Article 9. Reservoir water regulation
Decree 112/2008/NĐ-CP — Về quản lý, bảo vệ, khai thác tổng hợp tài nguyên và môi trường các hồ chứa thuỷ điện, thuỷ lợi
1. A reservoir operating process must be established and submitted to competent authorities for approval before reservoir water collection. Such process must ensure all reservoir functions according to the priority order, work and reservoir lowlands safety. integrated exploitation of reservoir resources any environment and maintenance of the minimum flow in reservoir lowlands: not cause major changes to the reservoir's flow regime downstream and take into account climate change elements; conform with the inter-reservoir operating process in the river basin (if any) already approved by competent state agencies.
2. Dam owners shall conduct hydro-meteorological observation and collect hydro-meteorological information and data at their own expenses to meet requirements on reservoir protections; operation management and exploitation under the guidance of natural resources and environment state management agencies and submit annual reports to concerned line ministries and provincial-level People's Committees.
3. Dam owners shall annually formulate a water regulation plan for reservoirs and notify' People's Committees at all levels of the localities having reservoirs and reservoir lowlands areas in order to reduce adverse impacts on people's production and life and the environment.
4: Water regulation plans for reservoirs shall be formulated on the basis of the approved reservoir operating process, minimum flow requirements, forecasts on flow changes in the year by hydro-meteorological agencies and water use needs of branches, localities and economic organizations.
5. When concerned agencies, organizations and localities do not accept reservoir water regulation plans, they may request dam owners and competent state agencies to consider and decide on such plans.
Article 9, Decree 112/2008/NĐ-CP