Circular 02/2007/TT-BXD
Hướng dẫn một số nội dung về: lập, thẩm định, phê duyệt dự án đầu tư xây dựng công trình; giấy phép xây dựng và tổ chức quản lý dự án đầu tư xây dựng công trình quy định tại Nghị định số 16/2005/NĐ-CP ngày 07/02/2005 và Nghị định số 112/2006/NĐ-CP ngày 29/09/2006 của Chính phủ
- Construction and urban planning
- Repealed
English translation (unofficial)
CIRCULAR
Guiding a number of contents regarding formulation, evaluation and approval of investment projects on the construction of works; construction permits; and management of investment projects on the construction of works provided for in the Government's Decree no. 16/2005/ND-CP of February 7, 2005, and Decree no. 112/2006/ND-CP of September 29, 2006
Pursuant to the Government's Decree No. 36/2003/ND-CP of April 4, 2003, defining the functions, tasks, powers and organizational structure of the Ministry of Construction;
Pursuant to the Government's Decree No. 16/2005/ND-CP of February 7, 2005, on the management of investment projects on the construction of works;
Pursuant to the Government's Decree No. 112/2006/ND-CP of September 29, 2006, amending and supplementing a number of articles of the Government's Decree No. 16/2005/ND-CP on the management of investment projects on the construction of works;
The Ministry of Construction provides guidance on a number of contents regarding formulation, evaluation and approval of investment projects on the construction of works; construction permits; and management of investment projects on the construction of works provided for in the Government's Decree No. 16/2005/ND-CP of February 7, 2005, on the management of investment projects on the construction of works (below referred to as Decree 16/CP for short) and the Government's Decree No. 112/2006/ND-CP of September 29, 2006, amending and supplementing a number of articles of the Government's Decree No. 16/2005/ND-CP on the management of investment projects on the construction of works (below referred to as Decree 112/CP for short) as follows:
Part I
GUIDANCE ON THE FORMULATION, EVALUATION AND APPROVAL OF INVESTMENT PROJECTS ON THE CONSTRUCTION OF WORKS
I. Determination of investors of projects funded with state budget capital
1. For projects in which the investment is decided by the Prime Minister, investors may be any of the following agencies or organizations: ministries, ministerial-level agencies, government-attached agencies or other central agencies (collectively referred to as ministerial-level agencies), People's Committees of provinces or centrally run cities (collectively referred to as provincial-level People's Committees) and state enterprises.
2. For projects in which the investment is decided by ministers, heads of ministerial-level agencies or presidents of People's Committees of all levels, investment deciders shall assign units that will manage and/or use the works to act as investors.
When a unit that will manage and/or use the work fails to meet the organizational structure, personnel, time or other necessary conditions for performance of the tasks and powers of an investor, or when the unit managing and/or using the work is not yet identified, the investment decider shall assign a unit which satisfies the above conditions to act as investor. Specifically as follows:
When the unit that will manage and/or use the work is not assigned to act as investor, such unit shall issue a document appointing a person to join the investor in managing the construction investment project and receive the work for putting it to exploitation and use. The investor shall arrange an appropriate position for the person of the unit that will manage and/or use the work to take part in managing the work right from the formulation of the project to the hand-over and putting of the work to use, ensuring the efficiency and objectives of the project. When the investor sets up a project management unit, one of the deputy directors of the project management unit must be the person of the unit that will manage and/or use the work.
When the unit that will manage and/or use the work is not yet identified, such unit shall be identified in the course of execution of the project in order to join the investor in testing before acceptance and receiving the work for putting it to exploitation and use.
II. For group-A projects not included in plannings
1. Before formulating an investment project on work construction which is not yet included in a branch planning or does not conform to a branch planning approved by a competent authority, the investor shall report it to the branch-managing ministry, which shall consider and supplement the planning according to its competence or submit the project to the Prime Minister for approval. For example: If an investment project on the construction of a power plant in Province X is not yet included in the electricity industry planning, before formulating the project, the investor shall report it to the Ministry of Industry for the latter to consider and adjust the planning according to its competence or submit the project to the Prime Minister for approval and additional inclusion in the electricity industry planning.
2. Before formulating an investment project on work construction which is not yet included in a construction planning or when a construction planning is not yet available, the investor shall report it to the provincial-level People's Committee for the latter to consider and approve the location, scale and total ground area of the project; at the same time, the provincial-level People's Committee shall adjust or formulate the construction planning according to regulations.
III. Formulation, evaluation and approval of investment projects on the construction of works
1. Formulation of an investment project on work construction:
After registering investment or being granted an investment certificate under the investment law, the investor shall formulate an investment project on work construction, carry out procedures for submission of the project for approval, and take subsequent steps as stipulated in the Construction Law, Decree 16/CP, Decree 112/CP and this Circular.
2. Competence to evaluate an investment project on work construction:
a/ The investment decider shall evaluate an investment project on work construction before approval. The project evaluator is a professional unit of the investment decider as provided for in Clause 5, Article 1 of Decree 112/CP. For a project in which the investment in decided under authorization, the project evaluator is a professional unit of the person authorized to decide on investment.
b/ Competence to evaluate basic designs must comply with Clause 5, Article 1 of Decree 112/CP.
For group-B and group-C projects in which the investment is decided by the Ministry of Industry, the Ministry of Agriculture and Rural Development, the Ministry of Transport, the Ministry of Construction, economic groups or state corporations, those ministries, groups or corporations shall themselves evaluate basic designs after obtaining localities' opinions on construction plannings and environmental protection. Specifically:
The Ministry of Industry shall itself evaluate basic designs of works under investment projects on the building of mines or oil and gas works, power plants, electricity transmission lines, transformer stations, production of chemicals or industrial explosives, machine building, metallurgy, or specialized industrial works of groups B and C, in which the investment is decided by the Ministry of Industry.
The Ministry of Agriculture and Rural Development shall itself evaluate basic designs of works under investment projects on the building of irrigation works and dykes of groups B and C, in which the investment is decided by the Ministry of Agriculture and Rural Development.
The Ministry of Transport shall itself evaluate basic designs of works under investment projects on the building of traffic works of groups B and C, in which the investment is decided by the Ministry of Transport.
The Ministry of Construction shall itself evaluate basic designs of works under investment projects on the building of civil works, construction material industry and urban technical infrastructure of groups B and C, in which the investment is decided by the Ministry of Construction.
Economic groups and state corporations shall themselves evaluate basic designs of works under projects of groups B and C in which the investment is decided by themselves if those projects are in the specialized domains assigned by the State to them for management. For example: The Electricity of Vietnam Group (EVN) which is assigned by the State to manage the national power grid may itself evaluate basic designs of works under electricity grid projects of groups B and C in which the investment is decided by itself. For other projects in which the investment is decided by EVN, competent state agencies defined in Clause 5, Article 1 of Decree 112/CP shall evaluate basic designs.
3. Order and procedures for the evaluation and approval of an investment project on work construction:
a/ The investor shall make and send the project dossier to the project evaluator for evaluation before submitting it to the person with investment-deciding competence for approval.
A project dossier submitted for evaluation comprises:
- A report for project evaluation, made according to Form No. 1 to this Circular (not printed herein);
- The investment project on work construction, including explanations and the basic design;
- The written permission for investment, for national important projects; the written approval of the branch planning, for group-A projects not included in a branch planning; or the written approval of the construction planning, for projects not included in a construction planning;
- Relevant legal documents.
b/ The project evaluator shall receive the investor's project dossier and send it to concerned agencies for comments and, at the same time, send a dossier for evaluation comments on the basic design to agencies competent to evaluate basic designs defined in Clause 5, Article 1 of Decree 112/CP.
The basic design-evaluating agency shall evaluate the basic design and send evaluation results to the project evaluator. The evaluation results of the basic design shall be presented according to Form No. 2 to this Circular (not printed herein).
When necessary, to ensure convenience, the project evaluator may authorize the investor to send the project dossier and explanations directly to the agency competent to evaluate the basic design.
c/ Duration of evaluation of projects:
The duration of evaluation of projects, including the duration of evaluation of basic designs, is counted from the date a complete and valid dossier is received. Specifically:
- For important national projects: The duration of evaluation of projects is as stipulated in the National Assembly's Resolution No. 66/2006/QH11, of which the duration of evaluation of basic designs must not exceed 30 working days.
- For group-A projects: The duration of evaluation of projects must not exceed 40 working days, of which the duration of evaluation of basic designs must not exceed 20 working days.
- For group-B projects: The duration of evaluation of projects must not exceed 30 working days, of which the duration of evaluation of basic designs must not exceed 15 working days.
- For group-C projects: The duration of evaluation of projects must not exceed 20 working days, of which the duration of evaluation of basic designs must not exceed 10 working days.
d/ Project evaluators shall evaluate projects, sum up comments of concerned agencies and evaluation results of basic designs, give their comments, evaluations and recommendations, and submit them to investment deciders for the latter to approve the projects.
A project dossier submitted for approval comprises:
- A report for project approval, made according to Form No. 3 to this Circular (not printed herein), indicating the evaluation results of the project; comments, evaluations and recommendations to the investment decider;
- The investor's project dossier submitted for evaluation specified at Item a, Point 3 of this Section;
- Evaluation documents of competent agencies related to the project.
IV. Formulation, evaluation and approval of econo-technical reports on the construction of works
1. Formulation of econo-technical reports on the construction of works:
a/ The investor shall formulate, or hire a consultancy organization to formulate, an econo-technical report on work construction investment (below referred to as econo-technical report for short). Such an econo-technical report shall be made in accordance with Clause 4, Article 35, of the Construction Law.
b/ Model designs or typical designs promulgated by competent state agencies may be used to prepare a construction drawing design in the econo-technical report.
2. Evaluation of econo-technical reports:
a/ The investment decider shall evaluate an econo-technical report before approval. The econo-technical report evaluator is a professional unit of the investment decider as defined in Clause 5, Article 1 of Decree 112/CP. For an econo-technical report on the investment decided under authorization, the report evaluator is a professional unit of the person authorized to decide on investment.
b/ The investor shall evaluate the construction drawing design and the work cost estimate or, when necessary, he/she/it may hire a consultant to conduct a verification as a basis for evaluation. For works in the domain of the environment, fire and explosion prevention and fighting, or security and defense, upon evaluation of their construction drawing designs, the agencies in charge of those domains shall be consulted.
The evaluation results of construction drawing designs and cost estimates shall be presented according to Form No. 4 to this Circular (not printed herein).
c/ The investor shall send the dossier to the econo-technical report evaluator for evaluation before the investment decider approves the econo-technical report.
A dossier of econo-technical report submitted for evaluation comprises:
- The report for evaluation of the econo-technical report, made according to Form No. 5 to this Ciruclar (not printed herein);
- The econo-technical report, including explanations and the construction drawing design;
- The evaluation results of the construction drawing design and cost estimate, enclosed with written comments of concerned agencies (if any).
d/ The evaluator shall send the dossier of the econo-technical report to professional units of the investment decider for evaluation comments on the econo-technical report.
The maximum duration of evaluation of an econo-technical report is 20 working days, of which the maximum duration for concerned units to give their comments is 10 working days.
e/ The investment decider shall evaluate an econo-technical report through:
- Considering efficiency assurance elements, including the necessity of the investment; inputs; scale, capacity, technologies, schedule of implementation; financial analysis and socio-economic benefits.
- Considering feasibility assurance elements, including conformity with the approved planning; the demand for use of land and natural resources (if any); ground clearance possibility; capacity to mobilize capital to ensure progress; capacity to repay loans; the investor's managerial experience; and the results of evaluation of the construction drawing design and cost estimate.
3. Approval of an econo-technical report:
a/ After evaluating an econo-technical report, the evaluator shall submit the dossier to the investment decider for consideration and approval.
A dossier of the cono-technical report submitted for approval comprises:
- The report for approval of the econo-technical report, made according to Form No. 6 to this Circular (not printed herein), indicating the results of evaluation of the econo-technical report; comments, evaluations and recommendations to the investment decider;
- The investor's dossier of the econo-technical report submitted for evaluation;
- Written comments of concerned agencies.
b/ The person competent to decide on investment shall approve the econo-technical report based on the evaluator's evaluation results. A decision approving the econo-technical report shall be made according to Form No. 7 to this Circular (not printed herein).
After an econo-technical report is approved by a competent person, the construction drawing design shall be stamped and certified by the investor before it is used for construction.
V. Formulation, evaluation and approval of work construction investment projects funded with ODA or foreign direct investment capital
1. For ODA-funded projects:
The formulation, evaluation and approval of ODA-funded investment projects on the construction of works must comply with the construction law and the law on management and use of official development assistance (ODA). Particularly, the competence to evaluate basic designs and evaluation contents must comply with the construction law. When an ODA treaty signed between the Vietnamese State or Government and donors contains different provisions, the provisions of that treaty prevail.
2. For foreign direct investment projects:
After being granted investment certificates under the investment law, investors shall formulate investment projects on the construction of works, carry out procedures for submission of projects for approval, and take subsequent steps in accordance with the Construction Law, Decree 16/CP, Decree 112/CP and this Circular.
Part II
GUIDANCE ON THE GRANT OF CONSTRUCTION PERMITS
I. Application for work construction permits
1. Before constructing works, construction permits are required under the provisions of the Construction Law, Decree 16/CP and Decree 112/CP, except for works defined at Point 2 of this Section.
2. Construction permits are not required for the following works:
a/ Works classified as state secrets;
b/ Works built under urgent orders;
c/ Makeshift works in service of the construction of principal works;
d/ Works built in lines not running through urban centers which are conformable with approved construction plannings;
e/ Works under construction investment projects already approved by competent state agencies, excluding works for which only econo-technical reports are required. However, before starting the construction of works, investors shall send the evaluation results of basic designs to construction permit-granting agencies for monitoring and management;
f/ Construction works under projects on new urban centers, industrial parks or residential areas with detailed construction plannings of a scale of 1/500 already approved by competent state agencies;
g/ Works on repair, renovation or installment of interior equipment without changing the architecture, force-bearing structure or safety of the works;
h/ Technical infrastructure works capitalized at under VND 7 billion each in deep-lying or remote communes which are located outside cultural-heritage conservation zones or historical-cultural relics;
i/ Individual dwelling houses in deep-lying or remote areas neither in urban centers nor in concentrated population quarters; or individual dwelling houses in rural residential areas without approved construction plannings.
3. Makeshift construction permits:
a/ The grant of makeshift construction permits shall apply only to areas for which construction plannings have been approved and publicized but are not implemented yet.
b/ Provincial-level People's Committees shall specify the grant of makeshift construction permits to suit local situation and characteristics.
c/ A makeshift construction permit must clearly indicate the permitted existence duration of the work. Upon the expiration of the duration specified in the makeshift construction permit, if the State clears the ground for implementation of the planning, the investor shall itself dismantle the work; if the investor fails to dismantle the work, the work shall be dismantled under coercion and the investor shall bear all expenses for such dismantlement.
The compensation and ground clearance for implementation of plannings must comply with current regulations; particularly, the construction under makeshift construction permits is not eligible for compensation.
4. Grant of construction permits to works under projects:
a/ For a project involving many works located in different provinces or centrally run cities, for a work located in a locality, the investor shall apply for a construction permit in that locality.
b/ For a project involving many works located in one place in a province or centrally run city, the investor may apply for a construction permit for all the works in that province or centrally run city.
II. Dossiers of application for construction permits
1. Dossiers of application for permits for construction of urban works and dwelling houses:
The dossiers of application for construction permits are as stipulated in Article 18 of Decree 16/CP and Clause 10, Article 1 of Decree 112/CP.
2. Dossiers of application for permits for construction of rural dwelling houses:
The dossiers of application for construction permits are as stipulated in Article 19 of Decree 16/CP, of which the ground plan is made according to Form No. 8 to this Circular (not printed herein). The plan of the work ground must clearly indicate the dimensions and the land occupancy area of the house, the works on the land lot, distance from the work to surrounding works, and points for connecting electricity, communication and water supply and drainage systems with public technical infrastructures (if any). The drawing must contain the name of the house owner, the address of his/her place of residence, the construction site, and the name and address of the drawer of that plan.
3. Dossiers of application for permits for the construction of works under projects with evaluated basic designs:
The investor may apply for a construction permit for a work, once for many works, or once for all works under a project.
a/ A dossier of application for the construction permit for a work comprises:
- Documents specified in Clauses 1 and 2, Article 18 of Decree 16/CP;
- The evaluation results of the basic design.
b/ A dossier of application for the construction permit for many works or for all works under a project comprises:
- An application for construction permit, made according to Form No. 9 to this Circular (not printed herein);
- A notarized or authenticated copy of the land use rights certificate as provided for by law;
- The evaluation results of basic designs of the works for which the investor applies for construction permit.
III. Contents of a construction permit
A construction permit has the principal contents as stipulated in Clause 1, Article 64 of the Construction Law and takes one of the following forms:
1. Permit for the construction of urban works and dwelling houses, made according to Form No. 1, Appendix No. 6 to Decree 16/CP.
2. Makeshift construction permit, made according to Form No. 2, Appendix No. 6 to Decree 16/CP.
3. Permit for the construction of rural dwelling houses, made according to Form No. 3, Appendix No. 6 to Decree 16/CP.
4. Permit for the construction of works under projects, made according to a form in Appendix No. 10 to this Circular.
IV. Competence to grant construction permits
1. Provincial-level People's Committees shall authorize directors of provincial-level Construction Services to grant construction permits for construction works of special grade or grade I (according to the classification of works provided for in the Decree on the quality management of construction works); religious works; historical-cultural relics works; monuments, advertisement signboards or grandiose paintings within the administrative boundaries under their management; works on principal routes or major streets in urban centers; works under projects funded with direct foreign investment capital; and works under other projects and works as provided for by provincial-level People's Committees.
2. District-level People's Committees shall grant construction permits for remaining urban works and individual dwelling houses within the administrative boundaries under their management, except for the works specified at Point 1 above.
3. Commune-level People's Committees shall grant construction permits for individual dwelling houses in rural residential areas where the construction plannings have been approved within the administrative boundaries under their management.
V. Modification of construction permits
1. When wishing to modify the work construction design, resulting in changes in the contents of the granted construction permit, the investor shall apply for the modification of the construction permit before constructing the work according to the modified contents. The construction permit-granting agency is also competent to modify the granted construction permits, while ensuring conformity with construction plannings and taking responsibility for the modified contents of construction permits. The modified contents of a construction permit shall be entered in the section "extension, modification" in the granted construction permit.
2. A dossier of application for the modification of a construction permit comprises:
a/ An application for the modification of the construction permit;
b/ The original construction permit;
c/ The modified design drawing.
3. The time limit for considering the modification of a construction permit is 10 working days after the receipt of a complete and valid dossier.
Part III
GUIDANCE ON THE MANAGEMENT OF INVESTMENT PROJECTS ON THE CONSTRUCTION OF WORKS
I. Cases where investors directly manage projects
1. An investor that directly manages a project shall set up a project management unit (below abbreviated to PMU), except for small and simple projects capitalized at under VND 1 billion.
The PMU is a unit attached to the investor, has the legal person status or uses the legal person status of the investor in managing the project. The tasks and powers of the PMU shall be defined by the investor.
The organizational structure of the PMU shall be decided by the investor to suit the size, nature and requirements of the project as well as the tasks and powers defined by the investor. The PMU may hire a consultancy organization or individual to manage and supervise some components of the project which it is incapable of doing so, provided that such hire is approved by the investor.
A PMU is composed of a director, deputy directors and professional sections; PMU personnel may work on a full-time or part-time basis. The director, deputy directors and persons in charge of technical, economic and financial matters must have university degrees relevant to the matters they are in charge of and have at least three years' working experience. Particularly for group-C projects in deep-lying and remote areas, the above posts may be held by persons having relevant college degrees or intermediate degrees.
2. For small and simple projects capitalized at under VND 1 billion, investors may, instead of setting up PMUs, employ their professional sections to manage the projects; when necessary, investors may hire persons with professional qualifications and experience to assist them in managing the projects.
3. PMUs shall be dissolved after they have completed their tasks.
II. Cases where investors hire consultants to manage projects
1. When a consultant is hired to manage a project, the consultancy contractor shall set up an organization to directly manage the project according to the contract signed with the investor. This organization is composed of the project management consultancy director, deputy directors and professional sections suitable to the tasks and powers defined in the contract signed between the consultancy contractor and the investor.
The project management consultancy director must have full capacity as specified in Clause 1, Article 55 of Decree 16/CP. Deputy directors and persons in charge of professional matters must have relevant university degrees and have at least three years' working experience.
The project management consultancy contractor may hire a consultancy organization or individual to join in managing some components of the project provided that such hire is approved by the investor and the hired organization's or individual's tasks and powers are compatible with those defined in the contract signed with the investor.
2. The tasks and powers of the consultancy organization directly managing the project at construction site shall be defined in writing by the consultancy contractor and sent to the investor for notification to relevant contractors.
III. Responsibilities of investors in managing investment projects on the construction of works
Investors have the tasks and powers as provided for by the construction law from the preparation of a project, execution of the project and acceptance and hand-over of the work for putting it to exploitation and use. For the tasks and powers already assigned by the investors to PMUs (under decisions to set up PMUs) or project management consultants (under contracts signed with project management consultancy contractors), the investors shall direct, monitor, urge and inspect the performance of those tasks and powers to ensure that the projects are executed according to the approved contents and progress. The investors shall take full responsibility for the jobs under their tasks and powers in accordance with law, even for the jobs already assigned to the PMUs or project management consultancy contractors.
Part IV
GUIDANCE ON TRANSITIONAL HANDLING
I. Transitional handling regarding the procedures for the formulation, evaluation and approval of investment projects on the construction of works and subsequent jobs
1. For investment projects on the construction of works which were approved before the effective date of Decree 16/CP but are not yet executed or are underway, investment deciders shall decide to carry out the procedures for performing the remaining jobs in accordance with Decree 16/CP or the regulations prior to the effective date of Decree 16/CP. If the investment deciders have decided to carry out the procedures for performing the remaining jobs according to the regulations prior to the effective date of Decree 16/CP, those regulations shall still be applied; if they have decided to carry out the procedures for performing the remaining jobs in accordance with Decree 16/CP, the transition to implementation of Decree 112/CP is as guided at Point 2 of this Section.
2. Before the effective date of Decree 112/CP, the procedures shall not be re-carried out for investment projects on the construction of works which have not yet approved but have project evaluation results or which have been approved but are not yet executed or are underway. The remaining procedures shall be carried out in accordance with Decree 16/CP, the amendments and supplements in Decree 112/CP, and the guidance in this Circular.
In the course of execution of a project, if modifications are made, resulting in changes in the basic design, the competence to evaluate the changed basic design is as defined in Decree 112/CP.
II. Transitional handling regarding the grant of construction permits
1. Construction permits are not required for construction works in which investment has been decided and for which construction permits are not required as provided for in Decree 16/CP when the construction of which started before the effective date of Decree 112/CP.
2. Where a project involving many works in which investment has been decided and the construction of some of these works started before the effective date of Decree 112/CP, if the investor carries out the procedures for application for the construction permit once for all works under that project, he/she/it shall follow the guidance at Point 4, Section I and Point 3, Section II, Part II of this Circular and declare the works of which construction started. The construction permit-granting agency shall inspect the observance of law with respect to these works before giving certification in the construction permit.
3. For works under construction investment projects which were approved before the effective date of Decree 112/CP but the construction of which has not started yet, before their construction starts, construction permits should be applied in accordance with Decree 112/CP and the guidance in this Circular, excluding works for which construction permits are not required as specified at Point 2, Section I, Part II of this Circular.
III. Transitional handling regarding the management of projects
1. PMUs already assigned to act as investors shall be reorganized timely in accordance with current provisions of law to ensure the principle that investors shall set up PMUs, assign tasks to, and inspect the performance of the PMUs.
2. Regional PMUs and specialized PMUs set up by ministries, branches or localities for management of many projects shall be converted into professional project management consultancy organizations operating under the enterprise law or be dissolved. When a PMU is assigned to manage one or many projects which will be completed in 2007, such PMU may be maintained but shall be reorganized to be fully capable of performing the remaining jobs. After a project is completed, the PMU shall be dissolved or transformed in accordance with the enterprise law.
Part V
IMPLEMENTATION PROVISIONS
I. This Circular replaces the following documents:
1. The Construction Ministry's Circular No. 08/2005/TT-BXD of May 6, 2005, guiding a number of contents regarding the formulation, evaluation and approval of investment projects on the construction of works and transitional handling for implementation of the Government's Decree No. 16/2005/ND-CP of February 7, 2005.
2. The Construction Ministry's Circular No. 09/2005/TT-BXD of May 6, 2005, guiding a number of contents regarding construction permits.
3. Points 3.1, Section II on PMUs of the Construction Ministry's Circular No. 12/2005/TT-BXD of July 15, 2005, which guides a number of contents regarding the quality management of construction works and capacity conditions for organizations and individuals in construction activities.
II. Implementation effect:
1. This Circular takes effect 15 days after its publication in "CONG BAO." Previous regulations on the formulation, evaluation and approval of investment projects on the construction of works; construction permits; and the management of investment projects on the construction of works, which are contrary to the guidance in this Circular, are all annulled.
2. Organizations and individuals should report problems arising in the course of implementation to the Ministry of Construction for consideration and solution.
11 parts
Bộ Xây dựng
Số: 02/2007/TT-BXD
ngày 14 tháng 02 năm 2007
THÔNG TƯ
Hướng dẫn một số nội dung về: lập, thẩm định, phê duyệt dự án đầu tư xây dựng
công trình; giấy phép xây dựng và tổ chức quản lý dự án đầu tư xây dựng công trình
quy định tại Nghị định số 16/2005/NĐ-CP ngày 07/02/2005 và Nghị định số
112/2006/NĐ-CP ngày 29/09/2006 của Chính phủ
Căn cứ Nghị định số 36/2003/NĐ-CP ngày 04/04/2003 của Chính phủ quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Xây dựng;
Căn cứ Nghị định số 16/2005/NĐ-CP ngày 07/02/2005 của Chính phủ về quản lý dự án đầu tư xây dựng công trình;
Căn cứ Nghị định số 112/2006/NĐ-CP ngày 29/09/2006 của Chính phủ về sửa đổi, bổ sung một số điều của Nghị định số 16/2005/NĐ-CP về quản lý dự án đầu tư xây dựng công trình;
-
Mục Mở đầu
Bộ Xây dựng hướng dẫn một số nội dung về: lập, thẩm định, phê duyệt dự án đầu tư xây dựng công trình; giấy phép xây dựng và tổ chức quản lý dự án đầu tư xây dựng công trình quy định tại Nghị định số 16/2005/NĐ-CP ngày 07/02/2005 của Chính phủ về quản lý dự án đầu tư xây dựng công trình (dưới đây viết tắt là Nghị định 16/CP) và Nghị định số 112/2006/NĐ-CP ngày 29/09/2006 của Chính phủ về sửa đổi, bổ sung một số điều của Nghị định số 16/2005/NĐ-CP về quản lý dự án đầu tư xây dựng công trình (dưới đây viết tắt là Nghị định 112/CP) như sau:
-
Mục Phần I › Mở đầu
Phần I
HƯỚNG DẪN VỀ LẬP, THẨM ĐỊNH, PHÊ DUYỆT
DỰ ÁN ĐẦU TƯ XÂY DỰNG CÔNG TRÌNH -
Mục Phần I › I
1. Đối với dự án do Thủ tướng Chính phủ quyết định đầu tư thì chủ đầu tư là một trong các cơ quan, tổ chức sau: Bộ, cơ quan ngang Bộ, cơ quan thuộc Chính phủ, cơ quan khác ở Trung ương (gọi chung là cơ quan cấp Bộ), Uỷ ban nhân dân tỉnh, thành phố trực thuộc trung ương (gọi chung là UBND cấp tỉnh) và doanh nghiệp nhà nước.2. Đối với dự án do Bộ trưởng, Thủ trưởng cơ quan cấp Bộ, Chủ tịch UBND các cấp quyết định đầu tư thì người quyết định đầu tư giao cho đơn vị quản lý, sử dụng công trình làm chủ đầu tư. Trường hợp đơn vị quản lý, sử dụng công trình không đủ điều kiện về tổ chức, nhân lực, thời gian và các điều kiện cần thiết khác để thực hiện các nhiệm vụ, quyền hạn của chủ đầu tư hoặc chưa xác định được đơn vị quản lý, sử dụng công trình thì người quyết định đầu tư giao cho đơn vị có đủ các điều kiện nêu trên làm chủ đầu tư và thực hiện như sau: Đối với trường hợp đơn vị quản lý, sử dụng công trình không được giao làm chủ đầu tư thì đơn vị quản lý, sử dụng công trình phải có văn bản cử người tham gia với chủ đầu tư để quản lý dự án đầu tư xây dựng và tổ chức tiếp nhận công trình đưa vào khai thác sử dụng. Chủ đầu tư có trách nhiệm bố trí người của đơn vị quản lý, sử dụng công trình vào vị trí phù hợp để được tham gia quản lý ngay từ khâu lập dự án đến khi bàn giao đưa công trình vào sử dụng đảm bảo hiệu quả và mục tiêu của dự án. Trường hợp chủ đầu tư thành lập Ban quản lý dự án thì một trong các phó giám đốc Ban quản lý dự án phải là người của đơn vị quản lý, sử dụng công trình. Đối với trường hợp chưa xác định được đơn vị quản lý, sử dụng công trình thì trong quá trình triển khai thực hiện dự án phải xác định được đơn vị quản lý, sử dụng công trình để tham gia cùng với chủ đầu tư trong việc nghiệm thu và tiếp nhận công trình đưa vào khai thác sử dụng.
-
Mục Phần I › II
II. VỀ VIỆC XỬ LÝ ĐỐI VỚI CÁC DỰ ÁN NHÓM A KHÔNG CÓ TRONG QUY HOẠCH
1. Trường hợp dự án không có trong quy hoạch ngành hoặc không phù hợp với quy hoạch ngành được cấp có thẩm quyền phê duyệt thì trước khi lập dự án đầu tư xây dựng công trình, chủ đầu tư phải báo cáo Bộ quản lý ngành; Bộ quản lý ngành có trách nhiệm xem xét, bổ sung quy hoạch theo thẩm quyền hoặc trình Thủ tướng Chính phủ chấp thuận. Ví dụ: Dự án đầu tư xây dựng nhà máy điện tại tỉnh X chưa có trong quy hoạch ngành điện thì trước khi lập dự án chủ đầu tư báo cáo Bộ Công nghiệp để Bộ Công nghiệp xem xét điều chỉnh quy hoạch theo thẩm quyền hoặc trình Thủ tướng Chính phủ chấp thuận bổ sung vào quy hoạch ngành điện.
2. Trường hợp dự án không có trong quy hoạch xây dựng hoặc chưa có quy hoạch xây dựng thì trước khi lập dự án đầu tư xây dựng công trình, chủ đầu tư phải báo cáo Uỷ ban nhân dân cấp tỉnh để được xem xét chấp thuận về vị trí, quy mô, tổng mặt bằng của dự án; đồng thời UBND cấp tỉnh có trách nhiệm tổ chức điều chỉnh hoặc lập quy hoạch xây dựng theo quy định. -
Mục Phần I › III
1. Về lập dự án đầu tư xây dựng công trình: Sau khi thực hiện đăng ký đầu tư hoặc được cấp giấy chứng nhận đầu tư theo quy định của pháp luật về đầu tư, chủ đầu tư tổ chức lập dự án đầu tư xây dựng công trình, làm các thủ tục trình duyệt dự án và triển khai thực hiện các bước tiếp theo theo quy định của Luật Xây dựng, Nghị định 16/CP, Nghị định 112/CP và hướng dẫn của Thông tư này.2. Thẩm quyền thẩm định dự án đầu tư xây dựng công trình:a) Người quyết định đầu tư có trách nhiệm tổ chức thẩm định dự án đầu tư xây dựng công trình trước khi phê duyệt. Đơn vị đầu mối thẩm định dự án là đơn vị chuyên môn trực thuộc người quyết định đầu tư theo quy định tại khoản 5 Điều 1 Nghị định 112/CP. Trường hợp dự án được uỷ quyền quyết định đầu tư thì đầu mối thẩm định dự án là đơn vị chuyên môn trực thuộc người được uỷ quyền quyết định đầu tư.b) Thẩm quyền thẩm định thiết kế cơ sở được thực hiện theo quy định tại khoản 5 Điều 1 Nghị định 112/CP. Đối với các dự án nhóm B, C do Bộ Công nghiệp, Bộ Nông nghiệp và Phát triển nông thôn, Bộ Giao thông - Vận tải, Bộ Xây dựng, các Tập đoàn kinh tế và Tổng công ty nhà nước quyết định đầu tư thuộc chuyên ngành do mình quản lý thì các Bộ, doanh nghiệp này tự tổ chức thẩm định thiết kế cơ sở sau khi có ý kiến của địa phương về quy hoạch xây dựng và bảo vệ môi trường, cụ thể: Bộ Công nghiệp tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án đầu tư xây dựng công trình hầm mỏ, dầu khí, nhà máy điện, đường dây tải điện, trạm biến áp, hoá chất, vật liệu nổ công nghiệp, chế tạo máy, luyện kim và các công trình công nghiệp chuyên ngành nhóm B, C do Bộ Công nghiệp quyết định đầu tư. Bộ Nông nghiệp và Phát triển nông thôn tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án đầu tư xây dựng công trình thuỷ lợi, đê điều nhóm B, C do Bộ Nông nghiệp và Phát triển nông thôn quyết định đầu tư. Bộ Giao thông vận tải tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án đầu tư xây dựng công trình giao thông nhóm B, C do Bộ Giao thông vận tải quyết định đầu tư. Bộ Xây dựng tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án đầu tư xây dựng công trình dân dụng, công nghiệp vật liệu xây dựng, hạ tầng kỹ thuật đô thị nhóm B, C do Bộ Xây dựng quyết định đầu tư. Tập đoàn kinh tế, Tổng công ty nhà nước tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án nhóm B, C do mình quyết định đầu tư nếu dự án thuộc chuyên ngành được Nhà nước giao cho doanh nghiệp đó quản lý. Ví dụ: Tập đoàn Điện lực Việt nam (EVN) được Nhà nước giao quản lý mạng lưới điện trên toàn quốc thì EVN được tự tổ chức thẩm định thiết kế cơ sở các công trình thuộc dự án mạng lưới điện nhóm B, C do mình quyết định đầu tư. Đối với các dự án khác do EVN quyết định đầu tư thì việc thẩm định thiết kế cơ sở do cơ quan nhà nước có thẩm quyền quy định tại khoản 5 Điều 1 Nghị định 112/CP thực hiện.3. Trình tự, thủ tục thẩm định, phê duyệt dự án:a) Chủ đầu tư có trách nhiệm tổ chức lập và gửi hồ sơ dự án tới đơn vị đầu mối thẩm định dự án để tổ chức thẩm định trước khi trình người có thẩm quyền quyết định đầu tư phê duyệt. Hồ sơ trình thẩm định dự án bao gồm: - Tờ trình thẩm định dự án theo mẫu tại Phụ lục số 1 của Thông tư này; - Dự án đầu tư xây dựng công trình gồm phần thuyết minh và thiết kế cơ sở; - Văn bản cho phép đầu tư đối với dự án quan trọng quốc gia; văn bản chấp thuận về quy hoạch ngành đối với dự án nhóm A không có trong quy hoạch ngành; văn bản chấp thuận về quy hoạch xây dựng đối với dự án không có trong quy hoạch xây dựng; - Các văn bản pháp lý có liên quan.b) Đơn vị đầu mối thẩm định dự án có trách nhiệm tiếp nhận hồ sơ dự án của chủ đầu tư và gửi tới cơ quan có liên quan để lấy ý kiến, đồng thời gửi hồ sơ để lấy ý kiến thẩm định thiết kế cơ sở của cơ quan có thẩm quyền thẩm định thiết kế cơ sở quy định tại khoản 5 Điều 1 Nghị định 112/CP. Cơ quan thẩm định thiết kế cơ sở có trách nhiệm tổ chức thẩm định và gửi kết quả thẩm định tới đơn vị đầu mối thẩm định dự án. Kết quả thẩm định thiết kế cơ sở được lập theo mẫu tại Phụ lục số 2 của Thông tư này. Trường hợp cần thiết, để đảm bảo thuận tiện, đơn vị đầu mối thẩm định dự án có thể uỷ quyền cho chủ đầu tư trực tiếp gửi hồ sơ dự án và giải trình với cơ quan có thẩm quyền thẩm định thiết kế cơ sở.c) Thời gian thẩm định dự án: Thời gian thẩm định dự án, bao gồm cả thời gian thẩm định thiết kế cơ sở được tính từ ngày nhận đủ hồ sơ hợp lệ, cụ thể: - Đối với dự án quan trọng quốc gia: thời gian thẩm định dự án theo quy định của Nghị quyết số 66/2006/QH11 của Quốc hội, trong đó thời gian thẩm định thiết kế cơ sở không quá 30 ngày làm việc. - Đối với dự án nhóm A: thời gian thẩm định dự án không quá 40 ngày làm việc, trong đó thời gian thẩm định thiết kế cơ sở không quá 20 ngày làm việc. - Đối với dự án nhóm B: thời gian thẩm định dự án không quá 30 ngày làm việc, trong đó thời gian thẩm định thiết kế cơ sở không quá 15 ngày làm việc. - Đối với dự án nhóm C: thời gian thẩm định dự án không quá 20 ngày làm việc, trong đó thời gian thẩm định thiết kế cơ sở không quá 10 ngày làm việc.d) Đơn vị đầu mối thẩm định dự án có trách nhiệm tổ chức thẩm định dự án, tổng hợp ý kiến của các cơ quan có liên quan và kết quả thẩm định thiết kế cơ sở, nhận xét, đánh giá, kiến nghị và trình người quyết định đầu tư phê duyệt dự án. Hồ sơ trình phê duyệt dự án bao gồm: - Tờ trình phê duyệt dự án theo mẫu tại Phụ lục số 3 của Thông tư này, trong đó phải nêu được kết quả thẩm định dự án; nhận xét, đánh giá và kiến nghị với người quyết định đầu tư; - Hồ sơ của chủ đầu tư trình để thẩm định dự án theo điểm a mục này; - Các văn bản tham gia thẩm định của cơ quan có thẩm quyền liên quan tới dự án.
-
Mục Phần I › IV
1. Lập Báo cáo kinh tế - kỹ thuật xây dựng công trình:a) Chủ đầu tư lập hoặc thuê tổ chức tư vấn lập Báo cáo kinh tế - kỹ thuật đầu tư xây dựng công trình (dưới đây gọi tắt là Báo cáo kinh tế – kỹ thuật). Nội dung Báo cáo kinh tế - kỹ thuật được lập theo quy định tại khoản 4 Điều 35 của Luật Xây dựng.b) Khi lập thiết kế bản vẽ thi công trong Báo cáo kinh tế - kỹ thuật có thể sử dụng thiết kế mẫu, thiết kế điển hình do cơ quan nhà nước có thẩm quyền ban hành.2. Tổ chức thẩm định Báo cáo kinh tế - kỹ thuật: a) Người quyết định đầu tư có trách nhiệm tổ chức thẩm định Báo cáo kinh tế - kỹ thuật trước khi phê duyệt. Đơn vị đầu mối thẩm định Báo cáo kinh tế - kỹ thuật là đơn vị chuyên môn trực thuộc người quyết định đầu tư theo quy định tại khoản 5 Điều 1 Nghị định 112/CP. Trường hợp Báo cáo kinh tế - kỹ thuật được uỷ quyền quyết định đầu tư thì đầu mối thẩm định Báo cáo kinh tế - kỹ thuật là đơn vị chuyên môn trực thuộc người được uỷ quyền quyết định đầu tư.b) Chủ đầu tư tổ chức thẩm định thiết kế bản vẽ thi công và dự toán công trình, trường hợp cần thiết thì có thể thuê tư vấn thẩm tra để làm cơ sở cho việc thẩm định. Đối với công trình có liên quan đến môi trường; phòng, chống cháy, nổ; an ninh, quốc phòng thì khi thẩm định thiết kế bản vẽ thi công phải lấy ý kiến của các cơ quan quản lý về những lĩnh vực này. Kết quả thẩm định thiết kế bản vẽ thi công và dự toán được lập theo mẫu tại Phụ lục số 4 của Thông tư này.c) Chủ đầu tư có trách nhiệm gửi hồ sơ tới đơn vị đầu mối thẩm định Báo cáo kinh tế kỹ thuật để tổ chức thẩm định trước khi trình người quyết định đầu tư phê duyệt Báo cáo kinh tế kỹ thuật. Hồ sơ trình thẩm định Báo cáo kinh tế - kỹ thuật bao gồm: - Tờ trình thẩm định Báo cáo kinh tế - kỹ thuật theo mẫu tại Phụ lục số 5 của Thông tư này; - Báo cáo kinh tế - kỹ thuật bao gồm phần thuyết minh và thiết kế bản vẽ thi công; - Kết quả thẩm định thiết kế bản vẽ thi công và dự toán, kèm theo văn bản góp ý của các cơ quan có liên quan (nếu có).d) Đơn vị đầu mối có trách nhiệm gửi hồ sơ Báo cáo kinh tế kỹ thuật tới các đơn vị chuyên môn trực thuộc người quyết định đầu tư lấy ý kiến về các nội dung có liên quan để thẩm định Báo cáo kinh tế - kỹ thuật. Thời gian tối đa cho việc thẩm định Báo cáo kinh tế - kỹ thuật là 20 ngày làm việc, trong đó thời gian tối đa cho các đơn vị tham gia ý kiến là 10 ngày làm việc.đ) Nội dung thẩm định Báo cáo kinh tế - kỹ thuật của người quyết định đầu tư: - Xem xét các yếu tố đảm bảo tính hiệu quả, bao gồm: sự cần thiết đầu tư; các yếu tố đầu vào; quy mô, công suất, công nghệ, thời gian, tiến độ thực hiện; phân tích tài chính, hiệu quả về kinh tế - xã hội. - Xem xét các yếu tố đảm bảo tính khả thi, bao gồm: sự phù hợp với quy hoạch được duyệt; nhu cầu sử dụng đất, tài nguyên (nếu có); khả năng giải phóng mặt bằng; khả năng huy động vốn đáp ứng tiến độ; khả năng hoàn trả vốn vay; kinh nghiệm quản lý của chủ đầu tư; kết quả thẩm định thiết kế bản vẽ thi công và dự toán.3. Phê duyệt Báo cáo kinh tế - kỹ thuật:a) Sau khi thẩm định Báo cáo kinh tế - kỹ thuật, đơn vị đầu mối trình hồ sơ tới người quyết định đầu tư xem xét phê duyệt. Hồ sơ trình phê duyệt Báo cáo kinh tế - kỹ thuật bao gồm: - Tờ trình phê duyệt Báo cáo kinh tế - kỹ thuật theo mẫu tại Phụ lục số 6 của Thông tư này, trong đó phải nêu được kết quả thẩm định Báo cáo kinh tế - kỹ thuật; nhận xét, đánh giá và kiến nghị với người quyết định đầu tư; - Hồ sơ của chủ đầu tư trình để thẩm định Báo cáo kinh tế - kỹ thuật; - Văn bản góp ý của các cơ quan có liên quan.b) Người có thẩm quyền quyết định đầu tư có trách nhiệm phê duyệt Báo cáo kinh tế - kỹ thuật trên cơ sở kết quả thẩm định của đơn vị đầu mối. Nội dung quyết định phê duyệt Báo cáo kinh tế - kỹ thuật theo mẫu tại Phụ lục số 7 của Thông tư này. Sau khi Báo cáo kinh tế - kỹ thuật đã được người có thẩm quyền phê duyệt, thiết kế bản vẽ thi công phải được chủ đầu tư đóng dấu xác nhận trước khi đưa ra thi công.
-
Mục Phần I › V
V. VỀ LẬP, THẨM ĐỊNH, PHÊ DUYỆT DỰ ÁN ĐẦU TƯ XÂY DỰNG CÔNG TRÌNH SỬ DỤNG VỐN ODA, VỐN ĐẦU TƯ TRỰC TIẾP NƯỚC NGOÀI
1. Đối với dự án sử dụng vốn ODA: Việc lập, thẩm định, phê duyệt dự án đầu tư xây dựng công trình sử dụng vốn ODA được thực hiện theo quy định của pháp luật về xây dựng và pháp luật về quản lý và sử dụng nguồn hỗ trợ phát triển chính thức (ODA). Riêng thẩm quyền và nội dung thẩm định thiết kế cơ sở được thực hiện theo quy định của pháp luật về xây dựng. Trường hợp điều ước quốc tế về ODA đã được ký kết giữa Nhà nước hoặc Chính phủ Việt Nam với nhà tài trợ có quy định khác thì thực hiện theo quy định của điều ước quốc tế đó.
2. Đối với dự án có vốn đầu tư trực tiếp nước ngoài: Sau khi được cấp giấy chứng nhận đầu tư theo quy định của pháp luật về đầu tư, chủ đầu tư tổ chức lập dự án đầu tư xây dựng công trình, làm các thủ tục trình duyệt dự án và triển khai thực hiện các bước tiếp theo theo quy định của Luật Xây dựng, Nghị định 16/CP, Nghị định 112/CP và hướng dẫn của Thông tư này. -
Mục Phần II
1. Các công trình xây dựng trước khi khởi công phải có giấy phép xây dựng theo quy định của Luật Xây dựng, Nghị định 16/CP và Nghị định 112/CP, trừ những công trình quy định tại điểm 2 mục này.2. Những công trình dưới đây không phải xin giấy phép xây dựng:a) Công trình thuộc bí mật Nhà nước.b) Công trình xây dựng theo lệnh khẩn cấp.c) Công trình tạm phục vụ thi công xây dựng công trình chính.d) Công trình xây dựng theo tuyến không đi qua đô thị nhưng phù hợp với quy hoạch xây dựng được duyệt.đ) Công trình thuộc dự án đầu tư xây dựng đã được cơ quan nhà nước có thẩm quyền phê duyệt, trừ công trình chỉ lập Báo cáo kinh tế - kỹ thuật. Tuy nhiên, trước khi khởi công xây dựng công trình chủ đầu tư phải gửi kết quả thẩm định thiết kế cơ sở cho cơ quan cấp giấy phép xây dựng để theo dõi, quản lý.e) Công trình xây dựng thuộc dự án khu đô thị mới, khu công nghiệp, khu nhà ở có quy hoạch chi tiết xây dựng tỷ lệ 1/500 đã được cơ quan nhà nước có thẩm quyền phê duyệt.g) Các công trình sửa chữa, cải tạo, lắp đặt thiết bị bên trong không làm thay đổi kiến trúc, kết cấu chịu lực và an toàn của công trình.h) Công trình hạ tầng kỹ thuật có tổng mức đầu tư dưới 7 tỷ đồng thuộc các xã vùng sâu, vùng xa không nằm trong các khu vực bảo tồn di sản văn hoá, di tích lịch sử - văn hoá.i) Nhà ở riêng lẻ tại vùng sâu, vùng xa không thuộc đô thị, không thuộc điểm dân cư tập trung; nhà ở riêng lẻ tại các điểm dân cư nông thôn chưa có quy hoạch xây dựng được duyệt.3. Về giấy phép xây dựng tạm:a) Việc cấp giấy phép xây dựng tạm chỉ áp dụng đối với những vùng đã có quy hoạch xây dựng được duyệt và công bố nhưng chưa thực hiện.b) Uỷ ban nhân dân cấp tỉnh quy định cụ thể về việc cấp giấy phép xây dựng tạm phù hợp với tình hình, đặc điểm của địa phương.c) Trong nội dung giấy phép xây dựng tạm phải ghi rõ thời gian được phép tồn tại của công trình, hết thời hạn quy định trong giấy phép xây dựng tạm nếu Nhà nước giải phóng mặt bằng để thực hiện quy hoạch thì chủ đầu tư phải tự phá dỡ công trình, nếu không tự phá dỡ thì bị cưỡng chế phá dỡ và chủ đầu tư phải chịu mọi chi phí cho việc phá dỡ công trình. Việc bồi thường, giải phóng mặt bằng để thực hiện quy hoạch áp dụng theo quy định hiện hành; riêng phần xây dựng theo giấy phép xây dựng tạm thì không được bồi thường.4. Về cấp giấy phép xây dựng cho các công trình thuộc dự án:a) Đối với dự án gồm nhiều công trình nằm ở các tỉnh, thành phố khác nhau thì công trình nằm ở địa phương nào chủ đầu tư xin cấp giấy phép xây dựng ở địa phương đó.b) Đối với dự án gồm nhiều công trình nằm ở một địa điểm thuộc một tỉnh, thành phố thì chủ đầu tư xin cấp giấy phép xây dựng một lần cho các công trình thuộc dự án tại địa phương đó. II. HỒ SƠ XIN CẤP GIẤY PHÉP XÂY DỰNG1. Hồ sơ xin cấp giấy phép xây dựng đối với công trình và nhà ở đô thị: Hồ sơ xin cấp giấy phép xây dựng theo quy định tại Điều 18 Nghị định 16/CP và khoản 10 Điều 1 Nghị định 112/CP.2. Hồ sơ xin cấp giấy phép xây dựng đối với nhà ở nông thôn: Hồ sơ xin cấp giấy phép xây dựng theo quy định tại Điều 19 Nghị định 16/CP, trong đó sơ đồ mặt bằng được lập theo mẫu tại Phụ lục số 8 của Thông tư này. Sơ đồ mặt bằng công trình phải thể hiện rõ các kích thước và diện tích chiếm đất của ngôi nhà, các công trình trên lô đất, khoảng cách tới các công trình xung quanh và các điểm đấu nối điện, thông tin liên lạc, cấp - thoát nước với các công trình hạ tầng kỹ thuật công cộng bên ngoài (nếu có). Trên bản vẽ phải ghi rõ tên chủ nhà, địa chỉ nơi ở, địa điểm xây dựng và tên, địa chỉ người vẽ sơ đồ đó.3. Hồ sơ xin cấp giấy phép xây dựng cho các công trình thuộc dự án đã có thiết kế cơ sở được thẩm định: Chủ đầu tư có thể xin giấy phép xây dựng cho một công trình, một lần cho nhiều công trình hoặc một lần cho tất cả các công trình thuộc dự án.a) Trường hợp xin cấp giấy phép xây dựng cho một công trình: - Các tài liệu như quy định tại khoản 1, 2 Điều 18 Nghị định 16/CP; - Kết quả thẩm định thiết kế cơ sở.b) Trường hợp xin cấp giấy phép xây dựng một lần cho nhiều công trình hoặc một lần cho tất cả các công trình thuộc dự án: - Đơn xin cấp giấy phép xây dựng theo mẫu tại Phụ lục số 9 của Thông tư này; - Bản sao có công chứng hoặc chứng thực giấy tờ về quyền sử dụng đất theo quy định của pháp luật; - Kết quả thẩm định thiết kế cơ sở các công trình mà chủ đầu tư xin giấy phép xây dựng. III. NỘI DUNG GIẤY PHÉP XÂY DỰNG Nội dung chủ yếu của Giấy phép xây dựng theo quy định tại khoản 1 Điều 64 Luật Xây dựng và theo các mẫu sau:1. Giấy phép xây dựng đối với công trình và nhà ở đô thị theo mẫu số 1 Phụ lục số 6 của Nghị định 16/CP.2. Giấy phép xây dựng tạm theo mẫu số 2 Phụ lục số 6 của Nghị định 16/CP.3. Giấy phép xây dựng đối với nhà ở nông thôn theo mẫu số 3 Phụ lục số 6 của Nghị định 16/CP.4. Giấy phép xây dựng đối với các công trình thuộc dự án theo mẫu tại Phụ lục số 10 của Thông tư này. IV. THẨM QUYỀN CẤP GIẤY PHÉP XÂY DỰNG 1. Ủy ban nhân dân cấp tỉnh uỷ quyền cho Giám đốc Sở Xây dựng cấp giấy phép xây dựng đối với các công trình xây dựng cấp đặc biệt, cấp I (theo phân cấp công trình tại Nghị định về quản lý chất lượng công trình xây dựng); công trình tôn giáo; công trình di tích lịch sử - văn hoá; công trình tượng đài, quảng cáo, tranh hoành tráng thuộc địa giới hành chính do mình quản lý; những công trình trên các tuyến, trục đường phố chính trong đô thị; công trình thuộc dự án có vốn đầu tư trực tiếp nước ngoài; công trình thuộc dự án và các công trình khác do Ủy ban nhân dân cấp tỉnh quy định.2. Ủy ban nhân dân cấp huyện cấp giấy phép xây dựng các công trình còn lại và nhà ở riêng lẻ ở đô thị thuộc địa giới hành chính do mình quản lý, trừ các đối tượng quy định tại điểm 1 nêu trên.3. Ủy ban nhân dân xã cấp giấy phép xây dựng nhà ở riêng lẻ tại những điểm dân cư nông thôn đã có quy hoạch xây dựng được duyệt thuộc địa giới hành chính do mình quản lý. V. ĐIỀU CHỈNH GIẤY PHÉP XÂY DỰNG 1. Khi có nhu cầu điều chỉnh thiết kế xây dựng công trình khác với nội dung giấy phép xây dựng đã được cấp, chủ đầu tư phải xin điều chỉnh giấy phép xây dựng trước khi thi công xây dựng công trình theo nội dung điều chỉnh. Cơ quan cấp giấy phép xây dựng là cơ quan có thẩm quyền điều chỉnh giấy phép xây dựng đảm bảo phù hợp quy hoạch xây dựng và chịu trách nhiệm về nội dung cho phép điều chỉnh giấy phép xây dựng. Nội dung điều chỉnh giấy phép xây dựng được ghi bổ sung vào mục "gia hạn, điều chỉnh” trong giấy phép xây dựng đã được cấp cho chủ đầu tư.2. Hồ sơ xin điều chỉnh giấy phép xây dựng gồm:a) Đơn xin điều chỉnh giấy phép xây dựng;b) Bản chính giấy phép xây dựng đã được cấp;c) Bản vẽ thiết kế điều chỉnh.3. Thời hạn xét điều chỉnh giấy phép xây dựng chậm nhất là 10 ngày làm việc kể từ ngày nhận đủ hồ sơ hợp lệ.
-
Mục Phần III
1. Khi áp dụng hình thức chủ đầu tư trực tiếp quản lý dự án thì chủ đầu tư phải thành lập Ban quản lý dự án (sau đây viết tắt là Ban QLDA), trừ trường hợp dự án có quy mô nhỏ, đơn giản có tổng mức đầu tư dưới 1 tỷ đồng. Ban QLDA là đơn vị trực thuộc chủ đầu tư, có tư cách pháp nhân hoặc sử dụng tư cách pháp nhân của chủ đầu tư để thực hiện quản lý dự án. Nhiệm vụ, quyền hạn của Ban QLDA do chủ đầu tư giao. Cơ cấu tổ chức của Ban QLDA do chủ đầu tư quyết định phù hợp với quy mô, tính chất, yêu cầu của dự án và nhiệm vụ, quyền hạn được chủ đầu tư giao. Ban QLDA có thể thuê tổ chức, cá nhân tư vấn để tham gia quản lý, giám sát khi không có đủ điều kiện, năng lực để tự thực hiện, nhưng phải được chủ đầu tư chấp thuận. Cơ cấu tổ chức của Ban QLDA gồm có giám đốc, các phó giám đốc, các đơn vị chuyên môn, nghiệp vụ; những người tham gia Ban QLDA có thể làm việc theo chế độ chuyên trách hoặc kiêm nhiệm. Giám đốc, các phó giám đốc và những người phụ trách về kỹ thuật, kinh tế, tài chính phải có trình độ đại học thuộc chuyên ngành phù hợp với lĩnh vực phụ trách và có kinh nghiệm làm việc chuyên môn tối thiểu 3 năm. Riêng đối với các dự án nhóm C ở vùng sâu, vùng xa thì các chức danh nêu trên có thể giao cho những người có trình độ cao đẳng hoặc trung cấp thuộc các chuyên ngành phù hợp.2. Đối với những dự án quy mô nhỏ, đơn giản có tổng mức đầu tư dưới 1 tỷ đồng thì chủ đầu tư có thể không thành lập Ban QLDA mà sử dụng các đơn vị chuyên môn của mình để quản lý dự án; trường hợp cần thiết có thể thuê người có chuyên môn, kinh nghiệm để giúp quản lý dự án.3. Ban QLDA được giải thể sau khi hoàn thành nhiệm vụ. II. TRƯỜNG HỢP CHỦ ĐẦU TƯ THUÊ TƯ VẤN QUẢN LÝ DỰ ÁN1. Khi áp dụng hình thức thuê tư vấn quản lý dự án thì nhà thầu tư vấn phải thành lập một tổ chức để trực tiếp thực hiện nhiệm vụ quản lý dự án theo hợp đồng đã ký với chủ đầu tư. Cơ cấu, thành phần của tổ chức này gồm có giám đốc tư vấn quản lý dự án, các phó giám đốc và các bộ phận chuyên môn, nghiệp vụ phù hợp với nhiệm vụ, quyền hạn theo hợp đồng mà nhà thầu tư vấn đã ký với chủ đầu tư. Giám đốc tư vấn quản lý dự án phải có đủ điều kiện năng lực theo quy định tại khoản 1 Điều 55 của Nghị định 16/CP. Các phó giám đốc và những người phụ trách chuyên môn, nghiệp vụ phải có trình độ đại học thuộc các chuyên ngành phù hợp và có thời gian làm việc chuyên môn tối thiểu 3 năm. Nhà thầu tư vấn quản lý dự án được thuê tổ chức, cá nhân tư vấn tham gia một số phần việc quản lý dự án, nhưng phải được chủ đầu tư chấp thuận và phù hợp với nhiệm vụ, quyền hạn trong hợp đồng đã ký với chủ đầu tư.2. Nhiệm vụ, quyền hạn của tổ chức tư vấn trực tiếp thực hiện quản lý dự án tại công trường do nhà thầu tư vấn giao bằng văn bản và phải được gửi cho chủ đầu tư để thông báo tới các nhà thầu có liên quan. III. TRÁCH NHIỆM CỦA CHỦ ĐẦU TƯ TRONG VIỆC QUẢN LÝ DỰ ÁN ĐẦU TƯ XÂY DỰNG CÔNG TRÌNH Chủ đầu tư có nhiệm vụ, quyền hạn theo quy định của pháp luật về xây dựng kể từ giai đoạn chuẩn bị dự án, thực hiện dự án và nghiệm thu bàn giao đưa công trình vào khai thác sử dụng. Đối với những nhiệm vụ, quyền hạn mà chủ đầu tư đã giao cho Ban QLDA (theo quyết định thành lập Ban QLDA) hoặc Tư vấn quản lý dự án (theo hợp đồng đã ký kết với nhà thầu tư vấn quản lý dự án) thì chủ đầu tư có trách nhiệm chỉ đạo, theo dõi, đôn đốc, kiểm tra việc thực hiện những nhiệm vụ, quyền hạn đó, đảm bảo dự án được thực hiện đúng nội dung và tiến độ đã được phê duyệt. Chủ đầu tư phải chịu trách nhiệm toàn diện về những công việc thuộc nhiệm vụ, quyền hạn của mình theo quy định của pháp luật, kể cả những công việc đã giao cho Ban QLDA hoặc nhà thầu tư vấn quản lý dự án.
-
Mục Phần IV
Phần IV
HƯỚNG DẪN VỀ XỬ LÝ CHUYỂN TIẾP
I. XỬ LÝ CHUYỂN TIẾP VỀ THỦ TỤC LẬP, THẨM ĐỊNH, PHÊ DUYỆT DỰ ÁN ĐẦU TƯ XÂY DỰNG CÔNG TRÌNH VÀ CÁC CÔNG VIỆC TIẾP THEO
1. Các dự án đầu tư xây dựng công trình đã được phê duyệt trước ngày Nghị định 16/CP có hiệu lực, nhưng chưa triển khai thực hiện hoặc đang thực hiện dở dang thì các thủ tục còn lại được thực hiện theo Nghị định 16/CP hoặc theo quy định trước ngày Nghị định 16/CP có hiệu lực do người quyết định đầu tư quyết định. Nếu người quyết định đầu tư đã lựa chọn thủ tục thực hiện các bước còn lại theo quy định trước ngày Nghị định 16/CP có hiệu lực thì tiếp tục thực hiện theo các quy định đó; nếu đã lựa chọn thủ tục thực hiện các bước còn lại theo quy định của Nghị định 16/CP thì việc chuyển tiếp sang thực hiện Nghị định 112/CP theo hướng dẫn tại điểm 2 mục này.
2. Trước ngày Nghị định 112/CP có hiệu lực, các dự án đầu tư xây dựng công trình chưa được phê duyệt, nhưng đã có kết quả thẩm định dự án và các dự án đầu tư xây dựng công trình đã được phê duyệt nhưng chưa triển khai thực hiện hoặc đang thực hiện dở dang thì không phải làm lại thủ tục. Các thủ tục còn lại được thực hiện theo quy định của Nghị định 16/CP và các nội dung sửa đổi, bổ sung tại Nghị định 112/CP và hướng dẫn của Thông tư này.
Trong quá trình thực hiện dự án, trường hợp có sự điều chỉnh dự án làm thay đổi thiết kế cơ sở thì thẩm quyền thẩm định phần thiết kế cơ sở thay đổi được thực hiện theo quy định của Nghị định 112/CP.
II. XỬ LÝ CHUYỂN TIẾP VỀ CẤP GIẤY PHÉP XÂY DỰNG
1. Các công trình xây dựng đã được quyết định đầu tư và thuộc đối tượng không phải xin giấy phép xây dựng theo quy định của Nghị định 16/CP, nhưng đã khởi công xây dựng trước ngày Nghị định 112/CP có hiệu lực thì không phải xin giấy phép xây dựng. 2. Trường hợp dự án gồm nhiều công trình đã được quyết định đầu tư và đã có một số công trình được khởi công xây dựng trước ngày Nghị định 112/CP có hiệu lực, nếu chủ đầu tư làm thủ tục xin cấp giấy phép xây dựng một lần cho tất cả các công trình thuộc dự án thì thực hiện theo hướng dẫn tại điểm 4 mục I và điểm 3 mục II phần II Thông tư này, trong đó kê khai cả những công trình đã khởi công. Cơ quan cấp giấy phép xây dựng kiểm tra việc tuân thủ các quy định của pháp luật đối với những công trình đã khởi công trước khi ghi nhận vào nội dung giấy phép xây dựng.
3. Các công trình thuộc dự án đầu tư xây dựng đã được phê duyệt trước ngày Nghị định 112/CP có hiệu lực nhưng chưa được khởi công xây dựng thì trước khi khởi công xây dựng phải xin giấy phép xây dựng theo quy định của Nghị định 112/CP và hướng dẫn tại Thông tư này trừ những công trình không phải xin giấy phép xây dựng quy định tại điểm 2 mục I phần II của Thông tư này. III. XỬ LÝ CHUYỂN TIẾP VỀ TỔ CHỨC QUẢN LÝ DỰ ÁN
1. Đối với các Ban QLDA đã được giao làm chủ đầu tư thì phải được xử lý kịp thời theo quy định của pháp luật hiện hành đảm bảo nguyên tắc Ban QLDA do chủ đầu tư thành lập, giao nhiệm vụ và kiểm tra thực hiện. 2. Đối với các Ban QLDA khu vực, Ban QLDA chuyên ngành do các Bộ, ngành, địa phương đã thành lập để quản lý nhiều dự án thì phải được chuyển đổi thành tổ chức tư vấn quản lý dự án chuyên nghiệp hoạt động theo quy định của pháp luật về doanh nghiệp hoặc giải thể. Trường hợp Ban QLDA được giao quản lý một hoặc nhiều dự án mà những dự án này được kết thúc trong năm 2007 thì các Ban QLDA được tồn tại nhưng phải củng cố, sắp xếp cho đủ năng lực để thực hiện nốt những nhiệm vụ còn lại. Sau khi dự án hoàn thành thì Ban QLDA phải được giải thể hoặc chuyển đổi hoạt động theo quy định của pháp luật về doanh nghiệp. -
Mục Phần V
1. Thông tư số 08/2005/TT-BXD ngày 06/05/2005 của Bộ Xây dựng hướng dẫn một số nội dung về lập, thẩm định, phê duyệt dự án đầu tư xây dựng công trình và xử lý chuyển tiếp thực hiện Nghị định số 16/2005/NĐ-CP ngày 07/02/2005 của Chính phủ.2. Thông tư số 09/2005/TT-BXD ngày 06/05/2005 của Bộ Xây dựng hướng dẫn một số nội dung về giấy phép xây dựng.3. Điểm 3.1 mục II về Ban QLDA của Thông tư số 12/2005/TT-BXD ngày 15/07/2005 của Bộ Xây dựng hướng dẫn một số nội dung về Quản lý chất lượng công trình xây dựng và điều kiện năng lực của tổ chức, cá nhân trong hoạt động xây dựng. II. HIỆU LỰC THI HÀNH1. Thông tư này có hiệu lực thi hành sau 15 ngày, kể từ ngày đăng Công báo. Những quy định trước đây về lập, thẩm định, phê duyệt dự án đầu tư xây dựng công trình; giấy phép xây dựng; tổ chức quản lý dự án đầu tư xây dựng công trình trái với hướng dẫn tại Thông tư này đều bãi bỏ.2. Trong quá trình thực hiện nếu có vướng mắc, tổ chức, cá nhân gửi ý kiến về Bộ Xây dựng để xem xét, giải quyết./.
Basis for the status
The publishing source records this status (code HHL) as of May 11, 2009.