Article 13. Contents of a financial plan
Circular 55/2016/TT-BTC — Quy định một số nội dung về quản lý tài chính đối với dự án đầu tư theo hình thức đối tác công tư và chi phí lựa chọn nhà đầu tư.
Financial plans of ppp projects
1. Total investment amount.
2. Structure of investment sources:
a/ Equity;
b/ The State’s investment capital as support for construction of works or auxiliary works and for organizing payment of compensations, ground clearance and resettlement as prescribed in Clause 2, Article 11 of Decree No. 15/2015/ND-CP;
c/ Funds raised by investors.
3. Fund raising plan:
a/ Equity:
- Total;
- Fund raising plan;
- Disbursement schedule.
b/ The State’s investment capital as support (if any) prescribed in Clause 2, Article 11 of Decree No. 15/2015/ND-CP:
- Total;
- Funding sources;
- Contents of support;
- Disbursement schedule.
c/ Raised funds (commercial loans, concessional credit, foreign loans, and other funding sources):
- Total raised funds (by each type of funding source);
- Time of loan borrowing and repayment and grace period (by each type of loan);
- Interest rate for each type of loans and average interest rate;
- Currency of loans and payment exchange rate;
- Conditions to raise funds;
- Necessary expenses for the fund raising (guarantee fee, commitment fee, credit insurance and brokerage);
- Disbursement schedule (by each type of fund);
- Plan on repayment of raised funds (by each type of fund).
4. Proposals on incentives (if any) to ensure implementation of the project’s financial plan.
5. The investor’s equity profit.
6. Implementation duration, operation, capital recovery and profit of the project.
7. Plan on recovery of investment capital and investor’s profit:
a/ Estimated lawful revenues;
b/ Estimated prices and service charge rates;
c/ Estimated turnover from every lawful revenue;
d/ For construction-transfer-lease (BTL) contracts and build-lease-transfer (BLT) contracts, a plan on the State’s payment to the investor is required;
dd/ For BT contracts, a land area with an equivalent value shall be projected for payment to the investor.
8. Criteria for assessing feasibility of a financial plan:
a/ The competent authority shall decide to select an investment project based on the following criteria:
- Net present value (NPV);
- Internal rate of return (IRR);
- Benefit-cost (B/C) ratio;
- Return on equity (ROE) rate;
- Project contract term;
- Sensitivity of the above financial criteria as a result of a change in the total investment amount, operation expense, turnover or project contract term.
b/ Based on specific characteristics of a project, the related state management agency may set additional financial criteria such as debt to equity ratio, debt service ratio, rapid conversion rate for property, solvency ratio, and capital preservation measures under current regulations in order to select an efficient investment project.
Article 13, Circular 55/2016/TT-BTC