Article 19. Activities to be carried out in advance
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Formulation and appraisal of, and decision on investment policy on, programs and projects
Managing agencies may carry out in advance the following activities in the stage of program or project implementation preparation:
1. After the investment policy is decided by a competent authority, the managing agency shall assign the unit that has proposed the program or project to:
a/ Design and submit a resettlement policy framework to competent authorities for approval in the course of appraisal of the program or project document and investment decision;
b/ Prepare a contractor selection plan; dossier of invitation of interests, dossier for prequalification, bidding dossier and dossier of requirements.
2. From the time investment in the program or project is decided by a competent authority to the time a specific treaty or an agreement on ODA or concessional loan for the program or project comes into effect, the managing agency shall:
a/ Appraise and approve the contractor selection plan, dossier of invitation of interests, dossier for prequalification, bidding dossier or dossier of requirements, organize the contractor selection, appraise and approve the contractor selection result, negotiate and finalize the contract for bidding packages of procurement and construction and installment for activities to be carried out in the first 12 months of the program or project and some bidding packages of consultancy (consultancy on project management, technical design, supervision, resettlement, environmental and social issues);
b/ Procurement, construction and installment and consultancy contracts of bidding packages specified at Point a of this Clause may be entered into only after a specific treaty or an agreement on ODA and concessional loan for the program or project comes into effect.
3. Funds for carrying out activities in advance shall be allocated by the project owner from funding sources for project preparation or advanced source and retrospectively settled with the project capital source based on the prior agreement of the foreign donor.
Article 19, Decree 16/2016/NĐ-CP