Article 42
Decree 45/2001/NĐ-CP — Về hoạt động điện lực và sử dụng điện.
The electricity sellers shall have the duty:
1. To sell in adequate volume (capacity, electric energy), ensure stable quality (current, voltage) for the buyers according to the provisions in Article 31 of this Decree and the agreement in the contracts.
2. To make written notices and post up at electricity trading transaction places the relevant law provisions and the sellers stipulations, which the electricity buyers should know for joint implementation.
3. In case of electricity shut-off according to plans, to notify such to the electricity buyers at least 5 days before the time of electricity break in the following forms:
a) Sending written notices to organizations and individuals that use electricity for production activities and electricity users being organizations and individuals that have exclusive transformer stations;
b) Publishing announcements on the mass media for organizations and individuals using electricity for daily life.
4. To break off electricity strictly at the time already announced. In cases where the electricity buyers request the change of electricity-shut-off time, the buyers shall have to notify such to the sellers at least 48 hours before the time of electricity break. The electricity sellers shall have to consider and reasonably settle the request of the electricity buyers.
If the electricity shut-off cannot be delayed, the electricity sellers can shut-off the electricity according to plans but shall have to inform the buyers thereof at least 24 hours before the announced time of electricity shut-off.
Where the electricity seller agrees to change the time of or delay the electricity shut-off, the electricity buyers must be informed thereof 24 hours before the announced time of electricity shut-off, except for force majeure cases .
5. When electricity grid is hit by an incident, thus causing power failure or urgent electricity shut-off to handle dangerous circumstance, important organizations and individuals that use electricity in great volume must be promptly notified of such as of well as the expected time of electricity re-supply.
6. To handle the incident within 2 hours as from the time the electricity buyers report on power failure; where the incident cannot be overcome within the above-said time limit, the electricity sellers shall have to promptly inform the electricity buyers thereof.
7. To compensate the buyers for the damage caused by the sellers according to regulations and agreement in the contracts, except for force majeure cases.
8. To effect the signing of contracts and electricity sale as provided for in Article 27 and 28 of this Decree.
9. To reach agreement with owners when using the electricity projects of the buyers to supply electricity to other electricity users being organizations and individuals.
10. To submit to the examination and inspection by competent State bodies as provided for by law.
11. To fulfill other obligations as prescribed by law.
Article 42, Decree 45/2001/NĐ-CP