Article 25. Making, submission and approval of finalization reports
Circular 55/2016/TT-BTC — Quy định một số nội dung về quản lý tài chính đối với dự án đầu tư theo hình thức đối tác công tư và chi phí lựa chọn nhà đầu tư.
Finalization of works of completed ppp projects
1. Agency making finalization reports: the project owner, or investor in case no project enterprise is established.
2. Dossier submitted for approval of finalization reports (with one set submitted to the agency verifying and approving finalization reports): to comply with the Ministry of Finance’s Circular on finalization of state-funded completed projects, project contract and contract annexes.
3. Competence to approve finalization reports: ministers, heads of ministerial-level agencies, chairpersons of provincial-level People’s Committees, or chairpersons of district-level People’s Committees in case they are authorized by provincial-level People’s Committees to sign and perform project contracts.
4. Agencies verifying finalization reports:
a/ Functional units under ministries or sectors shall verify finalization reports of projects managed by ministries or sectors;
b/ Provincial-level Finance Departments shall verify finalization reports of projects managed by provincial-level People’s Committees;
c/ District-level Finance-Planning Divisions shall verify finalization reports of projects with their contracts signed and performed by district-level People’s Committees.
5. Audit of finalization reports
Competent state agencies shall agree with investors on selecting capable and experienced independent audit firms to audit the value of investment capital for construction of project works.
6. Contents of verification of finalization reports must comply with the Ministry of Finance’s Circular on finalization of state-funded completed projects.
Article 25, Circular 55/2016/TT-BTC