Article 17. Construction contract advance payment
Decree 48/2010/NĐ-CP — Về hợp đồng trong hoạt động xây dựng
1. Construction contract advance payment means a sum of money advanced by the principal to the contractor for the performance of jobs under the contract.
2. Contract advance payment shall be made immediately after a construction contract takes effect and the principal receives the advance payment guarantee (if any).
3. The advance level, time of advance payment and retrieval of advances must be agreed upon by the parties in the contract.
4. The minimum advance level is prescribed
as follows:
a) For consultancy contracts, it is 25% of the contract price;
b) For work construction contracts, it is:
- 10% of the contract price, for contracts valued at over VND 50 billion:
- 15% of the contract price, for contracts valued at between VND 10 billion and 50 billion:
- 20%; of the contract price, for contracts valued at below VND 10 billion.
c) For equipment provision contracts, EPC contracts, turnkey contracts and other types of construction contracts, it is 10% of the contract price.
5. The maximum advance level is 50% of the contract price. In special cases, the maximum advance level shall be permitted by the investment decider.
6. Advance amounts shall be retrieved right at the first contract payment. The advance amount to be retrieved upon each payment shall be agreed upon by the contracting parties and indicated in the contract. The retrieval shall be completed when the paid value reaches 80% of the contract price.
The investor shall coordinate with the contractor in calculating an appropriate advance level and managing the use of advanced capital for proper purposes and objects and with efficiency. It is prohibited to leave advanced capital unused or use advanced capital for improper purposes. The investor shall retrieve advanced capital left unused or used for improper purposes.
7. In case of manufacturing components and
semi-finished products of large value for which
some materials must be seasonally stored, the principal and contractor shall agree on a plan on advance payment and advance level to assure contract performance progress.