Article 2. Classification and State management of investment projects on the construction or works
Decree 16/2005/NĐ-CP — Về quản lý dự án đầu tư xây dựng công trình
1. Investment projects on the construction of works (hereinafter collectively called construction investment projects or projects) are classified as follows:
a/ By size and nature: important national projects in which investment is approved and permitted by the National Assembly; and other projects which are classified into three groups A, B and C as stipulated in Appendix 1 to this Decree;
b/ By investment capital source:
- Projects using state budget capital;
- Projects using credit capital underwritten by the State or development investment credit capital of the State;
- Projects using development investment capital of state enterprises;
- Projects using capital of other sources, including private capital or capital of mixed sources.
2. Investments in the construction of works must conform to the overall socio-economic development planning, branch plannings and construction plannings, ensure security, social safety and environmental safety as well as compliance with the provisions of land and other relevant legislation.
3. In addition to the provisions of Clause 2 of this Article, depending on the sources of capital used for projects, the State shall also perform its management according to the following provisions:
a/ For projects using state budget capital, including component projects, the State shall manage the entire process of investment and construction, from the identification of investment undertakings, project formulation, investment decision, making of designs and total cost estimates, selection of contractors, construction to the pre-acceptance test, hand-over and commission of works. Investment deciders shall have to arrange sufficient capital for projects according to their execution schedule which must be not more than 2 years for group-C projects and more than 4 years for group-B projects.
The management of projects using state budget capital shall be decided by competent state management agencies according to their decentralized competence in accordance with the provisions of legislation on state budget.
b/ For projects of enterprises using credit capital underwritten by the State, development investment credit capital of the State or development investment capital of state enterprises, the State shall only manage them in terms of investment undertakings and size. Enterprises having such projects shall take self-responsibility for organizing the execution and management of the projects in accordance with the provisions of this Decree and other relevant provisions of law.
c/ For projects using capital of other sources, including also private capital, investors shall decide by themselves on the form and contents of management of such projects. For projects using capital of mixed sources, the capital contributors shall agree upon the mode of management or manage such projects according to the regulations applicable to the capital source accounting for the biggest percentage % in the total investment amount.
4. For projects for which investment undertakings are approved by the National Assembly and group-A projects each consisting of many component projects, if each component project may independently operate or may be executed in different investment phases stated in the documents approving the investment reports, it shall be managed and executed like an independent project.
Article 2, Decree 16/2005/NĐ-CP