Article 60. Management of foreign contractors
Decree 111/2006/NĐ-CP — Hướng dẫn thi hành Luật Đấu thầu và lựa chọn nhà thầu xây dựng theo Luật Xây dựng
1. After being selected for execution of bidding packages in the Vietnamese territory, foreign contractors must comply with the provisions of Vietnamese law on entry, exit, import and export of goods, temporary residence registration, accounting regime, taxes and relevant provisions of Vietnamese law, unless otherwise provided for by a treaty to which the Socialist Republic of Vietnam is a contracting party or by an international agreement which the competent agency or organization of the Socialist Republic of Vietnam has signed.
2. When performing contracts signed with investors in the Vietnamese territory, foreign contractors shall register their operations with the state agencies according to the provisions of this Article in order to be granted operation registration certificates.
3. A foreign contractor's dossier of registration for operation in Vietnam comprises:
a/ The operation registration paper made by the foreign contractor or a representative of the foreign contractor according to the form issued by the Ministry of Planning and Investment;
b/ A notarized copy of the written notice of contractor-selection results;
c/ A notarized copy of the passport of the contractor who is an individual; a notarized copy of the operation registration granted by the competent agency of the country or territory of which the contractor being an organization bears nationality (enclosed with a notarized Vietnamese or English translation of that registration).
4. The operation registration certificate, for foreign contractors granted such certificates free of charge.
5. The Planning and Investment Service of the province or centrally run city where the foreign contractor is based (hereinafter called the operation registering agency) shall receive and consider that contractor's dossier of registration for operation in Vietnam. Within 5 working days after receiving the complete and valid dossier prescribed in Clause 3 of this Article, the operation-registering agency shall grant operation registration certificate (made according to the form issued by the Ministry of Planning and Investment) to the foreign contractor. It shall concurrently notify the Planning and Investment Services of other localities of the operation registration by that contractor if the bidding package is to be executed in those localities.
When the operation-registering agency refuses to grant the certificate, it shall notify the concerned foreign contractor thereof in writing and state the reasons therefor.
6. An operation registration certificate becomes invalid in the following cases:
a/ The operation term indicated in that certificate expires;
b/ The foreign contractor is suspended from operation, dissolved or bankrupt under the provisions of Vietnamese law or the law of the country or territory of which that contractor bears nationality.
7. When the foreign contractor undertakes different bidding packages in the same duration, that contractor shall make only one dossier of registration for operation in Vietnam whereby the operation term lasts from the commencement of execution of the first bidding package till the accomplishment of the last bidding package.
8. When the foreign contractor has been granted by the operation-registering agency an operation registration certificate which remains valid, if that contractor continues to execute another bidding package in the same locality, that contractor is only required to supply updated information to the operation-registering agency in order to be granted an additional operation registration certificate (according to the form issued by the Ministry of Planning and Investment).
9. Foreign contractors winning bids in construction activities in Vietnam shall comply with the provisions of Clause 4, Article 7 of the Construction Law and the Prime Minister's Decision No. 87/2004/QD-TTg of May 19, 2004, promulgating the Regulation on management of operation of foreign contractors in construction in Vietnam without having to abide by the provisions of Clauses 1 thru 8 of this Article.
Article 60, Decree 111/2006/NĐ-CP