Article 50. Risks and force majeure circumstances
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Risk means a danger likely to adversely affect the performance of a construction contract. A contract must indicate the responsibility of the parties to handle a risk upon its occurrence to each party and the responsibility of each party upon occurrence of a risk.
2. Force majeure circumstance means a risky event which is irresistible once it occurs and unforeseeable upon the signing of a construction contract, such as earthquake, storm, whirlwind. flood, tsunami, landslide, volcano eruption, war or epidemic outbreak.
3. When a party finds itself in a force majeure circumstance, it shall notify such in writing to the other party as soon as possible.
4. The parties shall agree in the contract on actions taken in response to force majeure circumstances, including notification of force majeure circumstances, identification of responsibilities of the parties for force majeure circumstances, termination of and payment for the construction contract in force majeure circumstances (if any).
Article 50, Decree 48/2010/NĐ-CP