Article 20
Circular 55/2016/TT-BTC — Quy định một số nội dung về quản lý tài chính đối với dự án đầu tư theo hình thức đối tác công tư và chi phí lựa chọn nhà đầu tư.
Payment of the state’s investment capital for implementation of ppp projects
Payment of the State’s investment capital as support for building project works or auxiliary works and organizing payment of compensations, ground clearance and resettlement
1. Dossier for payment
1.1. Legal dossier for single submission
The agency assigned to manage the State’s capital amount shall send the project’s legal dossier as a basis for payment control to the state treasury office where it opens its account before or at the time of request for initial payment of the State’s capital for project implementation. A dossier must comprise:
a/ Project contract, contract annexes (if any), and legal documents enclosed with the project contract;
b/ Contract between the investor or project enterprise and the contractor or supplier and enclosed documents, such as contract annexes, payment-related specific conditions and general conditions; task assignment paper or internal contract, in case the investor itself/himself/herself implements the project;
c/ Cost estimates and a competent authority’s decision approving cost estimates for each activity or item of the project, in case the investor or project enterprise implements the project without signing a contract. A plan on payment of compensation, ground clearance support and resettlement approved by a competent authority, particularly for compensation, ground clearance support and resettlement work.
1.2. Dossier for payment
a/ In case the project enterprise and investor jointly form a party to the project contract under Point a, Clause 3, Article 31 of Decree No. 15/2015/ND-CP or the investor directly implements a BT project or group-C project under Clause 2, Article 42 of Decree No. 15/2015/ND-CP:
- For activities carried out by the investor or project enterprise under a construction contract signed with the contractor or supplier:
+ Written record of acceptance test of the value of completed volume and table calculating the value of contractual completed volume requested for payment, made by the investor according to Appendix No. 01. If an additional volume arises outside the contract, the investor shall make a written record of acceptance test of the value of this volume and a table calculating such value requested for payment according to Appendix No. 02;
+ Written request for payment of investment capital for completed volume, made by the agency assigned to manage the State’s investment capital used for implementation of PPP projects according to Appendix No. 03;
+ Money transfer document, issued under the Ministry of Finance’s regulations on accounting documents.
- For activities carried out by the investor or project enterprise without signing a contract:
+ Written record of acceptance test of the value of completed volume;
+ Approved cost estimates for each activity;
+ Written request for payment of the investment capital for completed volume, made by the agency assigned to manage the State’s investment capital used for implementation of PPP projects according to Appendix No. 03;
+ Money transfer document, issued under the Ministry of Finance’s regulations on accounting documents.
b/ In case the competent state agency or investor issues a document permitting the project enterprise to take over and exercise and perform the rights and obligations of the investor as stated in the investment registration certificate and project contract under Point b, Clause 3, Article 31 of Decree No. 15/2015/ND-CP:
- For activities carried out by the project enterprise under a construction contract signed with the contractor or supplier:
+ Written record of acceptance test of the value of completed volume and table calculating the value of contractual completed volume requested for payment, made by the investor according to Appendix No. 01. If an additional volume arises outside the contract, the investor shall make a written record of acceptance test of the value of this volume and a table calculating such value requested for payment according to Appendix No. 02;
+ Written request for payment of the investment capital for completed volume to the project enterprise, made by the agency assigned to manage the State’s investment capital used for implementation of PPP projects according to Appendix No. 03;
+ Money transfer document, issued under the Ministry of Finance’s regulations on accounting documents.
- For activities carried out by the project enterprise without signing a contract:
+ Written record of acceptance test of the value of completed volume;
+ Approved cost estimates for each activity;
+ Written request for payment of the investment capital for completed volume, made by the agency assigned to manage the State’s investment capital used for implementation of PPP projects according to Appendix No. 03;
+ Money transfer document, issued under the Ministry of Finance’s regulations on accounting documents.
1.3. Time limit for payment of the State’s investment capital
a/ Annual plan on allocation of funds as the State’s investment capital used for the project implementation only covers payment for the completed volume tested for acceptance under regulations (by December 31 of the plan year); the time limit for payment for the completed volume must comply with regulations (through January 31 of the subsequent year);
b/ If the State’s investment capital has not yet been fully paid in the plan year, the competent state agency shall report such to the competent authority for allowing extension of the project implementation and capital payment duration under regulations.
2. Advance payment and payment of the State’s investment capital as support for the activities prescribed at Point c, Clause 2, Article 11 of Decree No. 15/2015/ND-CP
a/ In case the State’s investment capital is provided for carrying out all activities of building auxiliary works and organizing payment of compensation, ground clearance and resettlement:
The dossier and documents for advance payment and payment of capital for a project to serve the paying agency’s capital control and payment; contents of advance payment and payment for completed volume; the State Treasury’s payment control principles; and the time limits for advance payment and payment must comply with the Ministry of Finance’s regulations on management and payment of investment capital and amending or supplementing documents (if any).
b/ In case the State’s investment capital is provided for carrying out part of activities of construction of building auxiliary works and organizing payment of compensation, ground clearance and resettlement: The order, procedures, dossier and time limit for payment must comply with Articles 19 and 20 of this Circular.
Article 20, Circular 55/2016/TT-BTC