Article 4. Formulation, appraisal and approval of project proposals under Section 1, Chapter III of Decree No. 15/2015/ND-CP
Circular 02/2016/TT-BKHĐT — Hướng dẫn lựa chọn sơ bộ dự án, lập, thẩm định, phê duyệt đề xuất dự án và báo cáo nghiên cứu khả thi dự án đầu tư theo hình thức đối tác công tư.
1. Detailed process
a/ Formulating project proposals;
b/ Appraising project proposals;
c/ Proposing and approving policies on use of state investment capital for project implementation (if any);
d/ Approving project proposals;
dd/ Announcing projects.
2. Formulation of a project proposal
a/ Based on the guidance in Appendix I to this Circular, the project-preparing unit shall formulate the project proposal as specified in Article 16 of Decree No. 15/2015/ND-CP. For a project with construction components, the project proposal must contain a preliminary design (or a basic design, for group-C projects) as prescribed by the construction law. For a project without construction components, the project proposal must contain a preliminary design (or a basic design, for group-C projects) as prescribed by specialized laws;
b/ The project-preparing unit shall submit 1 set of the project proposal dossier to the minister, ministerial-level agency head or provincial-level People’s Committee chairperson; and at the same time send 4 sets of the dossier to the appraising unit.
c/ A project proposal dossier must comprise:
- A written request for approval of the project proposal, covering legal bases for formulation of the project proposal, explanations about main contents of the project proposal and recommendations;
- The draft project proposal;
- Competent persons’ approval for formulation of the project proposal in the PPP form;
- Relevant papers and legal documents.
3. Appraisal of a project proposal
a/ The appraising unit shall receive the project proposal dossier from the project-preparing unit and conduct the appraisal according to Points b, c, d and dd of this Clause;
b/ The appraising unit shall consult in writing agencies and units related to the project proposal and, when necessary, may hold appraisal meetings. The appraising unit shall seek opinions on the preliminary design (or basic design for group-C projects) from a construction agency in accordance with the construction law, for projects with construction components, or from a specialized agency in accordance with specialized laws, for projects without construction components;
c/ Based on the guidance in Appendix II to this Circular, the appraising unit shall formulate an project proposal appraisal report. A project proposal to be recommended by the appraising unit for approval must fully meet the conditions specified in Article 15 of Decree No. 15/2015/ND-CP;
d/ The appraising unit shall submit a project proposal appraisal dossier to the minister, ministerial-level agency head or provincial-level People’s Committee chairperson. A dossier must comprise:
- A project proposal appraisal report;
- The draft project proposal;
- Relevant papers and legal documents.
dd/ The time limit for appraisal of a project proposal is 25 days from the date of receiving a complete dossier, excluding the time for approving the policy on use of state investment capital specified in Clause 4, Article 17 of Decree No. 15/2015/ND-CP.
4. For projects using the State’s investment capital, ministries, ministerial-level agencies and provincial-level People’s Committees shall propose competent agencies to approve policies on use of state investment capital for project implementation in accordance with the law on public investment.
5. Approval of a project proposal
a/ Based on the project-preparing unit’s project proposal dossier, the appraising unit’s appraisal dossier, and a competent agency’s decision on the policy on use of state investment capital for project implementation in accordance with the law on public investment (if any), the minister, ministerial-level agency head and provincial-level People’s Committee chairperson shall approve the project proposal within 5 days. For projects subject to investment policy approval by ministers, heads of ministerial-level agencies or provincial-level People’s Committee chairpersons as decentralized by the law on public investment, project proposals may be approved together with the policy on use of state investment capital for project implementation;
b/ A project proposal approval decision must have the following principal contents:
- Name of the project;
- Name of the state agency competent to sign the contract with the investor;
- Name of the project-preparing unit;
- Location, size and capacity of the project, land area;
- Technical requirements;
- Total estimated investment capital;
- State investment capital for project implementation (if any);
- Type of project contract;
- Preliminary financial plan;
- Term of project contract;
- Investment incentives and guarantees;
- Other contents.
6. Ministries, ministerial-level agencies and provincial-level People’s Committees shall announce projects under Article 18 of Decree No. 15/2015/ND-CP. Information to be published and information publishing order must comply with the bidding law.
Article 4, Circular 02/2016/TT-BKHĐT