Article 85
Decree 12/CP — Quy định chi tiết thi hành Luật Đầu tư nước ngoài tại Việt Nam
The technical design evaluation and construction decision is stipulated as follows:
1. The Ministry of Construction shall evaluate the technical designs of the structures belonging to Group A projects defined in Article 93 of this Decree. The provincial People’s Committee shall evaluate the technical design of the structures belonging to Group B projects defined in Article 93 of this Decree.
2. With regard to the structures belonging to Group A projects, within 20 days from the date of receipt of the dossier, the Ministry of Construction shall complete the evaluation of the technical design of the structure and notify the investor of its decision. After the technical design is approved, the investor may start building the structure.
3. With regard to the structures belonging to Group B projects, within 20 days from the date of receipt of the dossier, the provincial People’s Committee shall complete the evaluation of the technical design of the structure and notify the investor of its decision. After the technical design is approved, the investor may start building the structure.
4. After the aforesaid time limit of twenty days, if the design evaluating agency fails to notify the investor of its decision, the investor may still start building the structure.
5. Not later than 10 days before starting building the structure, the investor must notify the provincial People’s Committee of the locality where the structure is built of the building.
Article 85, Decree 12/CP