Article 46
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Management of implementation of
Formulation and approval of overall plans for implementation of programs and projects funded by ODA or concessional loans and counterpart fund
1. An overall plan for program and project implementation shall be formulated for the entire implementation period of a program or project and must cover all components, items, activity groups and corresponding funding sources (ODA, concessional loan and counterpart fund) and its tentative implementation schedule.
2. Within 30 days after signing a specific treaty or an agreement on ODA or concessional loan, based on the approved program or project document, program or project investment decision, and the specific treaty or agreement on ODA or concessional loan for the program or project, the project owner shall work with the foreign donor in formulating or reviewing and updating the overall plan for program and project implementation, and submit it to the managing agency for consideration and approval.
3. For an umbrella program or project, an overall plan must consist of overall plans of component projects. The head of the managing agency of an umbrella program or project shall approve the overall plan of the umbrella program or project; the head of the managing agency of a component project shall approve the overall plan of the component project.
4. Within 5 working days after approving the overall plan for program or project implementation, the managing agency of such program or project, including also umbrella program or project, shall send the approval decision enclosed with such overall plan to the Ministry of Planning and Investment, related agencies and the foreign donor to serve the supervision, evaluation and coordinated implementation of the program or project.
Article 46, Decree 16/2016/NĐ-CP