Article 12. Guarantee charges
Decree 15/2011/NĐ-CP — Về cấp và quản lý bảo lãnh chính phủ.
1. Based on the appraisal of financial plans of programs or projects and enterprises' financial situation, the Ministry of Finance shall set specific charge rates for each program or project depending on its risk level, which, however, must not exceed 1.5%)year of (he balance of the guaranteed debt. Guarantee charge rates arc specified in Appendix III to this Decree.
2. Guarantee charges shall he collected as follows:
a) A guarantee charge is set in the loan currency, calculated from the date of the first capital withdrawal and paid to the accumulation fund for debt payment under the Finance Ministry's guidance;
b) A guarantee charge i s collected on the date of interest payment for the guaranteed loan. At the request of the guaranteed, the guarantee charge during the loan's grace period may be collected when the project is commissioned, but at an interest rate equal to that of the guaranteed loan;
c) The guarantee charge shall be collected in the loan currency or in Vietnam dong at the selling rate announced by the Joint Stock Commercial Bank for Foreign Trade of Vietnam at the time of charge payment;
d) If the guarantee charge payment is delayed, the guaranteed shall bear an interest on the lately paid guarantee charge amount calculated on the number of days of delayed payment. The applicable interest rate is equal to that of the guaranteed loan or bond.
3. The Ministry of Finance may deduct 1.5% of the total collected guarantee charge amounts to offset expenses for the provision and management of government guarantee and expenses permitted by the Prime Minister.
Article 12, Decree 15/2011/NĐ-CP