Article 40. Termination of construction contracts
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Circumstances in which a construction contract may be terminated, the right to termination of contract, order and procedures for termination, and level of compensation for damage caused by termination must be agreed upon by the parties in the contract.
2. Each party has the right to terminate the contract without having to pay compensation for damage in the cases specified in Clauses 7 and 8 of this Article.
3. In case the performance of a contract has been already suspended but the breaching part still fails to remedy its fault during the period of time agreed upon by the parties without any plausible reason, the suspending party may terminate the contract.
4 In case any party unilaterally terminates the contract for a reason for which the odier party is not at fault, the contract-terminating party shall pay compensation for damage caused to the other party.
5. Before any party terminates the contract, it shall notify such in writing to the other party within a certain time limit which is agreed upon in the contract but must be at least twenty one (21) days, clearly stating the reason for termination. If the contract-terminating party fails to do so. causing damage to the other party, it shall pay compensation for damage caused to the latter.
6. A construction contract becomes invalid from the time of termination and the parties shall
complete contract liquidation procedures within a time limit which is agreed upon in the contract but must not exceed 45 days from the date of contract termination. Past that time limit, if any party fails to carry out contract liquidation procedures, the other party has the full right lo decide on the contract termination.
7. The principal may terminate the contract in the following cases:
a) The contractor goes bankrupt or transfers its contractual benefits to its creditor without the principal's consent.
b) The contractor refuses to perform jobs under the contract or fails lo perform jobs under the contract for 45 consecutive days, unless it is so permitted by the principal.
8. The contractor may terminate the contract in the following cases:
a) The principal goes bankrupt or is dissolved.
b) Jobs are suspended for 45 consecutive days due to the principal's fault, unless otherwise agreed upon by the parties.
c) The principal fails to pay to the contractor 45 days after the principal receives a complete and valid payment dossier, unless otherwise agreed upon by the parties.
9. Two (2) days after the date of termination of a construction contract, the contractor shall remove all supplies, workforce, machine, equipment and other assets under its ownership from the construction site. Past that time limit, if the contractor still fails to do so, the principal has the right to dispose of these assets.
Article 40, Decree 48/2010/NĐ-CP