Article 53. Adjustment of contents of programs and projects and use of surplus funds during the program and project implementation
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Management of implementation of
1. For adjustments resulting in changes in the content of the investment policy decision, the managing agency shall comply with Article 21 of this Decree.
On the basis of a competent authority’s approval of changes in the content of the investment policy decision, the managing agency shall carry out procedures related to the appraisal and approval of the program or project document and adjustment of the program or project investment decision.
2. For adjustments to the content of a program or project resulting in amendment, supplementation or extension of a treaty or agreement on ODA or concessional loan, the agency that has proposed the conclusion of the treaty or agreement shall comply with the order and procedures prescribed in Articles 33 and 36 of this Decree.
3. The use of surplus funds (ODA and concessional loans) arising during the program or project implementation, including surplus fund after bidding, surplus fund due to changes of exchange rates, interest rates, unallocated provisional funds and other surplus funds, must comply with the following provisions:
a/ In case of using surplus funds within the scope of the program or project determined in the project investment decision and in conformity with the investment policy approval decision of a competent authority: After consulting the Ministry of Planning and Investment and the Ministry of Finance, the managing agency shall reach agreement with the foreign donor to decide on the use of surplus funds under current regulations;
b/ In case of using surplus funds for implementing a new program or project in order to promote the effectiveness of the ongoing program or project: The managing agency shall send a document enclosed with the investment policy proposal report for the new program or project to be funded by surplus funds to the Ministry of Planning and Investment and the Ministry of Finance. The Ministry of Planning and Investment shall assume the prime responsibility for, and coordinate with related agencies in, working with the foreign donor to reach agreement on the use of surplus funds. The subsequent steps relating to the submission and appraisal of, and decision on investment policy on, the new program or project must comply with Articles 14, 15, 16, 17 and 18 of this Decree.