Article 15. Order and procedures for decision on investment policy on ODA or concessional loan-funded group-A projects
Decree 16/2016/NĐ-CP — Về quản lý và sử dụng vốn hỗ trợ phát triển chính thức (ODA) và vốn vay ưu đãi của các nhà tài trợ nước ngoài.
Formulation and appraisal of, and decision on investment policy on, programs and projects
1. The head of the managing agency shall:
a/ Based on Clause 3, Article 13 of this Decree, assign an attached unit to formulate a prefeasibility study report according to the form provided in Appendix IIIb to this Decree;
b/ Assign an attached unit with the appraising function or form a council to appraise the prefeasibility study report, ODA or concessional loan, counterpart fund and the ability to balance these funding sources;
c/ Direct the unit referred to at Point a of this Clause to finalize the prefeasibility study report based on the appraisal result before submitting it to the Prime Minister.
2. The provincial-level People’s Committee chairperson shall:
a/ Based on Clause 3, Article 13 of this Decree, assign an attached unit to formulate a prefeasibility study report according to the form provided in Appendix IIIb to this Decree;
b/ Form a council with a provincial-level People’s Committee vice chairperson as the head and the provincial-level Planning and Investment Department as the standing body and related departments and sectors as members to appraise the prefeasibility study report, ODA or concessional loan, counterpart fund and the ability to balance these funding sources;
c/ Direct the unit referred to at Point a of this Clause to finalize the prefeasibility study report based on the appraisal result prescribed at Point b of this Clause before reporting it to the provincial-level People’s Committee;
d/ Submitting the prefeasibility study report to the provincial-level People’s Council for opinion before submission to the Prime Minister.
3. The Prime Minister shall decide to form an intersectoral council to appraise, or assign an agency to take charge of appraisal, the prefeasibility study report at the proposal of the Ministry of Planning and Investment.
4. The Ministry of Planning and Investment shall assume the prime responsibility for, and coordinate with the Ministry of Finance and the State Bank of Vietnam (for loans provided by the World Bank, the Asian Development Bank, international financial and monetary institutions and other international banks for which the State Bank of Vietnam acts as a representative) in, appraising the ODA or concessional loan, counterpart fund and the ability to balance these funding sources and sending the appraisal result to the intersectoral appraisal council or the agency in charge of appraisal referred to in Clause 3 of this Article. The Ministry of Finance shall assume the prime responsibility for, and coordinate with the Ministry of Planning and Investment and related agencies in, giving opinions on the domestic financial mechanism and onlending method and sending them to the intersectoral appraisal council or the agency in charge of appraisal referred to in Clause 3 of this Article.
5. The intersectoral appraisal council or the agency in charge of appraisal referred to in Clause 3 of this Article shall send its appraisal opinion to the managing agency for finalizing the prefeasibility study report before submission to the Prime Minister.
6. The Prime Minister shall consider and decide on investment policy.
Article 15, Decree 16/2016/NĐ-CP