Article 26. Rights and obligations of the work construction principal
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Rights of the work construction principal:
a) To cease the construction of a work and request the remedying of consequences caused by the contractor's violation of regulations on work quality, labor safety, environmental protection and fire and explosion prevention and fighting;
b) To inspect the quality of performed jobs and products processed or manufactured by the contractor's establishments without impeding the contractor's normal operation;
c) Other rights provided by law.
2. Obligations of the work construction principal:
a) In case the principal is the investor, a construction license is required under regulations;
b)To hand over the construction site in whole or part by part to the contractor for management and use according to the set schedule and agreements ol the contract:
c) To assign its persons to participate in managing and performing the contract and notify in writing the contractor of these persons;
d) To promptly provide the engineering dossier and relevant documents and supplies (if any) as agreed upon in the contract and prescribed by relevant laws:
e) To pay to the contractor according to the payment schedule in the contract;
f) To supervise the work construction;
g) To inspect measures taken by the construction contractor to assure labor safety, environmental protection, fire and explosion prevention and fighting;
h )To conduct takeover test and make payment and settlement of the contract within the set time limit;
i) To clearly define tasks and powers of consultants in case of hiring organizations or individuals to provide consultancy services:
j) To promptly consider and approve in writing the contractor's proposals related to engineering and construction in the course of work construction:
k) Other obligations provided by law.
Article 26, Decree 48/2010/NĐ-CP