Article 57. Handling of bidding circumstances
Decree 111/2006/NĐ-CP — Hướng dẫn thi hành Luật Đấu thầu và lựa chọn nhà thầu xây dựng theo Luật Xây dựng
The bidding circumstances prescribed in Article 70 of the Bidding Law are handled as follows:
1. When it is necessary to adjust bidding package prices or contents, except for cases prescribed in Clause 6 of this Article, investors shall carry out procedures to adjust bidding plans according to the provisions of law before bid-opening time.
2. When cost estimates of bidding packages are lower than their approved prices, those cost estimates will substitute bidding-package prices to serve as a basis for consideration of contractor-selection results; when cost estimates of bidding packages are higher than their approved prices, investors shall report thereon in writing to investment deciders for consideration and decision of adjustment of bidding-package prices within the bidding plans in order to ensure legal grounds for consideration of contractor-selection results.
3. When by the bid-closing time less than 3 contractors have submitted bids, bid solicitors shall immediately report on the bidding process to investment deciders or the authorized persons for consideration and handling within no more than 2 hours so that the latter may permit the extension of bid-closing time to increase the number of bids or permit the opening and evaluation of submitted bids. When bids fall under the approving competence of the Prime Minister, these circumstances shall be handled by ministers, heads of ministerial-level agencies, heads of Government-attached agencies or heads of other central agencies, presidents of provincial-level People's Committees or chairmen of the managing boards of enterprises set up under decisions of the Prime Minister in relation to projects.
4. When bidding dossiers permit contractors to make offers for one or different parts of a bidding package, the evaluation of bids and consideration for approval of bid winners shall be conducted part by part but must ensure that the bid-winning prices of bidding packages does not exceed the approved prices of those bidding packages.
5. When bidding dossiers contain abnormal unit prices, which are unfavorable to bid solicitors, bid solicitors may request contractors to make written explanations and clarifications. If contractors' explanations are not clear enough, the abnormalities shall be considered flaws and must be adjusted under regulations as for redundant or deficient offers of bids, in line with the requirements of bidding dossiers according to the provisions of Article 28 of this Decree.
6. When the proposed bid-winning prices of contractors exceed the approved bidding-package prices, investors shall report them in writing to investment deciders or the authorized persons for consideration and decision to permit these contractors to offer other prices or together with the offer of new prices to reconsider the approved bidding-package prices and contents of bidding dossiers if necessary.
7. When only one bid passes the technical evaluation (for procurement, construction and installation bidding packages and bidding packages for selection of general construction contractors, except for those for selection of general engineering contractors), the determination of evaluation prices is not required but the proposed bid-winning prices must be determined to serve as a basis for consideration of bid-winning results.
8. When two bids gain the best evaluation results and are equal (in terms of points or evaluation prices), except for preferential cases prescribed in Clause 2, Article 4 of this Decree, the contractor that requests the lower bid-winning price shall be considered to win bidding.
9. When the proposed contract-conclusion prices exceed the approved bid-winning prices, investors shall report them in writing to investment deciders or authorized persons for consideration and decision.
10. When the bid-winning prices proposed by investors or appraising agencies are abnormally low or below fifty per cent (50%) of the approved bidding-package prices or cost estimates, before approving the bidding results, investment deciders or authorized persons may put forth appropriate measures such as setting up inter-branch appraising teams for more thorough appraisal of bids of contractors or other appropriate measures in contracts to ensure the feasible performance of those contracts.
In addition to the above-mentioned cases, when new circumstances arise, bid solicitors and investors shall report them to investment deciders or authorized persons for consideration and decision.
Article 57, Decree 111/2006/NĐ-CP