Article 80. Pre-acceptance test and hand-over of construction works
Law 16/2003/QH11 — Luật Xây dựng số 16/2003/QH11
1. The pre-acceptance test of construction works must comply with the following regulations:
a/ Regulations on management of quality of construction works;
b/ Pre-acceptance test shall be made upon each job, each part, each stage and each work item and pre-acceptance test for putting works into use. Particularly for hidden parts of works, the pre-acceptance test and construction completion drawings must be made before the subsequent jobs are carried out;
c/ Pre-acceptance test shall be made only when the to be-tested objects are completed and the dossiers thereon are complete;
d/ Works shall be put into pre-acceptance test for use only when they satisfy the design requirements, ensure the quality and are up to the prescribed standards.
2. The hand-over of construction works must comply with the following regulations:
a/ Satisfying the requirements on principles, contents and order for handing over completed construction works for being put into use according to the provisions of construction legislation;
b/ Ensuring safety in the operation and exploitation when the works are put into use.
3. The work construction contractors shall have to finish the construction, clear the construction sites, make construction completion drawings and prepare documents in service of the pre-acceptance test and hand-over of the works.
4. The work construction investors shall have to organize the pre-acceptance test and reception of works. Persons taking part in the pre-acceptance test and hand-over of works shall bear personal responsibility for products certified by them in the course of work construction and work hand-over.
Article 80, Law 16/2003/QH11