Article 38. Adjustment of construction contract performance schedule
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. In a construction contract the parties shall agree on cases eligible for contract performance schedule adjustment. In case the date of contract performance completion is behind the set contract performance schedule, the contracting parties shall clearly identify the responsibility of each party for damage caused by the delay.
2. The contract performance schedule may be adjusted in the following cases:
a) An earthquake, storm, flood, tsunami, fire, enemy sabotage or another force majeure event occurs;
b) The scope of jobs, designs or construction measures change at the request of the principal, affecting the contract performance progress;
c) The construction ground is handed over not in accordance with agreements in the contract or related procedures slows down the construction contract performance but the contractor is not at fault.
3. In case the adjustment of the contract performance schedule will not extend the deadline for project completion, the investor and the contractor may agree on the adjustment. In case the adjustment will extend the project completion deadline, the investor shall report such to the investment decider for consideration and decision.
Article 38, Decree 48/2010/NĐ-CP