Article 16
Decree 84-CP — Quy định chi tiết việc thi hành Luật Dầu khí
The Contractor shall have to work out programs and plans for the dismantlement of immovable works and submit them to the Vietnam Oil and Gas Corporation for approval. All costs for the dismantlement shall be borne by the Contractor and shall be accounted for in the costs for the recovery of oil and gas.
In cases where the Vietnam Oil and Gas Corporation conducts oil and gas activities by itself, it shall have to work out programs and plans for the dismantlement of the immovable works and submit them to the State management agency for approval.
The competent State management agency may request the concerned organization and/or individual to dismantle the whole or part of the immovable works.
Article 16, Decree 84-CP