Article 6
Decree 112/2008/NĐ-CP — Về quản lý, bảo vệ, khai thác tổng hợp tài nguyên và môi trường các hồ chứa thuỷ điện, thuỷ lợi
Formation of reservoir protection corridors Adam owner shall:
1. Assume the prime responsibility for. and coordinate with the provincial-level Natural Resources and Environment Service, district- and commune-level People's Committees of the locality where the reservoir is located in, formulating a scheme to place reservoir protection corridor boundary markers and submit it for approval to the provincial-level People's Committee of the locality where the reservoir is located.
2. Assume the prime responsibility for, and coordinate with the district-and commune-level People's Committees of the locality where the reservoir is located in, placing markers on the field after the scheme to place reservoir protection corridor boundary markers is approved.
3. Hand over reservoir boundary markers to the commune-level People's Committee of the locality where the reservoir is located for management and protection; for new reservoirs, complete their boundary determination and handover of their boundary markers prior to the official operation of a reservoir; for operating reservoirs, complete such determination and handover within one year from the effective date of this Decree.
4. When reservoir protection corridors or reservoir zones are encroached, occupied or illegally used, promptly report to local administrations, and coordinate with them in handling according to law these violations.
Article 6, Decree 112/2008/NĐ-CP