Article 296. Extension of time limit for performance of contracts, or refusal to perform contracts in force majeure circumstances
Law 36/2005/QH11 — Luật Thương mại số 36/2005/QH11
1. In a force majeure circumstance, the parties may agree to extend the time limit for performing their respective contractual obligations. If the parties do not agree or cannot agree upon such extension, the time limit for performing contractual obligations shall be extended for a period of time equal to the time length of such force majeure circumstance plus a reasonable period of time for remedying consequences, but not exceeding:
a/ Five months for goods or services for which the agreed time limit for their delivery or provision does not exceed twelve months from the date the contract is entered into;
b/ Eight months for goods or services for which the agreed time limit for their delivery or provision exceeds twelve months from the date the contract is entered into.
2. Beyond the time limits specified in Clause 1 of this Article, the parties may refuse to perform the contract and neither party is entitled to request the other party to pay damages.
3. Where a party refuses to perform a contract, it must, within ten days from the expiry date of the time limit specified in Clause 1 of this Article, notify the other party thereof before the latter begins to perform its contractual obligations.
4. The extension of the time limit for performing contractual obligations mentioned in Clause 1 of this Article does not apply to contracts for purchase and sale of goods or contracts for provision of services with fixed time limit for goods delivery or service completion.