Article 22. Liquidation of construction contracts
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. A construction contract shall be liquidated in the following cases:
a) The parties fulfill their obligations under the signed contract;
b) It is terminated (cancelled) under law.
2. The liquidation of a contract shall be completed within forty five (45) days after the contracting parties fulfill their contractual obligations or the contract is terminated (cancelled) under Point b. Clause 1 of this Article. For big contracts, the contract liquidation shall be made within ninety (90) days.
Article 22, Decree 48/2010/NĐ-CP