Article 11. Electricity development investment
Law 28/2004/QH11 — Luật Điện lực số 28/2004/QH11
1. Electricity development investment must comply with electricity development plannings. Investment projects not yet included in the electricity development plannings shall be executed only when they are so permitted by authorities competent to approve the plannings.
2. The electricity project investors shall have to strictly comply with law provisions on investment, construction and environmental protection.
3. Units engaged in electricity generation, electricity transmission and/or electricity distribution shall have to invest in the construction of transformer stations, electricity meters and electric conductors to electricity meters for electricity sale.
4. Organizations or individuals that build or renovate, expand electricity works must use modern technical equipment and technologies suitable to the branch regulations and standards as well as Vietnamese standards set by competent state bodies.
5. The Industry Ministry and the provincial-level People’s Committees shall publicize lists of electricity projects calling for investment in each period and the licensed investment projects.