Article 21. Direct procurement
Law 61/2005/QH11 — Luật Đấu thầu số 61/2005/QH11
1. Direct procurement shall apply when contracts for the bidding packages with similar contents have been signed earlier for not more than six months.
2. In case of direct procurement, contractors that have earlier been selected through bidding for execution of bidding packages with similar contents may be invited.
3. Unit prices for contents of bidding packages subject to direct procurement must not exceed those for corresponding contents of similar bidding packages for which contracts have been signed earlier.
4. Direct procurement may also apply for execution of similar bidding packages of the same project or other projects.
Article 21, Law 61/2005/QH11