Circular 96/2000/TT-BTC
Guiding the management and payment of investment capital and public-service capital of investment and construction nature belonging to the State budget’s capital source
- Public finance
- Investment
- Repealed
English translation (unofficial)
THE MINISTRY OF FINANCE
THE MINISTRY OF FINANCE
CIRCULAR No. 96/2000/TT-BTC OF SEPTEMBER 28, 2000 GUIDING THE MANAGEMENT AND PAYMENT OF INVESTMENT CAPITAL AND PUBLIC-SERVICE CAPITAL OF INVESTMENT AND CONSTRUCTION NATURE BELONGING TO THE STATE BUDGET’S CAPITAL SOURCE
Pursuant to the State Budget Law promulgated on March 20, 1996 and the Government’s Decree No. 87/CP of December 19, 1996 detailing the division of responsibilities for managing, drafting, implementing and settling the State budget;
Pursuant to the Government’s Decree No. 52/1999/ND-CP of July 8, 1999 issuing the Investment and Construction Management Regulation and Decree No. 12/2000/ND-CP of May 5, 2000 amending and supplementing a number of articles of the Investment and Construction Management Regulation issued together with the Government’s Decree No. 52/1999/ND-CP of July 8, 1999;
The Finance Ministry hereby guides the management and payment of investment capital and public-service capital of investment and construction nature belonging to the State budget’s capital source as follows:
Part I
GENERAL PROVISIONS
1. The State budget capital (including domestic capital of all State budget levels, the Government’s foreign loans and foreign aid capital provided to the Government, local administrations and State bodies) shall be paid only for investment projects of subjects entitled to use the State budget capital in accordance with the State Budget Law and the Investment and Construction Management Regulation.
2. Investment projects using the State budget capital must complete all investment and construction procedures, be incorporated in the State’s annual investment plans and meet all conditions for capital payment according to the Investment and Construction Management Regulation and the provisions of this Circular.
3. The finance agencies of different levels shall manage investment capital and public-service capital of investment and construction nature belonging to the State budget’s capital source as well as investment projects using other capital sources of the State. The State treasuries shall have the responsibility to closely inspect and control all stages of the payment process, ensure full and timely capital payment according to the prescribed regime for projects qualified for capital payment; if detecting that investors have used capital for wrong purposes or at variance with the prescribed regime, thus causing waste and loss to the State’s capital, they must take measures to prevent and handle such cases in time.
4. This Circular applies to projects with investment from the State budget’s capital source and the source of public-service capital of investment and construction nature under the management of the ministries, agencies attached to the Government, political organizations, socio-political organizations, social organizations, socio-professional organizations, State corporations (herein after collectively referred to as ministries), the provinces and centrally-run cities (hereinafter collectively referred to as provinces) as well as urban districts, rural districts, towns and provincial cities (hereinafter collectively referred to as districts).
The management, control and payment of investment capital belonging to the commune budgets; the management, control and payment of State budget capital for planning projects and investment projects of overseas Vietnamese representative missions, security and defense projects of confidential requirements, and projects on copyright purchase shall be regulated by separate documents.
Part II
SPECIFIC PROVISIONS
I. INVESTMENT PROJECTS USING STATE BUDGET CAPITAL AND PUBLIC-SERVICE CAPITAL OF INVESTMENT AND CONSTRUCTION NATURE
1. Socio-economic infrastructure projects where capital is irrecoverable in the following fields:
- Communications, irrigation, education and training, healthcare;
- Planting of headwater forests, protection forests, national gardens, nature conservation parks;
- Farms and stations for veterinary care, fauna and flora, research into new breeds and varieties and improvement of breeds and varieties;
- Construction of cultural, social, physical training and sport, public welfare works;
- State management, science and technology;
- Protection of the environment and ecology in different regions and territories.
2. Defense and security projects where capital is irrecoverable.
3. Support for enterprises’ investment projects in those fields where the State’s involvement is required by law.
4. Projects allocated with public-service capital in the State budget estimate to repair, renovate, expand and upgrade existing material bases, which have a value of VND 100 million or more, for the purpose of recovering or increasing the value of fixed assets (including also the building of new construction items for existing bases of administrative and public-service agencies and units).
Public-service capital shall not be allocated to investment projects on new construction, except for cases decided by the Prime Minister.
5. Other investment projects decided by the Government.
II. MAKING AND NOTIFICATION OF PLANS ON INVESTMENT CAPITAL, PUBLIC-SERVICE CAPITAL OF INVESTMENT AND CONSTRUCTION NATURE
1. Annual plans:
1.1. During the time when the annual State budget estimates are drafted, basing themselves on the project implementation tempo and the examination figures already notified, investors shall make plans on investment capital of their projects and submit them to the superior managing bodies for incorporation into the State budget estimates according to the State Budget Law.
Basing themselves on the agencies’ and units’ needs to repair, renovate, expand and upgrade their existing material bases, investors shall make plans on investment expenditure with the public-service capital source, incorporate them in the State budget estimates to be sent to the superior bodies according to the State Budget Law.
1.2. The ministries and the provincial People’s Committees shall synthesize and make investment capital plans and send them to the Finance Ministry and the Ministry of Planning and Investment.
1.3. On the basis of the socio-economic development plans and the economy’s major balances, the Finance Ministry shall coordinate with the Ministry of Planning and Investment in allocating the investment capital plan to each ministry, provincial People’s Committee and to important projects of the State.
The provincial/municipal Finance and Pricing Services shall join the provincial/municipal Planning and Investment Services in advising the provincial People’s Committees on the development investment policies for each period and each plan year and on the apportion of investment capital to each project under the provincial management.
The district Finance Sections shall join the district’s functional bodies in advising the district People’s Committees on the development investment policies for each period and each plan year, on the apportion of investment capital to each project under the district management.
1.4. After being assigned the budgets by the Government, the ministries and the provincial People’s Committees shall allocate investment capital to each project under their respective management, ensuring compatibility with the assigned quotas on total investment amount; structure of domestic capital and foreign capital; structure of economic branches; capital amounts of the State’s important projects as well as compliance with the Government’s direction on the management of annual socio-economic development plans and State budget estimates.
1.5. After allocating investment capital to each project, the ministries and provincial People’s Committees shall send the investment capital plans to the Ministry of Finance for examination of the following aspects:
- Assurance of conditions by the projects incorporated in the investment capital plan prescribed at Point 1, Clause III, Part II of this Circular.
- Compatibility with the Government-assigned quotas on total investment level, structure of domestic capital and foreign capital, structure of economic branches, capital levels of the State’s important projects.
- Adherence to the principles on plan allocation; investment projects must have investment decisions issued by October of the year preceding the plan year; Groups B and C projects must be allocated with sufficient capital for implementation according to the Government’s stipulations.
After examination, if the deployed plans fail to meet the above-mentioned requirements, the Finance Ministry shall make written requests for the readjustment thereof. Where the ministries or provincial People’s Committees fail to make readjustments or have made readjustments but their plans still fail to comply with regulations, the Finance Ministry shall send written reports thereon to the Prime Minister for decision while the finance agencies shall refrain from transferring capital to the State treasuries for payment.
The provincial/municipal Finance-Pricing Services (or the district Finance Sections) shall review the list of projects incorporated in the local capital construction investment plans according to the above provisions. Particularly for projects invested with capital sources left at the localities under the National Assembly’s resolutions and the Government’s decisions, they must also comply with the provisions on investment objects and the use of each investment capital source. Where the deployed plans fail to comply with regulations, the provincial/municipal Finance and Pricing Services (or the district Finance Sections) shall have to send reports thereon to the provincial (or district) People’s Committees for consideration and readjustment while refraining from transferring money to the State treasuries for payment.
1.6. On the basis of the allocated or readjusted plans which have complied with regulations:
- The ministries and the provincial or district People’s Committees shall assign the plan quotas to investors for implementation, and concurrently send them to the State treasuries of the same level for monitoring and use as basis for capital control and payment.
- For projects managed by the ministries, the Finance Ministry shall notify the investment capital payment plans to the State treasuries for use as basis for payment of capital therefor.
- For projects managed by the provinces, the provincial/municipal Finance and Pricing Services shall notify the investment capital payment plans to the provincial State treasuries for use as basis for payment of capital therefor.
- For projects managed by the districts, the district Finance Sections shall notify the investment capital payment plans to the district State treasuries for use as basis for payment of capital therefor.
2. Quarterly plans:
The contents of the quarterly plans on investment capital, public-service capital of investment and construction nature must reflect the value of the volume already performed in the preceding quarter and in the whole period from the beginning of the year till the end of the preceding quarter; the capital amounts already advanced and recovered and paid in the preceding quarter and in the whole period from the beginning of the year till the end of the preceding quarter; anticipate the value of the volume to be performed in the quarter; demands for capital advance and payment in the quarter.
2.1. Basing themselves on the assigned investment capital plans and the project implementation tempo, investors shall make quarterly investment capital plans with the above contents and send them to the State treasuries where investors have direct transactions with and concurrently to the ministries or provincial People’s Committees on the 10 th of the last month of the preceding quarter (particularly for the first quarter, investors shall send such plans within 5 days after receiving the annual investment capital plans assigned by the ministries or the provincial People’s Committees).
2.2. Basing themselves on the annual investment capital plans and the budget capability, the finance agencies shall have to arrange quarterly spending levels and notify the State treasuries thereof; basing themselves on the payment capital demands they shall transfer capital in time to the State treasuries for payment for projects.
2.3. For projects managed by the districts, investors shall make quarterly capital allocation plans and send them to the district Finance Sections. Basing themselves on the whole year’s capital plan and the budget capability, the district Finance Sections shall allocate the quarterly spending amount to each project, notify investors as well as the district State treasuries thereof; basing themselves on the payment capital demands, they shall transfer capital in time to the State treasuries for payment for projects.
2.4. For public-service capital of investment and construction nature, basing themselves on the annual State budget estimates notified to them, investors shall make quarterly spending plans and send them to the State treasuries they have direct transactions with for use as basis for control and payment.
III. CONDITIONS FOR HAVING INVESTMENT CAPITAL, PUBLIC-SERVICE CAPITAL OF INVESTMENT AND CONSTRUCTION NATURE PAID
Investment projects shall receive State budget capital payment when they meet all the following conditions:
1. Having completed all investment and construction procedures, specifically in the following stages:
1.1. Investment preparations:
- The competent authority’s document permitting the making of investment preparations.
- The cost estimate for the investment preparation work, which has been approved by the competent authority.
1.2. Project execution preparation
- The feasibility study report (or investment report) and the competent authority’s investment decision.
- The cost estimate for the project execution preparation work, which has been approved by the competent authority.
1.3. Investment execution:
- The feasibility study report (or investment report) and the competent authority’s investment decision.
- The technical design and total cost estimate, the decision approving the technical design and total cost estimate. For Groups A and B projects, if their technical design and total cost estimate have not yet been approved, their investment decisions must prescribe the capital level of each construction item and there must be the designs and cost estimates of different construction items to be constructed in the year, which have been approved by the competent authorities.
2. Having been incorporated in the investment capital plans as prescribed at Point 1, Clause II, Part II of this Circular.
3. Decisions on the assignment of tasks to the investor, on the establishment of the project management board (for cases where project management boards must be established), on the appointment of the board’s chairman, chief accountant or a person in charge of accounting.
4. Having organized bidding or designated bidders for the selection of consultants, procurement of equipment and construction and installation according to the Bidding Regulation.
5. Having satisfied all conditions for payment of advance capital and payment for the completed volumes according to the provisions in Clauses IV and V, Part II of this Circular.
6. For the source of public-service capital of investment and construction nature:
- There must be the feasibility study report (or investment report) and the investment decision.
- There must be the document approving the bidding result (for bidding package for which bidding is organized) or the decision approving the design and cost estimate (for bidding packages with designated bidders).
- There must be the contract for work assignment or the economic contract signed between the investor and the contractor.
- Being arranged in the annual State budget estimate.
7. Investors shall open accounts at the State treasury in the place convenient for payment control and for their transactions.
IV. ADVANCE CAPITAL AND RECOVERY OF ADVANCE CAPITAL
1. Objects eligible for advance capital
- Investment projects for which bidding is organized under turn-key contracts.
- Construction and installation biding packages for which bidding is organized.
- Procurement of equipment (including imported and locally-procured equipment).
- Consultancy contracts.
- The ground clearance and compensation work.
- Several jobs covered with other expenses of the project, such as expenses for the project management apparatus, land rentals or land use right transfer tax.
Investment projects or the work volumes belonging to investment projects other than the above-mentioned objects shall receive advance capital only when it is so permitted by the Prime Minister.
2. Conditions for receiving advance capital:
2.1. For investment projects for which bidding is organized under turn-key contracts (bidding for the entire work of designing, equipment supply, construction and installation to be performed by one contractor) and the construction and installation bidding packages for which bidding is organized.
- There must be the competent authority’s written approval of the bidding results.
- There must be the economic contract signed between the investor and contractor.
- There must be a contract performance security paper made by the contractor.
2.2. For the procurement of equipment (including imported and home-made equipment):
- There must be the competent authority’s written approval of the bidding result (for equipment for which bidding is organized) or the document designating bidders (for equipment for which no bidding is organized).
- There must be the economic contract signed between the investor and the contractor for the supply, processing or manufacture of equipment. Particularly for imported equipment, there must be the competent authority’s written approval of the contract therefor according to current regulations.
- There must be a contract performance security paper made by the contractor (for equipment for which bidding is organized).
2.3. For jobs in need of hired consultants:
- There must be the competent authority’s written approval of the bidding result (for jobs for which bidding is organized) or the document designating bidders (for jobs for which no bidding is organized).
- There must be the economic contract signed between the investor and consultancy contractor.
2.4. For some jobs covered by other expenses of the project:
- For the ground clearance and compensation work, there must be approved compensation plan and cost estimate.
- For expense for land allocation, land tax or land use right transfer tax, there must be the specialized bodies’ notices requesting the investor to make payment thereof.
- For expense for the operation of the project management apparatus, there must be the approved cost estimate.
3. The level of advance capital
3.1. For investment projects for which bidding is organized under turn-key contracts:
- Advance for the procurement of equipment shall be made on the basis of the payment tempo (pursuant to Item 3.3 below).
- The remaining advance amount equal to 15% of the bidding package’s value shall be paid, which, however, must not exceed the whole year’s capital plan already apportioned to these jobs.
3.2. For construction and installation:
- For bidding packages valued at under VND 10 billion, the advance level shall be equal to 20% of the contract value but must not exceed the whole year’s capital plan of the bidding package.
- For bidding packages valued at between VND 10 billion and under 50 billion, the advance level shall be equal to 15% of the contract value but must not exceed the whole year’s capital plan of the bidding package.
- For bidding packages valued at VND 50 billion or more, the advance level shall be equal to 10% of the contract value but must not exceed the whole year’s capital plan of the bidding package.
In cases where the whole year’s capital plan of a bidding package is lower than the advance level prescribed above (such bidding package has not yet received full advance amount at the prescribed level), the concerned State treasury shall continue to pay the advance capital in the subsequent year’s plan until the prescribed advance level is reached.
3.3. For the procurement of equipment:
- The advance amount shall be the sum of money the investor shall have to pay as contracted, but must not exceed the year’s capital plan. Where the allocated capital plan is not enough for payment as contracted, the investor shall have to seek for supplementary capital sources.
- The advance capital shall be paid according to the tempo of payment made by the investors to the contractors for the supply, processing or manufacture of equipment set in the economic contracts, which shall be effected till the equipment have been put into the investors’ storehouses (for equipment requiring no installation) or have been installed and pre-acceptance tested (for equipment requiring installation).
3.4. For consultancy contracts, the minimum advance amount shall be equal to 25% of the bidding package’s value but must not exceed the whole year’s capital plan already allocated to the jobs requiring hired consultants.
3.5. For the ground clearance and compensation work, the advance amount shall comply with the necessary requirements of the compensation work but must not exceed the whole year’s capital plan already arranged for the ground clearance and compensation work.
3.6. For some jobs covered with other expenses of the project, which are eligible for advance payment, the advance amount shall comply with the necessary requirements but must not exceed the whole year’s capital plan already allocated to such jobs.
4. Recovery of advance capital:
4.1. Capital advanced for construction and installation contracts shall be gradually recovered at each period of payment for the completed construction and installation volumes according to the following provisions:
- Time for starting the recovery:
+ For bidding packages valued at under VND 10 billion: when 30% of the contract’s value is paid.
+ For bidding packages valued at between VND 10 billion and under 50 billion: when 25% of the contract’s value is paid.
+ For bidding packages valued at VND 50 billion or more: when 20% of the contract’s value is paid.
- The advance amount shall be fully recovered when the bidding package receives payment equal to 80% of the value of the completed construction and installation volume.
- The advance amount to be recovered in each period shall be determined as follows:
+ When 50% of the contract’s value is paid, the recovered advance capital amount shall reach 40% of the total advance amount.
+ When 70% of the contract’s value is paid, the recovered advance capital amount shall reach 80% of the total advance amount.
+ When 80% of the contract’s value is paid, the recovered advance capital amount shall reach 100% of the total advance amount.
Where the advance capital is not fully recovered because the bidding package has not yet been paid at the rate prescribed above but the project is no longer incorporated in the plan or the construction thereof is suspended, the investor shall have to report to the State treasury on the situation of the use of the advance capital amount not yet recovered and concurrently to the competent authorities for handling.
Where the advance capital has been paid but the bidding package fails to be constructed according to the time limit prescribed in the contract, the investor shall have to explain such to the State treasury and have to repay the capital amount already advanced
4.2. Capital advanced for the procurement of equipment shall be recovered at each time of payment for the completed equipment volume.
For equipment requiring no installation, after they have been pre-acceptance tested and put into the investor’s storehouse, the investor shall have to immediately send vouchers thereof to the State treasury for completion of payment procedures for the completed equipment volume and for recovery of the capital amount already advanced.
For equipment requiring installation, when equipment has arrived at the investor’s storehouse, the investor shall have to report such to the State treasury for monitoring; when equipment has been installed, the investor shall have to send vouchers thereof to the State treasury for completion of payment procedures for the completed equipment volume and for recovery of the advanced capital amount. The State treasury shall recover the full advance amount advanced for equipment procurement when making payment for the completed construction and installation volume.
Where the advance capital has been paid but the investor, after the time limit prescribed in the contract has expired, still receives no equipment, the investor shall have to explain such to the State treasury and repay the capital amount already advanced.
4.3. Capital advanced for consultancy contracts shall be recovered at each time of payment for the completed consultancy volume on the following principles:
- The time of recovery shall be the time when the payment for the completed volume starts.
- The recovered capital amount shall be the capital amount to be paid multiplied by (x) the advance capital rate.
4.4. Capital advanced for the ground clearance and compensation work and jobs covered with other expenses of the project shall be recovered in lump sum at the time of payment for the completed volume of such jobs.
4.5. The level of recovering capital advanced for contracts of different kinds may be higher than the above-prescribed level if it is so unanimously requested by the investor and the contractors.
4.6. Where the plan schedule has expired but the advanced capital has not yet fully recovered because the bidding package has not yet received payment at the prescribed rate, the recovery shall continue in the subsequent year’s plan and such advanced capital shall not be subtracted from the subsequent year’s capital plan.
5. For some supplies being big-value structures and semi-finished products used in construction, which need to be manufactured in advance in order to ensure the project construction tempo and some special-typed supplies and supplies which need to be seasonally reserved, if investors find it necessary to have more advance capital than the advance levels prescribed above, they shall report such to the Finance Ministry (for projects managed by the ministries), the provincial/municipal Finance and Pricing Services (for projects managed by the provinces) or the district Finance Sections (for projects managed by the districts) for decision. Such advance capital shall be recovered at the time of payment for the completed capital construction volume composed of the supplies eligible for advance payment as mentioned above.
6. For public-service capital of investment and construction nature:
- For projects capitalized at VND 1 billion or more, the advance payment and the recovery of the advance capital shall be effected like for capital construction investment capital.
- For projects capitalized at under VND 1 billion, they shall receive an advance payment equal to 50% of their annual plans. Such advance capital shall be gradually recovered at each period of payment for the completed volume and recovered in full within the plan year. The advance capital amount to be recovered at each period shall be the paid capital amount multiplied by (x) the advance payment rate.
7. For investment projects funded with foreign capital or bidding packages for which international bidding is organized under credit agreements signed between the Vietnamese Government and the financial donors which contain provisions on capital advance (objects eligible for capital advance, conditions for and levels of advance, recovery of advance capital), which are different from the above-mentioned provisions, such provisions of the signed agreements shall apply.
V. PAYMENT FOR COMPLETED VOLUMES
1. Payment for completed construction and installation volumes:
1.1. The construction and installation volume completed in the form of bidder designation and qualified for payment shall be the performed volume already pre-acceptance tested every month as contracted, which is incorporated in the assigned investment plans and has its design and detailed cost estimate already approved according to the State’s norms and unit prices.
1.2. The construction and installation volume completed in the form of bidding and qualified for payment shall be the performed volume already pre-acceptance tested as contracted, which is included in the assigned investment plans.
1.3. To receive payment for the completed construction and installation volume, investors shall send to the State treasuries the following documents:
1.3.1. For cases of bidder designation
- The written approval of the designs and detailed cost estimates of construction items.
- The decision on bidder designation.
- The economic contract between the investor and the contractor.
- The record on the pre-acceptance test of the completed construction and installation volume, enclosed with the calculation of the value of the pre-acceptance tested volume.
- The price bill and payment vouchers.
1.3.2. For cases of bidding:
- The written approval of the bidding results.
- The economic contract between the investor and the contractor.
- The record on the pre-acceptance test of the completed construction and installation volume, enclosed with the calculation of the value of the pre-acceptance tested volume.
- The price bill and payment vouchers.
For volumes arising outside the bidding packages, there must be written approvals of the supplementary bidding results (if the arising volume is opened to bidding) or the approved supplementary cost estimate (if the arising volume is subject to bidder designation).
1.4. Basing themselves on the investors’ proposals and payment dossiers, within 7 working days after the receipt of valid dossiers, the State treasuries shall examine such dossiers, make payment to the investors and contractors and recover the advanced capital according to regulations.
2. Payment for completed equipment volumes:
2.1. The completed equipment volume qualified for payment shall be the equipment volume already put into the investor’s storehouse (for equipment requiring no installation) or already installed and pre-acceptance tested (for equipment requiring installation), which fully meets the following conditions:
- The list of equipment must be compatible with the investment decision and included in the assigned investment plan.
- Having been included in the economic contract between the investor and the contractor.
- Having been put into the investor’s storehouse (for equipment requiring no installation) or already installed and pre-acceptance tested (for equipment requiring installation).
2.2. To receive payment for completed equipment volumes, investors shall send to the State treasuries the following documents:
- The economic contract between the investor and the contractor.
- The bill-cum-delivery card (for domestically-procured equipment) or the import voucher set (for imported equipment).
- The warehousing card (for equipment requiring no installation) or the payment price bill for equipment installation volume (for equipment requiring installation).
- Transport, insurance, tax, warehousing charge vouchers.
- The price bill and payment vouchers.
2.3. Basing themselves on the investors’ proposals and payment dossiers, within 7 working days after the receipt of complete and valid dossiers, the State treasuries shall examine such dossiers, make payment to the investors and contractors and recover the advanced capital according to regulations.
3. Payment for completed consultancy volumes:
3.1. The completed consultancy volume qualified for payment shall be the performed volume already pre-acceptance tested in conformity with the economic contract and included in the assigned investment plan.
3.2. To receive payment, investors shall send to the State treasuries the following documents:
- The decision on bid winning or bidder designation.
- The economic contract between the investor and the contractor.
- The record on the pre-acceptance test of the completed consultancy volume.
- Payment vouchers.
3.3. Basing themselves on the investors’ proposals and payment dossiers, within 7 working days after the receipt of complete and valid dossiers, the State treasuries shall examine such dossiers, make payment to the contractors and recover the advanced capital according to regulations.
4. Payment for volumes covered with other expenses:
4.1. Apart from the jobs for which consultants are hired, other jobs covered with other expenses of the project shall be qualified for payment when they gather all the following grounds to prove that they have been completed:
- For construction land allocation fee, land tax or land use right transfer tax, there must be valid invoices and vouchers issued by the collecting agencies.
- For compensation and ground clearance expenses, there must be the approved compensation plans and cost estimates and the written certification of the performed compensation volume.
- For expenses for destruction and dismantlement of architectural objects and construction ground clearance, there must be the approved cost estimates, contracts and pre-acceptance test records.
- For expenses for the project management apparatus, there must be the approved cost estimates, cash plans, list of expenses and vouchers thereof.
- For expenses for making and evaluating designs and cost estimates, there must be contracts and pre-acceptance test records.
- For expenses for commencement of construction, pre-acceptance test, trial operation and inauguration, there must be the approved cost estimates and list of expenses.
- For expenses for specialists, training of technicians and production managers, there must be economic contracts and approved cost estimates.
- For construction insurance premiums, there must be insurance policies.
- For expenses for the investment and project preparation as well as execution preparation work, there must be the approved cost estimates, economic contracts, records on the pre-acceptance test of the work volume or reports on the work results.
4.2. Basing themselves on the investors’ proposals and payment dossiers, within 7 working days after the receipt of complete and valid dossiers, the State treasuries shall examine such dossiers, make payment to the contractors and recover the advanced capital according to regulations.
5. The capital paid for each construction item must not exceed the cost estimate or the bid-winning price; the total capital amount paid for a project must not exceed the approved total cost estimate and total investment amount.
The capital amount paid for a project in the year (including both advance amount and the amount paid for the completed volume) must not exceed the whole year’s capital plan already allocated to the project.
6. Documents sent by investors to the Sate treasuries shall include those sent only once for the whole projects and those sent together with each payment request. Documents sent only once shall be: feasibility study reports (or investment reports), investment decisions, decisions approving the technical designs and total cost estimates, documents on cost estimates, documents on the approval of bidding results and economic contracts signed between investors and contractors.
7. For investment projects funded with foreign capital or bidding packages for which international biddings are organized under credit agreements signed between the Vietnamese Government and the financial donors, which contain provisions on payment different from the above-said provisions, such provisions of the signed credit agreements shall apply.
8. Investors must arrange enough capital in the annual plans for purchase of construction work insurance. The State shall not make payment to investors to cover damage and risk losses which fall under the insurance scope if investors fail to purchase construction work insurance according to current regulations.
9. For public-service capital of investment and construction nature:
- For projects capitalized at VND 1 billion or more, the payment for the completed volumes shall comply with the current investment capital management regime.
- For projects capitalized at under VND 1 billion, when some volume has been completed and pre-acceptance tested, investors shall compile dossiers requesting payment therefor and send them to the State treasuries. Such a dossier shall consist of:
+ The record on the pre-acceptance test of the completed volume.
+ The detailed calculation of the value of the volume subject to payment.
+ The price bill or expense list (for other expenses with non-use of price bills) and payment vouchers.
Basing themselves on the funding limits allocated by the finance agencies, the State treasuries shall control and make payments to the beneficiaries and recover the already advanced amounts (if any).
10. For extremely important projects requiring a capital advance and payment regime different from the above provisions, after obtaining the opinions from the competent authorities, the Finance Ministry shall issue separate guiding documents.
VI. REPORTING, SETTLEMENT AND INSPECTION REGIMES
1. On the 20 th of every month and the 10 th of the first month of the subsequent quarter, investors shall have to make reports on the situation of the investment execution, capital receipt and use in the month or the preceding quarter and send them to the State treasuries and also to the investment-deciding authorities. Particularly for Group A projects, investors shall send such reports to the State treasuries, the ministries or the provincial People’s Committees, the Ministry of Planning and Investment, the Finance Ministry, the Ministry of Construction and the General Department of Statistics for sum-up and reporting to the Prime Minister.
At the end of the plan year, investors shall have to make reports on the plan implementation and their units’ accounting work according to current regulations; when their investment projects are completed, investors shall have to make reports on the settlement of investment capital according to regulations on the investment capital settlement regime.
Where the settlement of a completed investment project has been approved but the settled capital amount is lower than the capital amount already paid to the project, the investor shall have to recover the surplus capital amount from the contractor and refund it to the State.
2. Quarterly and at the end of the plan year, the ministries and the provincial People’s Committees shall have to synthesize the implementation of investment plans and the capital payment for projects under their respective management and send reports thereon to the Finance Ministry, the Ministry of Planning and Investment, the Ministry of Construction and the General Department of Statistics according to regulations.
3. The central and local State treasuries and finance agencies shall apply the regime of reporting on the capital payment and the settlement for completed projects and other necessary information according to the Finance Ministry’s regulations on the information and reporting regime in the field of capital construction investment.
At the end of the plan year, the State treasuries shall settle with the finance agencies the budget capital they have received and paid for projects according to regulations on the State budget settlement.
4. The ministries, the provincial People’s Committees, the finance agencies and the State treasuries shall conduct regular and irregular inspections of investors regarding their use of advance capital, capital paid for completed volumes and observance of the State’s development investment finance policies and regime.
VII. RESPONSIBILITIES AND POWERS OF CONCERNED AGENCIES
1. Investors:
- To perform the functions and tasks assigned to them according to the Investment and Construction Management Regulation. To receive and use capital for the right purposes and right subjects in an economical and efficient manner. To abide by law provisions on the financial management regime in investment and construction.
- To be accountable for the truthfulness and lawfulness of the project’s volume when payment is made (such volume must be compatible with the construction drawing design or technical construction design and its quality must comply with the design requirements); to ensure the accuracy, lawfulness and validity of data and documents supplied to the State treasuries and the functional State bodies.
- When the capital construction volumes have satisfied all the contractual conditions, to conduct timely pre-acceptance test thereof, compile complete payment dossiers and payment requests for the contractors.
- To report in time and fully as prescribed to the investment-deciding bodies and concerned State bodies; supply fully dossiers, documents and facts according to regulations of the State treasuries and finance agencies in service of the capital management and payment work; to submit to the inspection by the State treasuries, the finance agencies and the investment-deciding bodies of the use of investment capital and observance of the State’s development investment finance policies and regimes.
- To practice accounting for the receipt and use of investment capital according to current regulations on the accounting work of investors’ units; to settle the completed investment capital according to regulations.
- To request capital payment when they meet all the conditions and request the State treasuries to reply and explain matters they deem unsatisfactory in the capital payment.
2. The ministries and the provincial and district People’s Committees:
- To guide, inspect and urge investors under their respective management to carry out investment plans, receive and use investment capital for the right purposes in accordance with the State’s regimes.
- To report on the implementation of investment plans according to regulations.
- Within the scope of their delegated competence, to be responsible to the Government and the State’s laws for their decisions.
3. The State treasuries:
- The central State treasury shall prescribe the order, procedures, dossiers and vouchers which need to be sent only once or each time of payment request in the capital advance and payment process.
- To guide investors in opening accounts for advance capital and capital payment.
- To pay capital in time and fully for projects when all conditions are met.
- To clearly explain in writing to investors the reduced or rejected payment amounts, to answer investors’ inquiries about the capital payment.
- When detecting that decisions of competent authorities are contrary to current regulations, to make written requests for re-consideration and put forward proposals. If past the prescribed time limit, no reply is made, to be entitled to settle the cases according to their proposals; if a reply is made but deemed unsatisfactory, to settle the cases according to the competent authorities’ opinions and at the same time to report such to the higher-level competent authorities for consideration.
- To apply the regimes of information and reporting and settle the investment capital and public-service capital of investment and construction nature belonging to the State budget’s capital source according to the provisions of the State Budget Law and the guidance of the Finance Ministry.
- To be entitled to request investors to supply dossiers, documents and information according to the prescribed regime in service of the capital payment control work.
- To be permitted to suspend capital payment or recover capital amounts used by investors for wrong purposes or wrong objects or in contravention of the financial management regime of the State and, at the same time to report such to the Finance Ministry for handling; to be entitled to refuse capital payment for projects whose investors fail to strictly abide by the regime of formulating quarterly investment capital plans, the reporting regime prescribed in the Investment and Construction Management Regulation and in this Circular.
- Not to participate in the Councils for pre-acceptance test of completed capital construction volumes.
- To organize the capital control and payment according to uniform professional processes, to ensure the strict capital management and make timely, full and convenient payments to investors.
- To be responsible to the Finance Minister and the State’s laws for the receipt and use of State budget capital and the payment in investment and construction.
4. The finance agencies of different levels:
- To ensure sufficient capital sources and transfer capital in time to the State treasuries so that the latter make payment for projects.
- To report on and settle development investment capital in accordance with the State Budget Law.
- To coordinate with the ministries and the provinces in guiding and inspecting investors’ observance of the development investment finance regimes and policies, management and use of investment capital.
- To be entitled to request investors to supply documents and information necessary for the State management of development investment finance, including documents in service of evaluation of investment projects and allocation of annual plans, periodical reports according to the information and reporting regime and documents in service of examination of investment capital settlements.
Part III
IMPLEMENTATION PROVISIONS
1. This Circular takes effect 15 days after its signing and replaces the Finance Ministry’s Circular No. 135/1999/TT-BTC of November 19, 1999 guiding the management and settlement of investment capital and public-service capital of investment and construction nature belonging to the State budget’s capital source and Circular No. 76/TC-DTPT of November 1, 1997 guiding the management and allocation of capital construction investment capital belonging to the district and commune budgets.
2. For other development investment expenditures from the State budget (State reserve expenditures, expenditures in support of enterprises’ working capital, expenditures for contribution of joint venture shares, expenditures for loans to foreign countries and for foreign aid, expenditures for development assistance funds), they shall comply with separate guiding documents on each kind of expenditures mentioned above.
3. For investment projects funded with other capital sources of the State, the payment principles prescribed in this Circular shall also apply.
For the Finance Minister
Vice Minister
VU VAN NINH
7 parts
Bộ Tài chính
Số: 96/2000/TT-BTC
ngày 28 tháng 09 năm 2000
THÔNG TƯ
Hướng dẫn việc quản lý, thanh toán vốn đầu tư
và vốn sự nghiệp có tính chất đầu tư và xây dựng
thuộc nguồn vốn ngân sách nhà nước
Căn cứ Luật Ngân sách nhà nước ban hành ngày 20/3/1996 và Nghị định số 87/CP ngày 19/12/1996 của Chính phủ quy định chi tiết việc phân cấp quản lý,lập, chấp hành và quyết toán ngân sách nhà nước;
Căn cứ Nghị định số 52/1999/NĐ-CP ngày 8/7/1999 của Chính phủ về việc ban hành Quy chế Quản lý đầu tư và xây dựng và Nghị định số 12/2000/NĐ-CPngày 05/5/2000 của Chính phủ về việc sửa đổi, bổ sung một số điều của Quy chế Quản lý đầu tư và xây dựng ban hành kèm theo Nghị định số 52/1999/NĐ-CP ngày8/7/1999 của Chính phủ;
-
Section I
ĐỐI TƯỢNG CÁC DỰ ÁN ĐẦU TƯ SỬ DỤNG VỐN NSNN VÀ VỐN SỰ NGHIỆP CÓ TÍNH CHẤT ĐẦU TƯ VÀ XÂY DỰNG
1.Các dự án kết cấu hạ tầng kinh tế-xã hội không có khả năng thu hồi vốn thuộc các lĩnh vực:
Giaothông, thuỷ lợi, giáo dục đào tạo, y tế;
Trồng rừng đầu nguồn, rừng phòng hộ, vườn quốc gia, khu bảo tồn thiên nhiên;
Các trạm, trại thú y, động, thực vật, nghiên cứu giống mới và cải tạo giống;
Xây dựng công trình văn hoá, xã hội, thể dục thể thao, phúc lợi công cộng;
Quản lý nhà nước, khoa học kỹ thuật;
Bảo vệ môi trường sinh thái khu vực, vùng lãnh thổ.
2.Các dự án quốc phòng, an ninh không có khả năng thu hồi vốn.
3.Hỗ trợ các dự án của các doanh nghiệp đầu tư vào các lĩnh vực cần thiết có sự tham gia của Nhà nước theo quy định của pháp luật.
4.Các dự án được bố trí bằng vốn chi sự nghiệp trong dự toán NSNN để sửa chữa,cải tạo, mở rộng, nâng cấp các cơ sở vật chất hiện có, có giá trị từ 100 triệu đồng trở lên, nhằm phục hồi hoặc tăng giá trị tài sản cố định (bao gồm cả việc xây dựng mới các hạng mục công trình trong các cơ sở đã có của các cơ quan, đơn vị hành chính sự nghiệp).
Không được bố trí vốn sự nghiệp cho các dự án đầu tư xây dựng mới, trừ các trường hợp có quyết định của Thủ tướng Chính phủ.
5.Các dự án đầu tư khác theo quyết định của Chính phủ. -
Section II
1. Kế hoạch năm: 1.1Trong thời gian lập dự toán NSNN hàng năm, căn cứ vào tiến độ thực hiện dự ánvà số kiểm tra được thông báo, chủ đầu tư lập kế hoạch vốn đầu tư của dự án gửi cơ quan quản lý cấp trên để tổng hợp vào dự toán NSNN theo quy định của LuậtNSNN. Căn cứ vào nhu cầu sửa chữa, cải tạo, mở rộng, nâng cấp các cơ sở vật chất hiện có của cơ quan, đơn vị, chủ đầu tư lập kế hoạch chi đầu tư bằng nguồn vốn sự nghiệp, tổng hợp trong dự toán NSNN, gửi cơ quan cấp trên theo quy định cuảLuật NSNN. 1.2Các Bộ và UBND các tỉnh tổng hợp, lập kế hoạch vốn đầu tư gửi Bộ Tài chính vàBộ Kế hoạch và Đầu tư. 1.3Trên cơ sở kế hoạch phát triển kinh tế-xã hội, các cân đối chủ yếu của nền kinh tế, Bộ Tài chính phối hợp với Bộ Kế hoạch và Đầu tư phân bổ kế hoạch vốn đầu tư cho từng Bộ, UBND tỉnh và các dự án quan trọng của Nhà nước. Sở Tài chính-Vật giá tham gia với Sở Kế hoạch và Đầu tư tham mưu cho UBND tỉnh về chủ trương đầu tư phát triển trong từng thời kỳ và trong từng năm kế hoạch,phân bổ vốn đầu tư cho từng dự án do tỉnh quản lý. Phòng Tài chính huyện tham gia với các cơ quan chức năng của huyện tham mưu cho UBNDhuyện về chủ trương đầu tư phát triển trong từng thời kỳ và trong từng năm kế hoạch, phân bổ vốn đầu tư cho từng dự án do huyện quản lý. 1.4Sau khi được Chính phủ giao ngân sách, các Bộ và UBND các tỉnh phân bổ vốn đầu tư cho từng dự án thuộc phạm vi quản lý, đảm bảo khớp đúng với chỉ tiêu đượcgiao về tổng mức đầu tư; cơ cấu vốn trong nước, vốn ngoài nước; cơ cấu ngành kinh tế; mức vốn các dự án quan trọng của Nhà nước và đúng với chỉ đạo cuảChính phủ về điều hành kế hoạch phát triển kinh tế-xã hội và dự toán NSNN hàng năm. 1.5Sau khi đã phân bổ vốn đầu tư cho từng dự án, các Bộ và UBND các tỉnh gửi kế hoạch vốn đầu tư cho Bộ Tài chính để kiểm tra về các mặt sau đây: Việc đảm bảo các điều kiện của dự án được bố trí kế hoạch vốn đầu tư theo quy định tại điểm 1 khoản III phần II Thông tư này. Sự khớp đúng với chỉ tiêu do Chính phủ giao về tổng mức đầu tư, cơ cấu vốn trong nước,vốn ngoài nước, cơ cấu ngành kinh tế, mức vốn các dự án quan trọng của Nhà nước. Sựtuân thủ các nguyên tắc bố trí kế hoạch; các dự án đầu tư phải có quyết định đầu tư từ thời điểm tháng 10 về trước của năm trước năm kế hoạch; các dự án nhóm B, nhóm C phải bố trí đủ vốn để thực hiện dự án theo quy định của Chính phủ. Saukhi kiểm tra, nếu kế hoạch đã triển khai chưa đảm bảo các yêu cầu trên đây thì Bộ Tài chính có văn bản đề nghị điều chỉnh lại. Trường hợp các Bộ và UBND các tỉnh không điều chỉnh lại hoặc đã điều chỉnh nhưng vẫn không đúng quy định, Bộ Tài chính có văn bản báo cáo Thủ tướng Chính phủ quyết định, đồng thời cơ quan Tài chính chưa chuyển vốn sang Kho bạc nhà nước để thanh toán. Sở Tài chính-Vật giá (hoặc Phòng Tài chính huyện) rà soát danh mục dự án được bố trí trong kế hoạch đầu tư XDCB của địa phương theo các điểm quy định trên đây.Riêng đối với các dự án được đầu tư bằng các nguồn vốn được để lại theo Nghị quyết của Quốc hội và Quyết định của Chính phủ còn phải tuân thủ các quy định về đối tượng đầu tư và việc sử dụng từng nguồn vốn đầu tư. Trường hợp kế hoạch đã triển khai chưa đảm bảo các quy định, Sở Tài chính-Vật giá (hoặc Phòng Tài chính huyện) phải có văn bản báo cáo UBND tỉnh (hoặc huyện) xem xét, điều chỉnh lại và chưa chuyển tiền sang Kho bạc nhà nước để thanh toán. 1.6Trên cơ sở kế hoạch đã phân bổ hoặc sau khi điều chỉnh đã phù hợp với các quy định: Các Bộ và UBND các tỉnh, huyện giao chỉ tiêu kế hoạch cho các chủ đầu tư để thực hiện, đồng gửi cơ quan Kho bạc nhà nước đồng cấp để theo dõi, làm căn cứ kiểm soát, thanh toán vốn. Đối với các dự án do các Bộ quản lý, Bộ Tài chính thông báo kế hoạch thanh toán vốn đầu tư cho Kho bạc nhà nước để làm căn cứ thanh toán vốn cho các dự án. Đối với các dự án do tỉnh quản lý, Sở Tài chính-Vật giá thông báo kế hoạch thanhtoán vốn đầu tư cho Kho bạc nhà nước tỉnh để làm căn cứ thanh toán vốn cho các dự án. Đối với các dự án do huyện quản lý, Phòng Tài chính huyện thông báo kế hoạch thanhtoán vốn đầu tư cho Kho bạc nhà nước huyện để làm căn cứ thanh toán vốn cho các dự án.2. Kế hoạch quý: Nội dung kế hoạch vốn đầu tư, vốn sự nghiệp có tính chất đầu tư và xây dựng hàng quý phải phản ánh được giá trị khối lượng đã thực hiện của quý trước và luỹ kếtừ đầu năm đến cuối quý trước; vốn đã được tạm ứng, thu hồi tạm ứng và thanhtoán của quý trước và luỹ kế từ đầu năm đến cuối quý trước; dự kiến giá trị khối lượng thực hiện trong quý; nhu cầu vốn tạm ứng và vốn thanh toán trong quý. 2.1Căn cứ vào kế hoạch vốn đầu tư được giao và tiến độ thực hiện dự án, chủ đầu tư lập kế hoạch vốn đầu tư hàng quý theo các nội dung trên đây gửi Kho bạc nhà nước nơi chủ đầu tư trực tiếp giao dịch, đồng gửi Bộ hoặc UBND tỉnh vào ngày 10 cuảtháng cuối qúy trước (riêng qúy I, chủ đầu tư gửi 5 ngày sau khi nhận được kế hoạch vốn đầu tư năm do Bộ hoặc UBND tỉnh giao). 2.2Căn cứ vào kế hoạch vốn đầu tư năm và khả năng ngân sách, cơ quan Tài chính có trách nhiệm bố trí mức chi hàng quý và thông báo cho Kho bạc nhà nước; căn cứ vào nhu cầu vốn thanh toán, chuyển vốn kịp thời cho Kho bạc nhà nước để thanhtoán cho các dự án. 2.3Đối với các dự án do huyện quản lý, chủ đầu tư lập kế hoạch cấp vốn quý gửi Phòng Tài chính huyện. Căn cứ kế hoạch vốn cả năm và khả năng ngân sách, Phòng Tài chính huyện phân bổ mức chi quý cho từng dự án, thông báo cho chủ đầu tư,đồng gửi Kho bạc nhà nước huyện; căn cứ vào nhu cầu vốn thanh toán, chuyển vốn kịp thời cho Kho bạc nhà nước để thanh toán cho các dự án. 2.4Đối với vốn sự nghiệp có tính chất đầu tư và xây dựng, căn cứ vào dự toán NSNNnăm được thông báo, chủ đầu tư lập kế hoạch chi hàng quý gửi Kho bạc nhà nước nơi chủ đầu tư trực tiếp giao dịch để làm căn cứ kiểm soát, thanh toán.
-
Section III
ĐIỀU KIỆN ĐỂ ĐƯỢC THANH TOÁN VỐN ĐẦU TƯ, VỐN SỰ NGHIỆP CÓ TÍNH CHẤT ĐẦU TƯ VÀ XÂY DỰNG
Các dự án đầu tư được thanh toán vốn NSNN khi có đủ các điều kiện sau đây:
1.Có đủ thủ tục về đầu tư và xây dựng, cụ thể theo các giai đoạn như sau:
1.1 Chuẩn bị đầu tư:
Văn bản của cấp có thẩm quyền cho phép tiến hành chuẩn bị đầu tư.
Dựtoán chi phí cho công tác chuẩn bị đầu tư được cấp có thẩm quyền phê duyệt.
1.2Chuẩn bị thực hiện dự án:
Báo cáo nghiên cứu khả thi (hoặc báo cáo đầu tư) và quyết định đầu tư của cấp có thẩm quyền.
Dựtoán chi phí cho công tác chuẩn bị thực hiện dự án được cấp thẩm quyền phê duyệt.
1.3 Thực hiện đầu tư:
Báo cáo nghiên cứu khả thi (hoặc báo cáo đầu tư) và quyết định đầu tư của cấp có thẩm quyền.
Thiết kế kỹ thuật và tổng dự toán, quyết định phê duyệt thiết kế kỹ thuật và tổng dựtoán. Những dự án nhóm A, B nếu chưa có thiết kế kỹ thuật và tổng dự toán được duyệt, thì trong quyết định đầu tư phải quy định mức vốn của từng hạng mục công trình và phải có thiết kế và dự toán hạng mục công trình thi công trong năm được cấp có thẩm quyền phê duyệt.
2.Được bố trí kế hoạch vốn đầu tư theo quy định tại điểm 1 khoản II phần II Thông tư này.
3.Quyết định giao nhiệm vụ chủ đầu tư, thành lập Ban Quản lý dự án (trường hợp phải thành lập Ban QLDA), bổ nhiệm Trưởng ban, Kế toán trưởng hoặc phụ trách kếtoán.
4.Đã tổ chức đấu thầu hoặc chỉ định thầu tuyển chọn tư vấn, mua sắm thiết bị, xây lắp theo quy định của Quy chế Đấu thầu.
5.Đủ điều kiện được thanh toán vốn tạm ứng và thanh toán khối lượng hoàn thành theo quy định tại khoản IV và V phần II Thông tư này.
6.Đối với nguồn vốn sự nghiệp có tính chất đầu tư và xây dựng:
Có báo cáo nghiên cứu khả thi (hoặc báo cáo đầu tư) và quyết định đầu tư.
Có văn bản phê duyệt kết quả đấu thầu (đối với gói thầu tổ chức đấu thầu) hoặc quyết định phê duyệt thiết kế dự toán (đối với gói thầu chỉ định thầu).
Có hợp đồng giao việc hoặc hợp đồng kinh tế giữa chủ đầu tư và người nhận thầu.
Được bố trí trong dự toán NSNN năm.
7.Chủ đầu tư mở tài khoản tại Kho bạc nhà nước nơi thuận tiện cho việc kiểm soát thanh toán và thuận tiện cho giao dịch của chủ đầu tư. -
Section IV
TẠM ỨNG VÀ THU HỒI VỐN TẠM ỨNG
1. Đối tượng được tạm ứng vốn: Dựán đầu tư tổ chức đấu thầu theo hợp đồng chìa khoá trao tay. Các gói thầu xây lắp tổ chức đấu thầu. Mua sắm thiết bị (kể cả thiết bị nhập khẩu và thiết bị mua trong nước). Các hợp đồng tư vấn. Công việc đền bù giải phóng mặt bằng. Một số công việc thuộc chi phí khác của dự án, như chi phí bộ máy quản lý dự án,thuế đất hoặc thuế chuyển quyền sử dụng đất. Các dự án đầu tư hoặc khối lượng công việc thuộc dự án đầu tư ngoài đối tượng nêu trên chỉ được thanh toán vốn tạm ứng khi Thủ tướng Chính phủ cho phép.2. Điều kiện được tạm ứng vốn: 2.1Đối với các dự án đầu tư thực hiện đấu thầu theo hợp đồng chìa khoá trao tay(đấu thầu toàn bộ các công việc thiết kế, cung cấp thiết bị, xây lắp được thực hiện thông qua một nhà thầu) và các gói thầu xây lắp thực hiện đấu thầu: Có văn bản phê duyệt kết quả đấu thầu của cấp có thẩm quyền. Có hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Cógiấy bảo lãnh thực hiện hợp đồng của nhà thầu. 2.2Đối với mua sắm thiết bị (kể cả thiết bị nhập khẩu và thiết bị trong nước): Có văn bản phê duyệt kết quả đấu thầu của cấp có thẩm quyền (đối với phần thiết bịtổ chức đấu thầu) hoặc văn bản chỉ định thầu (đối với phần thiết bị không tổ chức đấu thầu). Có hợp đồng kinh tế giữa chủ đầu tư và nhà thầu cung ứng, gia công chế tạo thiết bị. Riêng đối với thiết bị nhập khẩu phải có văn bản phê duyệt hợp đồng của cấp có thẩm quyền theo quy định hiện hành. Cógiấy bảo lãnh thực hiện hợp đồng của nhà thầu (đối với phần thiết bị tổ chức đấu thầu). 2.3Đối với các công việc phải thuê tư vấn: Có văn bản phê duyệt kết quả đấu thầu của cấp có thẩm quyền (đối với công việc tổ chức đấu thầu) hoặc văn bản chỉ định thầu (đối với công việc không tổ chức đấu thầu). Có hợp đồng kinh tế giữa chủ đầu tư và nhà thầu tư vấn. 2.4Đối với một số công việc thuộc chi phí khác của dự án: Công tác đền bù, giải phóng mặt bằng phải có phương án đền bù và dự toán được duyệt. Các chi phí cấp đất, thuế đất hoặc chuyển quyền sử dụng đất phải có thông báo cuảcơ quan chuyên môn yêu cầu chủ đầu tư nộp tiền. Chi phí hoạt động của bộ máy quản lý dự án phải có dự toán được duyệt.3. Mức vốn tạm ứng: 3.1Đối với các dự án đầu tư thực hiện đấu thầu theo hợp đồng chìa khoá trao tay: Tạm ứng cho việc mua sắm thiết bị căn cứ vào tiến độ thanh toán (như quy định tại tiết 3.3 dưới đây). Phần còn lại tạm ứng 15% giá trị gói thầu, nhưng nhiều nhất không vượt kế hoạch vốn cả năm đã bố trí cho các công việc này. 3.2Đối với xây lắp: Các gói thầu có giá trị dưới 10 tỷ đồng, mức tạm ứng bằng 20% giá trị hợp đồng nhưng không vượt kế hoạch vốn hàng năm của gói thầu. Các gói thầu có giá trị từ 10 tỷ đồng đến dưới 50 tỷ đồng, mức tạm ứng bằng 15% giá trị hợp đồng nhưng không vượt kế hoạch vốn hàng năm của gói thầu. Các gói thầu có giá trị từ 50 tỷ đồng trở lên, mức tạm ứng bằng 10% giá trị hợp đồng nhưng không vượt kế hoạch vốn hàng năm của gói thầu. Trường hợp kế hoạch vốn cả năm của gói thầu bố trí thấp hơn mức vốn được tạm ứng theoquy định trên (gói thầu chưa được thanh toán đủ mức vốn tạm ứng theo tỷ lệ quy định), Kho bạc nhà nước tiếp tục thanh toán vốn tạm ứng trong kế hoạch năm saucho đến khi đạt đến mức tỷ lệ tạm ứng theo quy định. 3.3Đối với mua sắm thiết bị: Mức vốn tạm ứng là số tiền mà chủ đầu tư phải thanh toán theo hợp đồng nhưng nhiều nhất không vượt kế hoạch vốn trong năm. Trường hợp kế hoạch vốn bố trí không đủ nhu cầu vốn để thanh toán theo hợp đồng, chủ đầu tư có trách nhiệm tìm nguồn vốn bổ sung. Vốn tạm ứng được thanh toán theo tiến độ thanh toán tiền của chủ đầu tư đối với nhà thầu cung ứng, gia công chế tạo thiết bị được quy định trong hợp đồng kinh tếvà được thực hiện cho đến khi thiết bị đã nhập kho của chủ đầu tư (đối với thiết bị không cần lắp) hoặc đã được lắp đặt xong và nghiệm thu (đối với thiết bị cần lắp). 3.4Đối với các hợp đồng tư vấn, mức vốn tạm ứng tối thiểu là 25% giá trị gói thầu,nhưng không vượt kế hoạch vốn cả năm đã bố trí cho công việc phải thuê tư vấn. 3.5Đốivới công việc đền bù giải phóng mặt bằng, mức vốn tạm ứng theo yêu cầu cần thiết cho công việc đền bù nhưng không vượt kế hoạch vốn cả năm đã bố trí cho công việc đền bù giải phóng mặt bằng. 3.6Đối với một số công việc thuộc chi phí khác của dự án được cấp vốn tạm ứng, mức vốn tạm ứng theo yêu cầu cần thiết nhưng không vượt kế hoạch vốn cả năm đã bố trí cho các loại công việc đó.4. Thu hồi vốn tạm ứng: 4.1Vốn tạm ứng các hợp đồng xây lắp được thu hồi dần vào từng thời kỳ thanh toánkhối lượng xây lắp hoàn thành theo quy định sau đây: Thời điểm bắt đầu thu hồi: +Các gói thầu có giá trị dưới 10 tỷ đồng: khi thanh toán đạt 30% giá trị hợp đồng. +Các gói thầu có giá trị từ 10 tỷ đồng đến dưới 50 tỷ đồng: khi thanh toán đạt25% giá trị hợp đồng. +Các gói thầu có giá trị từ 50 tỷ đồng trở lên: khi thanh toán đạt 20% giá trị hợp đồng. Số vốn tạm ứng được thu hồi hết khi gói thầu được thanh toán khối lượng xây lắp hoàn thành đạt 80% giá trị khối lượng. Mức vốn tạm ứng thu hồi từng kỳ được xác định như sau: +Khi thanh toán khối lượng đạt đến 50% giá trị hợp đồng, mức vốn tạm ứng thu hồiđạt đến 40% tổng số vốn tạm ứng. +Khi thanh toán khối lượng đạt đến 70% giá trị hợp đồng, mức vốn tạm ứng thu hồiđạt đến 80% tổng số vốn tạm ứng. +Khi thanh toán khối lượng đạt đến 80% giá trị hợp đồng, mức vốn tạm ứng thu hồiđạt 100% tổng số vốn tạm ứng. Trường hợp vốn tạm ứng chưa thu hồi hết do gói thầu chưa được thanh toán đạt đến tỷ lệ quy định trên nhưng dự án không được ghi tiếp kế hoạch hoặc bị đình thi công,chủ đầu tư phải giải trình với Kho bạc nhà nước về tình hình sử dụng số vốn tạm ứng chưa được thu hồi, đồng thời báo cáo cấp có thẩm quyền xử lý. Trường hợp đã được thanh toán vốn tạm ứng mà gói thầu không triển khai thi công theo đúng thời hạn quy định trong hợp đồng, chủ đầu tư phải giải trình với Kho bạc nhà nước và có trách nhiệm hoàn trả số vốn đã tạm ứng. 4.2Vốn tạm ứng mua sắm thiết bị được thu hồi vào từng lần thanh toán khối lượng thiết bị hoàn thành. Đối với thiết bị không cần lắp, khi thiết bị đã được nghiệm thu và nhập kho chủ đầu tư, chủ đầu tư có trách nhiệm gửi ngay chứng từ đến Kho bạc nhà nước để làm thủ tục thanh toán khối lượng thiết bị hoàn thành và thu hồi số vốn đã tạm ứng. Đối với thiết bị cần lắp, khi thiết bị đã về đến kho chủ đầu tư, chủ đầu tư báo cáo với Kho bạc nhà nước để theo dõi; khi thiết bị đã lắp đặt xong, chủ đầu tư gửi ngay chứng từ đến Kho bạc nhà nước để làm thủ tục thanh toán khối lượng thiết bị hoàn thành và thu hồi số vốn đã tạm ứng. Kho bạc nhà nước thu hồi hết số vốn tạm ứng thiết bị khi thanh toán cho khối lượng lắp đặt hoàn thành. Trường hợp đã thanh toán vốn tạm ứng mà hết thời hạn quy định trong hợp đồng vẫn không nhận được thiết bị, chủ đầu tư phải giải trình với Kho bạc nhà nước và có trách nhiệm hoàn trả số vốn đã tạm ứng. 4.3Vốn tạm ứng cho các hợp đồng tư vấn được thu hồi vào từng lần thanh toán cho khối lượng công việc tư vấn hoàn thành theo nguyên tắc: Thời điểm thu hồi khi bắt đầu thanh toán khối lượng hoàn thành. Số vốn thu hồi bằng số vốn thanh toán nhân với (x) tỷ lệ cấp vốn tạm ứng. 4.4Vốn tạm ứng cho công việc đền bù giải phóng mặt bằng và các công việc thuộc chi phí khác của dự án được thu hồi một lần vào kỳ thanh toán khối lượng hoàn thành của công việc đó. 4.5Mức thu hồi vốn tạm ứng của các loại hợp đồng có thể cao hơn mức quy định trên đây nếu chủ đầu tư và nhà thầu thống nhất đề nghị. 4.6Trường hợp đến hết niên độ kế hoạch mà vốn tạm ứng chưa thu hồi hết do gói thầu chưa được thanh toán đạt đến tỷ lệ quy định thì tiếp tục thu hồi trong kế hoạch năm sau và không trừ vào kế hoạch vốn của năm sau. 5.Đối với một số vật tư là cấu kiện, bán thành phẩm trong xây dựng có giá trị lớn cần phải sản xuất trước để đảm bảo tiến độ xây dựng công trình và một số loại vật tư đặc chủng, vật tư cần phải dự trữ theo mùa vụ, nếu cần thiết phải tạm ứng nhiều hơn mức vốn tạm ứng theo quy định trên đây, chủ đầu tư báo cáo Bộ Tài chính (đối với dự án do các Bộ quản lý), Sở Tài chính-Vật giá (đối với dự án do tỉnh quản lý), Phòng Tài chính (đối với dự án do huyện quản lý) quyết định. Vốn tạm ứng này được thu hồi khi thanh toán cho khối lượng XDCB hoàn thành có cấu thành các loại vật tư được tạm ứng nêu trên. 6.Đối với vốn sự nghiệp có tính chất đầu tư và xây dựng: Các dự án có quy mô vốn từ 1 tỉ đồng trở lên, việc tạm ứng và thu hồi vốn tạm ứng được thực hiện như đối với vốn đầu tư XDCB. Các dự án có quy mô vốn dưới 1 tỉ đồng được tạm ứng 50% kế hoạch năm của dự án. Vốn tạm ứng được thu hồi dần vào từng kỳ thanh toán khối lượng hoàn thành và thu hồi hết trong năm kế hoạch. Số vốn tạm ứng thu hồi từng kỳ bằng số vốn thanhtoán nhân với (x) tỷ lệ tạm ứng. 7.Những dự án đầu tư có vốn nước ngoài hoặc những gói thầu tổ chức đấu thầu quốc tế mà trong Hiệp định tín dụng ký giữa Chính phủ Việt Nam và nhà tài trợ có quy định về việc tạm ứng vốn (đối tượng được tạm ứng, điều kiện và mức tạm ứng, thu hồi vốn tạm ứng) khác với các quy định nêu trên thì được thực hiện theo quy định trong Hiệp định tín dụng đã ký.
-
Section V
THANH TOÁN KHỐI LƯỢNG HOÀN THÀNH
1. Thanh toán khối lượng xây lắp hoàn thành: 1.1Khối lượng xây lắp hoàn thành theo hình thức chỉ định thầu được thanh toán là khối lượng thực hiện đã được nghiệm thu hàng tháng, theo hợp đồng, có trong kế hoạch đầu tư được giao, có thiết kế và dự toán chi tiết được duyệt theo đúng định mức, đơn giá của Nhà nước. 1.2Khối lượng xây lắp hoàn thành theo hình thức đấu thầu được thanh toán là khối lượng thực hiện đã được nghiệm thu theo hợp đồng, có trong kế hoạch đầu tư được giao. 1.3Để được thanh toán khối lượng xây lắp hoàn thành, chủ đầu tư gửi đến Kho bạc nhà nước các tài liệu sau đây: 1.3.1Trườnghợp chỉ định thầu: Văn bản phê duyệt thiết kế và dự toán chi tiết hạng mục công trình. Quyết định chỉ định thầu. Hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Biên bản nghiệm thu khối lượng xây lắp hoàn thành kèm theo bản tính giá trị khối lượng được nghiệm thu. Phiếu giá và chứng từ thanh toán. 1.3.2Trường hợp đấu thầu: Văn bản phê duyệt kết quả đấu thầu. Hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Biên bản nghiệm thu khối lượng xây lắp hoàn thành kèm theo bản tính giá trị khối lượng được nghiệm thu. Phiếu giá và chứng từ thanh toán. Những khối lượng phát sinh ngoài gói thầu phải có văn bản phê duyệt kết quả đấu thầu bổ sung (nếu khối lượng phát sinh được đấu thầu) hoặc dự toán bổ sung được duyệt (nếu khối lượng phát sinh được chỉ định thầu). 1.4Căn cứ đề nghị của chủ đầu tư và hồ sơ thanh toán do chủ đầu tư gửi đến, trong vòng 7 ngày làm việc kể từ khi nhận đủ hồ sơ hợp lệ, Kho bạc nhà nước kiểm tra,thanh toán cho chủ đầu tư và các nhà thầu và thu hồi vốn tạm ứng theo đúng quy định.2. Thanh toán khối lượng thiết bị hoàn thành: 2.1Khối lượng thiết bị hoàn thành được thanh toán là khối lượng thiết bị đã nhập kho chủ đầu tư (đối với thiết bị không cần lắp), hoặc đã lắp đặt xong và được nghiệm thu (đối với thiết bị cần lắp) và có đủ các điều kiện sau: Danh mục thiết bị phải phù hợp với quyết định đầu tư và có trong kế hoạch đầu tư đượcgiao. Có trong hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Đã được chủ đầu tư nhập kho (đối với thiết bị không cần lắp) hoặc đã lắp đặt xong và nghiệm thu (đối với thiết bị cần lắp đặt). 2.2Để được thanh toán khối lượng thiết bị hoàn thành, chủ đầu tư gửi đến Kho bạc nhà nước các tài liệu sau đây: Hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Hoá đơn kiêm phiếu xuất kho (đối với thiết bị mua trong nước) hoặc bộ chứng từ nhập khẩu (đối với thiết bị nhập khẩu). Phiếu nhập kho (đối với thiết bị không cần lắp) hoặc phiếu giá thanh toán khối lượng lắp đặt thiết bị (đối với thiết bị cần lắp). Các chứng từ vận chuyển, bảo hiểm, thuế, phí lưu kho. Phiếu giá và chứng từ thanh toán. 2.3Căn cứ đề nghị của chủ đầu tư và hồ sơ thanh toán do chủ đầu tư gửi đến, trong vòng 7 ngày làm việc kể từ khi nhận đủ hồ sơ hợp lệ, Kho bạc nhà nước kiểm tra,thanh toán cho chủ đầu tư và các nhà thầu và thu hồi vốn tạm ứng theo đúng quy định.3. Thanh toán khối lượng công tác tư vấn hoàn thành: 3.1Khối lượng công tác tư vấn hoàn thành được thanh toán là khối lượng thực hiện được nghiệm thu phù hợp với hợp đồng kinh tế và có trong kế hoạch đầu tư được giao. 3.2Để được thanh toán, chủ đầu tư gửi đến Kho bạc nhà nước các tài liệu sau: Quyết định trúng thầu hoặc chỉ định thầu. Hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. Biên bản nghiệm thu khối lượng công việc tư vấn hoàn thành. Chứng từ thanh toán. 3.3Căn cứ đề nghị của chủ đầu tư và hồ sơ thanh toán do chủ đầu tư gửi đến, trong vòng 7 ngày làm việc kể từ khi nhận đủ hồ sơ hợp lệ, Kho bạc nhà nước kiểm tra,thanh toán cho các nhà thầu và thu hồi vốn tạm ứng theo đúng quy định.4. Thanh toán khối lượng chi phí khác: 4.1Ngoài các công việc đã thuê tư vấn, các loại công việc khác thuộc chi phí khác của dự án được thanh toán khi đã có đủ các căn cứ chứng minh công việc đã được thực hiện như sau: Đối với lệ phí cấp đất xây dựng, thuế đất hoặc thuế chuyển quyền sử dụng đất phải có hoá đơn, chứng từ hợp lệ của cơ quan thu tiền. Đối với chi phí đền bù, giải phóng mặt bằng phải có phương án và dự toán đền bù được duyệt, bản xác nhận khối lượng đền bù đã thực hiện. Đối với chi phí phá dỡ vật kiến trúc và thu dọn mặt bằng xây dựng phải có dự toán được duyệt, hợp đồng, biên bản nghiệm thu. Đối với chi phí bộ máy quản lý dự án phải có dự toán được duyệt, kế hoạch tiền mặt,bảng kê các chi phí, các chứng từ liên quan. Đối với chi phí lập và thẩm định thiết kế, dự toán phải có hợp đồng, biên bản nghiệm thu. Các chi phí khởi công, nghiệm thu, chạy thử, khánh thành cần phải có dự toán được duyệt và bảng kê chi phí. Các chi phí chuyên gia, đào tạo công nhân kỹ thuật và cán bộ quản lý sản xuất cần phải có hợp đồng kinh tế, dự toán chi phí được duyệt. Đối với chi phí bảo hiểm công trình phải có hợp đồng bảo hiểm. Đối với các chi phí trong công tác chuẩn bị đầu tư, chuẩn bị thực hiện dự án phải có dự toán được duyệt, hợp đồng kinh tế, bản nghiệm thu khối lượng công việc hoặc báo cáo kết quả công việc hoàn thành. 4.2Căn cứ đề nghị của chủ đầu tư và hồ sơ thanh toán do chủ đầu tư gửi đến, trong vòng 7 ngày làm việc kể từ khi nhận đủ hồ sơ hợp lệ, Kho bạc nhà nước kiểm tra,thanh toán cho các nhà thầu và thu hồi vốn tạm ứng theo đúng quy định. 5.Số vốn thanh toán cho từng hạng mục công trình không được vượt dự toán hoặc giá trúng thầu; tổng số vốn thanh toán cho dự án không được vượt tổng dự toán và tổng mức đầu tư đã được phê duyệt. Số vốn thanh toán cho dự án trong năm (bao gồm cả tạm ứng và thanh toán khối lượng hoàn thành) nhiều nhất không vượt kế hoạch vốn cả năm đã bố trí cho dự án. 6.Trong các tài liệu do chủ đầu tư gửi cho cơ quan Kho bạc nhà nước, có loại tài liệu chỉ gửi một lần cho toàn bộ dự án và loại tài liệu gửi từng lần khi đề nghị thanh toán. Các tài liệu gửi một lần bao gồm: báo cáo nghiên cứu khả thi(hoặc báo cáo đầu tư), quyết định đầu tư, quyết định phê duyệt thiết kế kỹ thuật và tổng dự toán, các tài liệu về dự toán, văn bản phê duyệt kết quả đấu thầu, hợp đồng kinh tế giữa chủ đầu tư và nhà thầu. 7.Những dự án đầu tư có vốn nước ngoài hoặc những gói thầu tổ chức đấu thầu quốc tế mà trong Hiệp định tín dụng ký giữa Chính phủ Việt Nam với nhà tài trợ có quy định về việc thanh toán khác với các quy định nêu trên thì được thực hiện theo quy định trong Hiệp định tín dụng đã ký. 8.Chủ đầu tư phải bố trí đủ vốn trong kế hoạch hàng năm để mua bảo hiểm công trình xây dựng. Nhà nước không thanh toán cho chủ đầu tư để bù đắp các chi phí thiệt hại, rủi ro thuộc phạm vi bảo hiểm nếu chủ đầu tư không mua bảo hiểm công trình xây dựng theo quy định hiện hành. 9.Đối với vốn sự nghiệp có tính chất đầu tư và xây dựng: Các dự án có quy mô vốn từ 1 tỉ đồng trở lên, việc thanh toán khối lượng hoàn thành thực hiện theo chế độ quản lý vốn đầu tư hiện hành. Các dự án có quy mô vốn dưới 1 tỉ đồng, khi có khối lượng hoàn thành được nghiệm thu, chủ đầu tư lập hồ sơ đề nghị thanh toán gửi Kho bạc nhà nước, bao gồm: Biên bản nghiệm thu khối lượng hoàn thành. Bảng tính chi tiết giá trị khối lượng thanh toán. Phiếu giá hoặc bảng kê (đối với các khoản chi phí khác không dùng phiếu giá) và chứng từ thanh toán. Căn cứ vào hạn mức kinh phí do cơ quan Tài chính cấp, Kho bạc nhà nước kiểm soát,thanh toán cho đơn vị thụ hưởng và thu hồi số vốn đã tạm ứng (nếu có). 10.Đối với một số dự án đặc biệt quan trọng cần phải có cơ chế tạm ứng, thanh toánvốn khác với các quy định trên đây, sau khi có ý kiến của cấp có thẩm quyền, Bộ Tài chính sẽ có văn bản hướng dẫn riêng.
-
Section VI
CHẾ ĐỘ BÁO CÁO, QUYẾT TOÁN, KIỂM TRA
CHẾ ĐỘ BÁO CÁO, QUYẾT TOÁN, KIỂM TRA
1.Định kỳ ngày 20 hàng tháng và ngày 10 của tháng đầu quý sau, chủ đầu tư có trách nhiệm báo cáo tình hình thực hiện đầu tư, tình hình nhận vốn, sử dụng vốn trong tháng hoặc quý trước gửi cơ quan Kho bạc nhà nước, đồng gửi cấp quyết định đầu tư. Riêng đối với các dự án nhóm A, chủ đầu tư gửi báo cáo cho cơ quanKho bạc nhà nước, Bộ hoặc UBND tỉnh, Bộ Kế hoạch và Đầu tư, Bộ Tài chính, Bộ Xây dựng, Tổng cục Thống kê để tổng hợp báo cáo Thủ tướng Chính phủ.
Kết thúc năm kế hoạch, chủ đầu tư có trách nhiệm báo cáo tình hình thực hiện kế hoạch, báo cáo kế toán đơn vị chủ đầu tư theo quy định hiện hành; khi dự án đầu tư hoàn thành, chủ đầu tư có trách nhiệm lập báo cáo quyết toán vốn đầu tư theoquy định về chế độ quyết toán vốn đầu tư.
Trường hợp quyết toán của dự án đầu tư hoàn thành được duyệt mà số vốn được quyết toánthấp hơn số vốn đã thanh toán cho dự án, chủ đầu tư có trách nhiệm thu hồi lại của nhà thầu để hoàn trả cho Nhà nước số vốn thanh toán thừa.
2.Hàng quý và kết thúc năm kế hoạch, các Bộ và UBND các tỉnh có trách nhiệm tổng hợp tình hình thực hiện kế hoạch đầu tư, tình hình thanh toán vốn của các dự án thuộc phạm vi quản lý gửi Bộ Tài chính, Bộ Kế hoạch và Đầu tư, Bộ Xây dựng,Tổng cục Thống kê theo quy định.
3.Cơ quan Kho bạc nhà nước, cơ quan Tài chính trung ương và địa phương thực hiện chế độ thông tin báo cáo tình hình thanh toán vốn, tình hình quyết toán dự án hoàn thành và các thông tin cần thiết khác theo quy định của Bộ Tài chính về chế độ thông tin báo cáo trong lĩnh vực đầu tư XDCB.
Kết thúc niên độ kế hoạch, Kho bạc nhà nước quyết toán với cơ quan Tài chính về vốn ngân sách đã nhận, đã thanh toán cho các dự án theo quy định về quyết toánNSNN.
4.Các Bộ, UBND các tỉnh, cơ quan Tài chính và cơ quan Kho bạc nhà nước có chế độ kiểm tra định kỳ và đột xuất các chủ đầu tư về tình hình sử dụng vốn tạm ứng,vốn thanh toán khối lượng hoàn thành và chấp hành chính sách, chế độ tài chính đầu tư phát triển của Nhà nước. -
Section VII
TRÁCH NHIỆM VÀ QUYỀN HẠN CỦA CÁC CƠ QUAN CÓ LIÊN QUAN
1. Đối với chủ đầu tư: Thực hiện chức năng, nhiệm vụ được giao theo Quy chế Quản lý đầu tư và xây dựng.Tiếp nhận và sử dụng vốn đúng mục đích, đúng đối tượng, tiết kiệm và có hiệu quả. Chấp hành đúng quy định của pháp luật về chế độ quản lý tài chính đầu tưvà xây dựng. Chịu trách nhiệm về sự đúng đắn, hợp pháp của khối lượng dự án khi thanh toán (khối lượng phải theo thiết kế bản vẽ thi công hoặc thiết kế kĩ thuật thi công, chất lượng đảm bảo theo yêu cầu thiết kế); đảm bảo tính chính xác, hợp pháp, hợp lệ của các số liệu, tài liệu cung cấp cho Kho bạc nhà nước và các cơ quan chức năng của Nhà nước. Khi có khối lượng XDCB đã đủ điều kiện theo hợp đồng, tiến hành nghiệm thu kịp thời, lập đầy đủ hồ sơ thanh toán và đề nghị thanh toán cho nhà thầu. Báo cáo kịp thời, đầy đủ theo quy định cho cơ quan quyết định đầu tư và các cơ quan nhà nước có liên quan; cung cấp đủ hồ sơ, tài liệu, tình hình theo quy định choKho bạc nhà nước và cơ quan Tài chính để phục vụ cho công tác quản lý và thanhtoán vốn; chịu sự kiểm tra của Kho bạc nhà nước, cơ quan Tài chính và cơ quan quyết định đầu tư về tình hình sử dụng vốn đầu tư và chấp hành chính sách, chế độ tài chính đầu tư phát triển của Nhà nước. Thực hiện kế toán nhận và sử dụng vốn đầu tư theo quy định hiện hành về kế toán đơn vị chủ đầu tư; quyết toán vốn đầu tư hoàn thành theo quy định. Được yêu cầu thanh toán vốn khi đã có đủ điều kiện và yêu cầu cơ quan Kho bạc nhà nước trả lời và giải thích những điểm thấy chưa thoả đáng trong việc thanh toán vốn.2. Đối với các Bộ và UBND các tỉnh, huyện: Hướng dẫn, kiểm tra, đôn đốc các chủ đầu tư thuộc phạm vi quản lý thực hiện kế hoạch đầu tư, tiếp nhận và sử dụng vốn đầu tư đúng mục đích, đúng chế độ Nhà nước. Báo cáo tình hình thực hiện kế hoạch đầu tư theo quy định. Trong phạm vi thẩm quyền được giao, chịu trách nhiệm trước Chính phủ và pháp luật nhànước về những quyết định của mình.3. Đối với cơ quan Kho bạc nhà nước: Kho bạc nhà nước trung ương quy định quy trình, thủ tục, hồ sơ chứng từ gửi một lần và gửi từng lần trong quá trình tạm ứng, thanh toán vốn. Hướng dẫn chủ đầu tư mở tài khoản để tạm ứng và thanh toán vốn. Thanhtoán vốn kịp thời, đầy đủ cho dự án khi đã có đủ điều kiện. Cóý kiến rõ ràng bằng văn bản cho chủ đầu tư đối với những khoản giảm thanh toánhoặc từ chối thanh toán, trả lời các thắc mắc của chủ đầu tư trong việc thanhtoán vốn. Trường hợp phát hiện quyết định của các cấp có thẩm quyền trái với quy định hiện hành,phải có văn bản đề nghị xem xét lại và nêu rõ ý kiến đề xuất. Nếu quá thời gianquy định mà không được trả lời thì được quyền giải quyết theo đề xuất của mình;nếu được trả lời mà xét thấy không thoả đáng thì vẫn giải quyết theo ý kiến cuảcấp có thẩm quyền, đồng thời phải báo cáo lên cơ quan có thẩm quyền cao hơn để xem xét. Thực hiện chế độ thông tin báo cáo và quyết toán vốn đầu tư và vốn sự nghiệp có tính chất đầu tư và xây dựng thuộc nguồn vốn NSNN theo quy định của Luật NSNN và hướng dẫn của Bộ Tài chính. Được quyền yêu cầu chủ đầu tư cung cấp hồ sơ, tài liệu, thông tin theo chế độ quy định để phục vụ cho công tác kiểm soát thanh toán vốn. Được phép tạm ngừng thanh toán vốn hoặc thu hồi số vốn mà chủ đầu tư sử dụng sai mục đích, không đúng đối tượng hoặc trái với chế độ quản lý tài chính của Nhà nước,đồng thời báo cáo Bộ Tài chính để xử lý; được quyền từ chối thanh toán vốn cho các dự án mà chủ đầu tư không thực hiện nghiêm túc chế độ lập kế hoạch vốn đầu tư hàng quý, chế độ báo cáo theo quy định của Quy chế Quản lý đầu tư và xây dựng và Thông tư này. Không tham gia vào các Hội đồng nghiệm thu khối lượng XDCB hoàn thành. Tổ chức công tác kiểm soát, thanh toán vốn theo quy trình nghiệp vụ thống nhất,đảm bảo quản lý vốn chặt chẽ, thanh toán kịp thời, đầy đủ, thuận tiện cho chủ đầu tư. Chịu trách nhiệm trước Bộ trưởng Bộ Tài chính và pháp luật của Nhà nước về việc nhận, sử dụng vốn NSNN và thanh toán trong đầu tư xây dựng.4. Đối với cơ quan Tài chính các cấp: Đảm bảo đủ nguồn vốn và chuyển vốn kịp thời cho cơ quan Kho bạc nhà nước để Kho bạc nhà nước thanh toán cho các dự án. Báo cáo và quyết toán vốn đầu tư phát triển theo quy định của Luật NSNN. Phối hợp với các Bộ, các tỉnh hướng dẫn và kiểm tra các chủ đầu tư về chấp hành chế độ, chính sách tài chính đầu tư phát triển, tình hình quản lý, sử dụng vốn đầu tư. Được quyền yêu cầu chủ đầu tư cung cấp các tài liệu, thông tin cần thiết để phục vụ cho công tác quản lý nhà nước về tài chính đầu tư phát triển, bao gồm các tài liệu phục vụ cho thẩm định dự án đầu tư và bố trí kế hoạch hàng năm, các tài liệu báo cáo định kỳ theo quy định về chế độ thông tin báo cáo, các tài liệu phục vụ thẩm tra quyết toán vốn đầu tư. Phần III ĐIỀU KHOẢN THI HÀNH 1.Thông tư này có hiệu lực thi hành sau 15 ngày kể từ ngày ký và thay thế Thông tưsố 135/1999/TT-BTC ngày 19/11/1999 của Bộ Tài chính hướng dẫn việc quản lý,thanh toán vốn đầu tư và vốn sự nghiệp có tính chất đầu tư và xây dựng từ nguồnNSNN và Thông tư số 76 TC/ĐTPT ngày 1/11/1997 của Bộ Tài chính hướng dẫn việc quản lý, cấp phát vốn đầu tư XDCB thuộc ngân sách huyện, xã. 2.Đối với các khoản chi đầu tư phát triển khác từ NSNN (chi dự trữ nhà nước, chi hỗ trợ vốn lưu động cho doanh nghiệp, chi góp vốn cổ phần liên doanh, chi cho nước ngoài vay và viện trợ nước ngoài, chi cho các quỹ hỗ trợ phát triển) thực hiện theo các văn bản hướng dẫn riêng của từng loại chi nói trên. 3.Đối với các dự án đầu tư từ các nguồn vốn khác của Nhà nước cũng vận dụng những nguyên tắc thanh toán theo quy định tại Thông tư này./.
Basis for the status