Article 28
Decree 84-CP — Quy định chi tiết việc thi hành Luật Dầu khí
The contractor shall have to return the prospected and explored area in accordance with the following provisions:
1. No less than 20% of the initial contractual area at the end of each phase.
2. All the remaining contractual area after the completion of the prospection and exploration period, excluding the areas reserved for the development of oil and gas fields, exploitation of oil and gas and areas which are being assessed.
The contractor may of his own free will return the area at any time in the prospection and exploration period. The areas which have been returned voluntarily shall be deducted from those to be obligatorily returned. However, the voluntary return of areas shall not reduce the contractor’s obligations written in the petroleum contract.
The returned areas must form simple geometrical figures.
Fixed works must be dismantled from the returned areas in accordance with provisions of Article 16 of this Decree.
Article 28, Decree 84-CP