 12:
"18. The bid solicitor's failure to sell bidding dossiers to contractors within the time limit specified in bid invitation notices or bid invitation letters.
19. Employing foreign laborers while local laborers are capable of and satisfy requirements for performing bidding packages."
4. To amend and supplement Points c and e, Clause 1, and Clause 3, Article 20 as follows:
"1. Contractor designation is applicable to the following:
c/ Bidding packages classified as national secrets: bidding packages under urgent projects in the national interests:
e/ Bidding packages valued within the limit permitted for contractor designation or having other special requirements as prescribed by the Government."
"3. Before designating contractors for bidding packages specified at Points b, c. d and e. Clause 1 of this Article, cost estimates for these bidding packages must be approved in accordance with law; for bidding packages specified at Point e. contractor designation must also be more effective than bidding."
5. To amend and supplement Clauses 1 and 3, Article 29 as follows:
"1. Bid-evaluating methods must be reflected through evaluation criteria in bidding dossiers. Bid-evaluating criteria include criteria for evaluating capability and experience in case pre-qualification selection is not applied: criteria for technical evaluation; criteria for general evaluation of consultancy service bidding packages or contents for determining evaluation prices on the same technical, financial and commercial grounds in order to compare and rate bids for procurement, construction and installation or EPC bidding packages."
"3. For procurement, construction and installation and EPC bidding packages, the marking method or method of evaluation using the "satisfactory" or "unsatisfactory" criterion will be applied for technical evaluation. When formulating technical evaluation criteria in the form of a point scale, prescribed minimum technical requirements must not be lower than 70% of total technical points, or not lower than 80%. for bidding packages with high technical requirements. Bids which have passed technical evaluation shall be compared and rated based on evaluation prices on the same technical, financial and commercial grounds. The bid of a contractor having the lowest evaluation price on the same ground will be ranked first.
The Government shall specify the evaluation of bids."
6. To amend and supplement Clause 5, Article 31 as follows:
"5. The maximum duration for evaluating a bid is forty five days, for domestic bidding, or sixty days, for international bidding, from the bid-opening date to the date the bid solicitor submits bidding results to the investor for approval."
7. To amend and supplement Point a, Clause 1, Article 32 as follows:
"a/ Based on the nature and size of a bidding package, the pre-qualification selection of contractors shall be conducted before an open bidding is organized in order to select fully capable and experienced contractors as required by the bidding package to participate in the bidding."
8. To amend and supplement Clause 2, Article 33 as follows:
"2. Receipt and management of bids
Bid solicitors shall receive and manage bids submitted as required by bidding dossiers under regulations on management of "secret" dossiers. Bids submitted after the bid closing will be regarded as improper and shall be rejected."
9. To amend and supplement Point b, Clause 2, Article 35 as follows:
"b/ For procurement, construction and installation or EPC bidding packages, evaluation prices on the same technical, financial and commercial grounds shall be determined to compare and rate bids. For consultancy service bidding packages, general evaluation shall be conducted to compare and rate bids: particularly, consultancy service bidding packages with high technical requirements, financial proposals of the contractors technically ranked first shall be considered."
10. To amend and supplement Clause 4, Article 38 as follows:
"4. Offering the lowest evaluation price on the same ground;"
11. To amend and supplement Article 39 as follows:
"Article 39. Submission of bidding results for approval and appraisal
1. The bid solicitor shall make a report on bidding results and submit it to the investor for consideration, decision and further sending to a responsible agency or organization for appraisal.
2. The appraising agency or organization shall, based on the bid solicitor's report, make an evaluation report on bidding results and submit it to the investor for consideration and decision."
12. To amend and supplement Clause 1, Article 40 as follows:
"1. Investors shall consider and approve bidding results on the basis of reports on bidding results and evaluation reports on bidding results."
13. To amend and supplement Clause 1, Article 41 as follows:
"1. Bidding results shall be announced right after obtaining investors' decisions approving bidding results."
14. To amend and supplement Clause 3, Article 42 as follows:
"3. In case of unsuccessful negotiation and finalization of a contract, the investor shall consider and select next-ranked contractors. If the next-ranked contractors still fail to meet requirements, the case shall be considered and handled under regulations."
15. To amend and supplement Clause 2, Article 43 as follows:
"2. Based on investors' decisions, bid solicitors shall notify bidding contractors of the cancellation of bidding."
16. To amend and supplement Article 46 as follows:
"Article 46. Contract formulation principles
1. A contract must be formulated in accordance with this Law and other relevant laws.
2. For contractors forming a partnership, the contract signed with the investor must be signed by all partners.
3. The contractual price must not exceed the winning bid price."
17. To amend and supplement Clauses 2 and 3, Article 57 as follows:
"2. The adjustment of a signed contract may be made only in the contract performance duration and must be considered and decided by the investor. The adjusted contractual price must not result in an increase in the approved total investment, unless it is permitted by a person with investment-deciding competence.
3. In case reasonable jobs arising beyond those indicated in a contract do not result in a change in the investment objective or total investment, the investor shall reach agreement with the contractor that has signed the contract on additionally calculating arising jobs and sign a contract annex. If they cannot reach such agreement, those arising jobs will constitute a new biding package for which contractors shall be selected in accordance with this Law."
18. To amend and supplement Article 60 as follows:
"Article 60. Responsibilities of competent persons
1. To decide on forms of contractor selection, including contractor designation specified in Clause 1, Article 20 of this Law.
2. To approve bidding plans.
3. To settle petitions related to bidding.
4. To handle violations of the bidding law in accordance with Article 15 of this Law and other relevant laws.
5. To cancel or terminate biddings or refuse to recognize contractor selection results upon detecting acts of violating the bidding law or other relevant laws.
6. To lake responsibility before law for their decisions."
19. To add the following Clauses 13,14 and 15 to Article 61:
"13. To approve bidding dossiers.
14. To approve contractor selection results.
15. To decide on the handling of bidding circumstances."
20. To amend and supplement Point c, Clause 1, Article 70 as follows:
"c/ Investors shall decide on the handling of bidding circumstances and take responsibility before law for their decisions."
21. To amend and supplement Points a and c, Clause 1, Article 75 as follows:
"a/ Caution shall be imposed on organizations and individuals that violate this Law. except cases specified in Article 12 of this Law; successful bidders that intentionally fail to negotiate and finalize contracts or have negotiated and finalized contracts but do not sign them; contractors that have signed contracts but intentionally fail to perform part or the whole of the contracts; or contractors that perform consultancy service, procurement, construction and installation or EPC bidding packages but fail to ensure their quality and progress as agreed in the contracts;"
"c/ Organizations and individuals that violate Article 12 of this Law or have committed three or more acts of violation and been cautioned under Point a of this Clause shall be banned from participation in bidding activities."
Article 2, Law 38/2009/QH12