Mục SCHEDULE 4
Thông báo 24/2020/TB-LPQT — Về việc điều ước quốc tế có hiệu lực: "Hiệp định vay (Các nghiệp vụ thông thường [Ưu đãi] cho Dự án Nâng cao hiệu quả sử dụng nước cho các tỉnh bị ảnh hưởng bởi hạn hán giữa nước Cộng hòa xã hội chủ nghĩa Việt Nam và Ngân hàng Phát triển Châu Á [3745-VIE (COL)]".
1. The procurement of Goods, Works and Consulting Services shall be subject to and governed by the Procurement Guidelines, and the Consulting Guidelines, respectively. 2. Except as ADB may otherwise agree, Goods and Works shall be procured and Consulting Services shall be selected and engaged only on the basis of the procurement methods and the selection methods set forth below. These methods are subject to, among other things, the detailed arrangements and threshold values set forth in the Procurement Plan. The Borrower may only modify the procurement methods and the selection methods or threshold values with the prior agreement of ADB, and modifications must be set out in updates to the Procurement Plan.
3. All terms used in this Schedule and not otherwise defined in this Loan Agreement have the meanings provided in the Procurement Guidelines and/or the Consulting Guidelines, as applicable. Eligible Source of Procurement of Goods, Works and Consulting Services
4. Goods, Works and Consulting Services may also be procured under the Project from non-member countries of ADB. Goods and Works
5. Goods and Works shall be procured on the basis of the procurement methods set forth below: (a) International Competitive Bidding; and (b) National Competitive Bidding. National Competitive Bidding 6. The Borrower and ADB shall ensure that, prior to the commencement of any procurement activity under national competitive bidding, the Borrower's national competitive bidding procedures are consistent with the Procurement Guidelines. Any modifications or clarifications to such procedures agreed between the Borrower and ADB shall be set out in the Procurement Plan. Any subsequent change to the agreed modifications and clarifications shall become effective only after approval of such change by the Borrower and ADB. Conditions for Award of Contract
7. The Borrower shall not, and shall ensure that each Participating PPC does not, award any Works contract which involves environmental impacts until: (a) ADB has granted the final approval of the updated EMP, which is prepared based on the relevant Subproject's detailed design; and (b) the Participating PPC has incorporated the relevant provisions from the updated EMP into the relevant Works contract.
8. The Borrower shall not, and shall ensure that each Participating PPC does not, award any Works contract which involves land acquisition and/or involuntary resettlement impacts, and/or impacts on ethnic minorities, until the relevant Participating PPC has prepared and submitted to ADB the final REMDP based on the relevant Subproject's detailed design, and obtained ADB's clearance of such REMDP. Consulting Services
9. Except as set forth in the paragraph below, the Borrower shall apply Quality- and Cost-Based Selection for Consulting Services.
10. The Borrower shall apply the following selection methods for the specified Consulting Services, in accordance with, among other things, the procedures set forth in the Procurement Plan: (a) Fixed Budget Selection; (b) Consultants' Qualifications Selection; and (c) Single Source Selection. Industrial or Intellectual Property Rights
11. (a) The Borrower shall ensure that all Goods and Works procured (including without limitation all computer hardware, software and systems, whether separately procured or incorporated within other goods and services procured) do not violate or infringe any industrial property or intellectual property right or claim of any third party. (b) The Borrower shall ensure that all contracts for the procurement of Goods and Works contain appropriate representations, warranties and, if appropriate, indemnities from the contractor or supplier with respect to the matters referred to in subparagraph (a) of this paragraph.
12. The Borrower shall ensure that all ADB-financed contracts with consultants contain appropriate representations, warranties and, if appropriate, indemnities from the consultants to ensure that the Consulting Services provided do not violate or infringe any industrial property or intellectual property right or claim of any third party. ADB's Review of Procurement Decisions
13. Contracts procured under international competitive bidding procedures and contracts for Consulting Services shall be subject to prior review by ADB, unless otherwise agreed between the Borrower and ADB and set forth in the Procurement Plan.
Trích dẫn:
Mục SCHEDULE 4 Thông báo 24/2020/TB-LPQT
Nguồn
congbao.chinhphu.vn