Article 2. Order of planning implementation and investment capital source
Decision 84/2006/QĐ-TTg — Phê duyệt điều chỉnh, bổ sung Quy hoạch thuỷ lợi đồng bằng sông Cửu Long giai đoạn 2006 - 2010 và định hướng đến năm 2020
1. Basing themselves on the contents of this planning and the annual state budget balancing capability according to the provisions of the State Budget Law, the Agriculture and Rural Development Ministry, the People's Committees of the provinces and cities in the Mekong River delta and concerned ministries and branches shall set an order of priority and ensure synchronous and efficient investment. Concretely, they should implement the planning in the following order of priority:
a/ Uncompleted works being units of synchronous systems which should be completed as soon as possible for efficient operation;
b/ Urgent works and works of high efficiency in service of key programs on the region's socio-economic development;
c/ Works for protection of population in flooded areas and arterial roads where traffic and irrigation purposes are integrated;
d/ Works for protection of orchards;
e/ Works for delineation of boundaries between saltwater and freshwater areas and works in service of brackish water aquaculture;
f/ Works for flood water drainage, sea dikes and estuary dikes;
g/ Works for drainage of overflow floods in border areas in Dong Thap Muoi and Long Xuyen quadrangle;
h/ Axial canals for irrigation, drainage and soil improvement, other works, infield works.
2. Mechanism and estimated construction investment capital for irrigation projects and works in the Mekong River delta
a/ In the 2006-2010, the total investment capital is estimated at around VND 14,000 billion, of which VND 5,000 billion come from the central budget for investment in building of key works, source canals, axial/grade-I canals (see the list in Appendix I to this Decision); VND 6,000 billion from local budgets (for building of small-sized works and improvement of grade-II canals); VND 3,000 billion from people's contributions and other lawful capital sources, which shall be used for perfecting the infield canal and ditch system.
In the 2006-2010 period, investment capital shall be concentrated on completing uncompleted investment projects and works, which are truly urgent and may efficiently operate in localities, so that they will be put into operation and use as soon as possible according to objectives and schedules approved by competent authorities.
Investment capital sources: Annual state budget capital (central and local budgets, government bonds, ODA), contributions of population in areas benefiting from the planning and other lawful capital sources.
b/ The post-2010 period with orientations toward 2020
- To complete works for flood water drainage and saltwater control and axial canals for irrigation and drainage, which are left uncompleted from the previous period. To commence the construction of a number of large-sized works for saltwater control and freshwater retention downstream rivers of Cai Lon - Cai Be, Ham Luong, Vam Co, etc.
To build other irrigation works in service of fisheries in coastal areas and realize the rice cultivation-aquaculture models in freshwater ecological zones (see the list of planned works in Appendix II to this Decision).
- For the list of projects and works planned to be executed in the 2011-2015 period and up to 2020, an order of priority should be set and the structure of investment capital sources from the central budget, local budgets, capital sources mobilized from the population in areas benefiting from the planning, economic organizations and ODA resources for the planning implementation should be clearly determined.
Article 2, Decision 84/2006/QĐ-TTg