Article 23. Criteria for evaluation of bids for procurement bidding packages
Decree 111/2006/NĐ-CP — Hướng dẫn thi hành Luật Đấu thầu và lựa chọn nhà thầu xây dựng theo Luật Xây dựng
Criteria for evaluation of bids for procurement bidding packages include criteria for evaluation of contractors' capabilities and experience, criteria for technical evaluation and methods for determination of expenses on the same ground (evaluation prices). Specifically:
1. Criteria for evaluation of contractors' capabilities and experience, applicable to bidding packages not requiring pre-qualification, including:
a/ The experience on execution of similar bidding packages in Vietnam or in foreign countries; the major production or business experience;
b/ The production and business capabilities, material and technical foundations and professional qualifications of personnel;
c/ The financial capability: total assets, total payable debts, working capital, revenues, profits, value of contracts currently performed and other criteria.
The determination of specific requirements for each criterion provided for at Point a, b or c of this Clause shall be based on the requirements of each bidding package.
The "pass" or "fail" criterion may be used for evaluation prescribed in this Clause. Contractors that "pass" all the three contents mentioned at Points a, b and c of this Clause shall be evaluated as meeting the capability and experience requirements.
2. Technical evaluation criteria
Technical evaluation criteria are formulated according to the provisions of Article 22 of this Decree and cover contents on capabilities to meet quantitative and qualitative requirements for goods mentioned in a bidding dossier. Specifically:
a/ The characteristics and technical parameters of goods, production standards and other contents;
b/ The rationality and economic efficiency of technical solutions, measures for organization of goods supply;
c/ The equipment installation capability and qualifications of technical personnel;
d/ The extent of satisfaction of warranty requirements;
e/ The geographical adaptability;
f/ The environmental impacts and remedies;
g/ The financial capability (if required);
h/ Other factors regarding commercial and financial conditions, time for execution, training and technology transfer (if any).
3. Contents of determination of evaluation prices
Determination of evaluation prices means the determination of expenses on the same technical, financial and commercial grounds and other elements in order to compare and rank bids. Methods for determination of evaluation prices must be mentioned in the evaluation criteria. Evaluation prices are determined in the following order:
- Determining bidding prices;
- Correcting errors;
- Adjusting flaws;
Post-correction and -adjustment bidding prices are called the proposed requested bid-winning prices.
- Converting the proposed bid-wining prices to a common currency (if any) so as to have a basis for determination of evaluation prices;
- Calculating expenses on the same grounds for determination of evaluation prices, including:
+ Technical conditions such as the implementation schedule; the capacity and performance of machinery and equipment; the consumption of power, fuels and materials; the costs of operation and maintenance, the useful life of works and other technical elements, depending on specific requirements of each bidding package.
+ Financial and commercial conditions;
+ Preferences in international bidding (if any);
+ Other factors.
Factors for determination of evaluation prices shall be specified depending on the nature of each bidding package. Bids with the lowest evaluation prices shall be ranked first.
Article 23, Decree 111/2006/NĐ-CP